The Buildout
Everything expanding Australia's data centre footprint in one running list: campuses, land, power, and the fibre that connects them.

CDC expands Kemps Creek data centre plan to 1.4GW campus
CDC has expanded its Kemps Creek data centre at 845-901 Mamre Road from one building to a six-building campus with about 1GW of computing capacity.

Outback AI data centre drops 2028 start as NT EPA orders EIS
Energy North has dropped Project Ares' June 2028 start date after the NT EPA ordered an EIS and suspended its assessment deadline to seek Canberra's advice.

Stockland's Brooklyn data centre tops Victoria's A$5bn queue
Nine Melbourne data centre proposals worth over A$5 billion await a decision before caretaker begins on 3 November. Stockland's 250MVA Brooklyn plan leads them.

Approval waits put the 3.9GW data centre forecast at risk
Data Centres Australia and DC Byte forecast 3.9GW by 2030. Approvals and grid connection take about two years, and new capacity has been coming online at about 0.2 to 0.3GW a year.

Dover's 200MW South Morang data centre awaits a federal ruling
Dover DC's second South Morang data centre now waits on a federal environment decision. The up to 200MW data centre sits beside AusNet's terminal station, and ASX-listed CVC owns 30 per cent.

Recycled water pipeline to cool NEXTDC's S4 Sydney
NEXTDC's S4 Sydney will be cooled with up to 16 million litres of recycled water a day through coNEXA's new pipeline, after S7 and M4 were designed to run dry.

NEXTDC drops recycled water at its M4 Melbourne campus
NEXTDC's paused A$2bn M4 campus in Port Melbourne is now designed for closed-loop, air-cooled technology using no water, after recycled water was not viable, the operator told The Australian.

AirTrunk raises A$4.25 billion and plans A$75 billion more in Australia
AirTrunk raised A$4.25 billion from 32 lenders for SYD3 in Western Sydney, and plans a further A$75 billion of investment over the next decade.

Plan for a 1GW data centre south of Broome opens for comment
Gingerah Energy's Project Meridien pairs 6,700MW of solar and wind with up to 1GW of data centre load on Karajarri Country south of Broome. Comments close on 4 November 2026.

Zerra's rainwater plan for Anthropic's Dalby data centre
Zerra says its Western Downs campus can run on roof rainwater through drought. Bureau of Meteorology records show the roof would meet the first building's need in Dalby's driest year since 1992, with storage covering a dry half-year.

GreenSquare turns a 1995 Sydney data centre into an AI facility
GreenSquare has opened the 15MW first stage of SYD1, a 1995 Sydney data centre redeveloped for AI in eight months. Chief executive Charles Penny explains how.

DigiCo signs 71MW, 15-year contract at Sydney's SYD1
DigiCo has signed a 15-year, 71MW contract at its SYD1 data centre in Ultimo with an unnamed global technology firm, leaving the site fully contracted.

IREN plans 900MW Redbank data centre at Wagga Wagga
IREN's 900MW Redbank campus near Wagga Wagga, costing more than A$10bn, is the second large data centre proposed near the city in a month, after CDC Data Centres' 1.4GW plan, with a grid connection targeted for 2029.

SUBCO to build SM-1, an 850km Sydney to Melbourne fibre route
SUBCO said on 13 October it will build SM-1, an 850km land fibre route from Sydney to Melbourne with at least 96 fibre pairs, five years after Bevan Slattery's HyperOne planned a land link.

Goodman seeks a tenant for its Eastern Creek data centre site
Goodman is looking for a tenant from early 2027 at the Eastern Creek warehouse earmarked for its A$5bn Project Atlas, as it waits on a Transgrid connection date.

CDC's 576MW Canberra data centre heads to full environmental review
CDC's proposed 576MW Hume Campus 3 data centre in Canberra needs a full environmental impact statement, the ACT Conservator has ruled, citing 30 large trees on the site.

Microsoft's Huntingwood approval requires NSW renewables matched at all times
NSW approved Microsoft's 96MW Huntingwood data centre with NSW renewables matched to demand at all times, a month after Microsoft asked senators to count earlier deals.

