    CDC expands Kemps Creek data centre plan to 1.4GW campus

    By Winston Su, Editor · · Add us as a preferred source on Google

    CDC expands Kemps Creek data centre plan to 1.4GW campus
    CDC has expanded its Kemps Creek data centre at 845-901 Mamre Road from one building to a six-building campus with about 1GW of computing capacity.

    At a glance

    • CDC Data Centres has expanded its Kemps Creek data centre plan at 845-901 Mamre Road from one building in July to a six-building campus.

    • The campus is rated at about 1.4GW at peak, of which about 1GW is computing capacity, twice the 504MW approved at CDC's Marsden Park campus in November 2025.

    • CDC says the campus responds to growing demand for hyperscale data centres for cloud computing.

    • It wants all six buildings approved in one application, with one substation and grid connection, after Penrith City Council said it preferred one plan for the whole site.

    • The first stage would be three buildings with 504MW of computing capacity, though CDC says the staging is not finalised.

     

    CDC Data Centres has expanded its plans at Kemps Creek in Sydney's west from one building to a six-building campus with about 1GW of computing capacity. CDC says the expansion responds to growing demand for hyperscale data centres for cloud computing.

    CDC set out the change in an addendum to its scoping report for state significant development application SSD-133677993, prepared by planning consultancy Willowtree Planning and dated 2 October 2026. It wants the whole campus assessed and approved at once, so that one substation, one grid connection and one road layout can be planned for all six buildings rather than built up one application at a time. The addendum rates the campus at about 1.4GW at peak, about 1GW of it computing capacity and the rest cooling and supporting plant. The 1,008MW of computing capacity in the addendum's indicative schedule is twice the 504MW of IT load approved at CDC's Marsden Park campus in Sydney's north-west in November 2025.

    Map of CDC Data Centres campuses in Western Sydney: the expanded CDC Kemps Creek campus at 845-901 Mamre Road with 1,008MW of IT capacity across KC1 to KC6, CDC Eastern Creek and CDC Marsden Park, with AirTrunk/ISPT, Stockland and Microsoft at Kemps Creek, NEXTDC S4 and S7, AirTrunk SYD3, the M4, M7 and M12 motorways and Western Sydney International Airport.

     

    CDC's six Kemps Creek buildings would hold 1,008MW of IT capacity

    The plan places six two-storey data centres, KC1 to KC6, on the industrial-zoned part of the site, with an administration building, three security gatehouses and one substation. IT capacity is the power available to run servers. KC6 is the largest building, at 240MW across seven data halls.

    Building

    Data halls

    IT capacity

    KC1

    5

    168MW

    KC2

    5

    168MW

    KC3

    5

    168MW

    KC4

    4

    144MW

    KC5

    3

    120MW

    KC6

    7

    240MW

    Total

    29

    1,008MW

    Source: Willowtree Planning for CDC Data Centres, Scoping Report Addendum, indicative data centre schedule, SSD-133677993, 2 October 2026.

    CDC is considering building KC1, KC2 and KC3 first, with the substation, the administration building and a temporary car park, followed by KC4 to KC6, though the addendum says the staging is not finalised. On the indicative schedule, that first stage would hold 504MW of IT capacity, the same as the Marsden Park approval.

    Splitting the campus into two-storey buildings cuts the maximum height from 35.2 metres in the July plan to 25.5 metres. That is still above the 20-metre limit in the Mamre Road Precinct development control plan, the planning rules for the area, and the department asked CDC in August to give strong consideration to meeting it.

    CDC will plan the whole campus in one application

    CDC's July request for assessment requirements, lodged on 14 July 2026, proposed one four-storey building, KC1, rated at about 144MW at 859-901 Mamre Road. It put the development cost at A$1.8 billion excluding GST, with 510 construction jobs and 280 operational jobs, and the remaining lots were to follow in separate applications. The planning department issued the requirements on 10 August 2026.

    Penrith City Council's advice on that request noted several other proposed data centres in the Mamre Road Precinct, part of the cluster of data centres in Western Sydney around Eastern Creek, Erskine Park and Kemps Creek. It said it preferred a comprehensive concept plan for the whole site, particularly as more data centres were intended on the land. The addendum says the single application responds to that advice, so the campus's cumulative noise, air quality, traffic, visual and infrastructure impacts are assessed together, and avoids duplicating substations and supporting infrastructure across separate developments.

    CDC has gone a step further than the concept plan the council described. A concept application sets the layout and leaves each building to a later approval, while the addendum currently frames CDC's as a detailed application for the whole campus, to be constructed and operated, so a single consent would cover all six buildings.

    Other proposals in the precinct include a 1,000MW campus that AirTrunk and ISPT plan at 706-752 Mamre Road, and Stockland's planned Kemps Creek data centre. Microsoft has one data centre building operating at Kemps Creek and a second under construction.

    To fit the campus, CDC has added Lot 29 at 845-857 Mamre Road, a 29.14-hectare lot to the north. That takes the site from 88.33 hectares to 117.47 hectares. CDC also proposes removing a planned collector road through the middle of the site and widening the road on its western edge to carry that traffic, so the campus sits on one continuous block. A separate development application to Penrith City Council, DA25/0034, covers earthworks, roads and subdivision on the original four lots, and the addendum expects a decision in November 2026.

    The 1.4GW is CDC's peak design load

    The addendum describes the 1.4GW as the maximum design capacity of the campus, made up of about 1GW of IT load and about 0.4GW for cooling and all other supporting infrastructure under peak design conditions, and says it is not an annualised operating figure. At peak, total load is about 1.4 times IT load. CDC's Marsden Park consent, by comparison, allows a maximum power consumption of 720MW against its 504MW of IT load, and CDC has set out plans to lift that campus to 743.5MW.

    The August requirements for the single building require CDC to show it can reach a power usage effectiveness (total power divided by IT power) of 1.3 or less, and at least five stars under NABERS, the national building energy rating scheme. They also require a commitment to match operational electricity demand with NSW-based renewable supply at all times. The addendum says the environmental impact statement would meet the same tests for the full campus, with power usage effectiveness measured over a year rather than at peak. On 31 August 2026 the department added a requirement to address the performance measures in the NSW data centre guidelines, released on 17 August.

    CDC seeks one Transgrid connection for all six buildings

    Power for the campus would come through a high-voltage connection to the network of NSW transmission owner Transgrid, via an on-site switching station and substation. CDC has asked that the amended requirements cover the grid connection for the full campus, including the switching station, network capacity and the staging of electricity supply, prepared with Transgrid. Under Transgrid's rules for allocating data centre capacity, that capacity would be held provisionally for the campus once CDC signs a connection contract, and confirmed only if CDC meets Transgrid's conditions within three months.

    A 70-metre transmission line easement crosses the rear of the landholding, and all buildings and the realigned road sit outside it.

    On site, cooling would use an air-cooled, closed-loop system designed to keep operational water use low, with water demand to be quantified in the environmental impact statement. CDC met Sydney Water on 30 September 2026, the month the utility opened its Badu Yarragul plant at Kemps Creek, which it has said could supply recycled water to Western Sydney data centres.

    Six buildings also need substantially more backup diesel generators and fuel storage than one. On the July plan, the NSW Environment Protection Authority advised that the single building did not appear to need an environment protection licence, the permit required above set pollution thresholds. The environmental impact statement will recheck that threshold for the campus across all generator use, including testing, maintenance and emergencies.

    Investment and jobs grow with the larger campus

    The addendum says the campus is a substantially greater investment than the A$1.8 billion single building and that the number of jobs will rise significantly. The department's August letter requires an estimated development cost report to accompany the application.

    Kemps Creek would be CDC's third campus in Western Sydney, after Eastern Creek and Marsden Park. CDC's New South Wales page lists more than 200MW at Eastern Creek. All three are on the Sydney data centre map.

    Outside Sydney, CDC proposed a campus of up to 1.4GW at Wagga Wagga in the NSW Riverina in September 2026, and its other sites are in the directory of Australian data centres.

    What to watch

    The amended requirements. The department will decide whether to amend the assessment requirements to cover the six-building campus, including CDC's requested additions on the grid connection, the realigned road and the council application.

    The council decision. Penrith City Council's determination of DA25/0034, expected in November 2026, will set the earthworks, roads and subdivision on four of the five lots.

    Building height. CDC says the environmental impact statement will address the 20-metre height control against the 25.5 metres proposed.

    The environmental impact statement. It will quantify the campus's water demand and recheck the licence threshold across all generator use, and the application must carry an estimated development cost report.

    Marsden Park. CDC expects its modification to lift its other Western Sydney campus to 743.5MW to go to public comment in late 2026.

    Share this article

    Keep reading the market

    Get The Strategic Brief in your inbox every Thursday.

    The leading Australian data centre and AI infrastructure newsletter.

    One email a week. Unsubscribe in one click.

    Your Next Read

    Latest Headlines

    Interested in reaching this audience? Advertise with us.