Stockland wins 49MW Macquarie Park consent under new NSW rules
Stockland's A$630 million, 49MW Road 1 Data Centre at Macquarie Park won NSW consent on 1 October 2026, with renewable supply and efficiency reporting conditions from the August 2026 NSW data centre guidelines.

CDC wins ACT approval for its 84MW Beard 2 data centre in Canberra
The ACT approved CDC's A$203.5 million Beard 2 data centre on 29 September 2026, clearing an 84MW second building on its campus in Canberra's east, 40 days after the application went in.

Anthropic is in advanced talks for AirTrunk's Kurri Kurri campus
Anthropic is in advanced talks to anchor AirTrunk's 540MW campus on a former Hunter smelter site, the AFR reports, after its first lease at Kogan in Queensland.

CDC plans a 1.4GW, A$15bn data centre campus at Wagga Wagga
CDC's A$15bn campus at Wagga Wagga would add up to 1.4GW in regional NSW, close to the roughly 1.5GW of data centres operating across Australia.

CDC lodges plans for an 84MW second data centre in Canberra
CDC has applied to build Beard 2, an 84MW, A$200 million data centre in Canberra, reported on 9 September 2026 as the ACT prepares a draft Data Centre Framework for early 2027.

Australian data centre capacity: the 2026 to 2030 guide
Australia has about 1.6GW of data centre capacity running and a 3.9GW forecast for 2030. Every project with an opening date, by year and by state.

Amazon's A$2.17bn Glendenning data centre wins NSW approval
Amazon won NSW approval on 14 September 2026 for a A$2.17 billion, 193.6MW data centre campus at Glendenning in Blacktown, to be built in three stages.

Queensland wins Anthropic's first Australian data centre lease
Crisafulli courted Anthropic in California on 3 September. Thirteen days later the Financial Review reports the company leasing at Zerra's Western Downs campus.

Where in WA can an AI data centre be built?
Roger Cook says developers want WA's Mid West and Pilbara for land and power. Fibre reaches both. A 150MW Perth campus was approved as warehouses.

NSW approves Goodman's A$1.365bn Project Apollo at Macquarie Park
Goodman's A$1.365 billion, 135MW Project Apollo at Macquarie Park is the first new data centre New South Wales has approved since its 17 August guidelines, and the consent carries them as conditions.

Where in Queensland can an AI data centre actually be built?
Six locations where Queensland data centres are being proposed, scored on land, power, connectivity, water and workforce. Only Ipswich meets all five.

Melbourne gets a trans-Tasman cable, landing at Torquay
Datagrid has signed ASN and OMS Group to build the 2,300km Tasman Ring cable from Invercargill to Torquay, with service into Melbourne targeted for 2029.

AEMO's data centre queue hits 9GW as South Australia joins
AEMO's June quarter report counts 17 data centre projects and 9GW of grid connection capacity, up from 5.4GW in March, with South Australia now holding 17%.

NSW approves Goodman's A$1.11bn Project Pluto data centre
NSW has approved Goodman's A$1.11 billion, 68MW Project Pluto campus at Guildford West, its second Sydney data centre approval this year on a site once slated for warehouses.

Melbourne's data centre pipeline breaks out of the west
Applications at Mickleham, Truganina, Campbellfield and Clyde North put four campuses into Victoria's planning system, with about A$5 billion reported across the two costed sites.

Macquarie Technology’s road to 200MW
Macquarie Technology Group has secured a 34,200sqm Macquarie Park site for a proposed 200MW data centre campus it has costed at up to A$3 billion to build.

Google and Telstra join forces to power Australia’s AI connectivity
Telstra and Google have agreed to rent capacity on each other’s networks. The deal stitches Australia’s terrestrial backbone to three transpacific cables, and it sharpens the country’s role as a regional hub for AI traffic.

Mulwala Solar Farm nears grid connection: the Google and AirTrunk hyperscaler PPA explained
The 31MW Mulwala Solar Farm in the New South Wales Riverina is nearing grid connection. 25MW of that output is contracted to Google under a 2023 power purchase agreement signed with AirTrunk. The deal is the clearest Australian example to date of hyperscale data centre demand bringing a new-build solar project onto the National Electricity Market.