Australian data centre operator profile covering CDC sites, Certified Strategic Facilities, ownership and latest coverage.
Listed majority shareholder; CDC itself is privately held.
Profile summary
Ownership Infratil, the Future Fund, Commonwealth Superannuation Corporation and management (privately held; Infratil is the listed major shareholder) · HQ Canberra · Founded 2007 · Founder and CEO Greg Boorer · Certified Strategic 12 Facilities · Australian sites 23 · Contracted capacity 1.1GW · Independent valuation A$18.45bn (Infratil, 30 September 2026).
Operating capacity
550MW
Leasable, 30 September 2026 (Infratil); 810MW under construction; Australia and New Zealand together
Contracted capacity
1.1GW
30 September 2026, up 70MW in the quarter (Infratil)
Overview
Canberra Data Centres is a privately held Australian data centre operator headquartered in Canberra. It is owned by Infratil, the Future Fund, the Commonwealth Superannuation Corporation and management. Infratil, the largest shareholder, is listed on the ASX and NZX.
CDC runs campuses in Canberra, Sydney and Melbourne and is building more. Under construction: Marsden Park in Sydney (504MW approved on 27 November 2025, in the early stages of construction; NSW is assessing a change that replaces one planned data centre building with a two-storey administration building, offices and a 5MW data hall, adds a level to two others and redistributes the load), Laverton in Melbourne (over 400MW when complete), Brooklyn in Melbourne (over 350MW on completion, with BK1 operational) and Maddington in Perth, where the development application is approved, the outside of the first of four planned buildings is nearly finished, interior fit-out is under way and operations are due in January 2027. CDC's Perth figure is over 200MW when complete, and a second Perth site at Hazelmere is proposed. In Sydney's west, CDC is planning a six-building campus at 845-901 Mamre Road, Kemps Creek (state significant development SSD-133677993). A planning document dated 2 October 2026 puts it at about 1GW of IT capacity, 1,008MW across buildings KC1 to KC6, and about 1.4GW of total power consumption including cooling and supporting infrastructure, up from a single 144MW building in the July 2026 scoping report. CDC has asked the NSW Planning Secretary to update the assessment requirements for the larger campus, ahead of preparing an environmental impact statement. Capital Brief reported on 4 November 2026 that CDC is consulting on lifting Marsden Park from 504MW to 743.5MW without changing the site's footprint, according to a project update sent to local residents.
In Canberra, the ACT approved CDC's 84MW Beard 2 data centre on 29 September 2026, a three-storey building with 12 data halls and works costed at A$203.5 million. 84MW is the total capacity of the 12 halls, and no start or finish date has been published. CDC's proposed Hume Campus 3, four data centres with 24 data halls and 576MW on preliminary plans, needs a full environmental impact statement, the ACT Conservator of Flora and Fauna ruled; CDC says the project remains at an early stage. In regional NSW, CDC has lodged a scoping report for a campus of up to 1.4GW near Wagga Wagga (Gregadoo), costed at about A$15 billion, which its Sydney and regional NSW page lists as "exploring". Wagga Wagga City Council, which owns the site, voted on 12 October 2026 to sell it to CDC on condition of a binding agreement for community benefits worth at least 1 per cent of the development cost, and on 13 October CDC offered a package worth up to A$225 million, subject to the project being approved and proceeding.
In October 2025 CDC agreed the 1.6GW Project Southgate rollout with Firmus and NVIDIA. CDC and Firmus agreed not to proceed with the rollout; about 42MW was deployed at Brooklyn.
Australian facilities
Live Supabase directory
View Canberra Data Centres in the Certified Strategic directoryBeard 1
Certification
Not certifiedScale band
Hyperscale
City
Canberra
State
ACT
BK1
Certification
Strategic FacilityScale band
Wholesale
City
Melbourne
State
VIC
BK2
Certification
Not certifiedScale band
Hyperscale
City
Melbourne
State
VIC
EC1
Certification
Strategic FacilityScale band
Hyperscale
City
Sydney
State
NSW
EC2
Certification
Strategic FacilityScale band
Hyperscale
City
Sydney
State
NSW
EC3
Certification
Strategic FacilityScale band
Hyperscale
City
Sydney
State
NSW
EC4
Certification
Strategic FacilityScale band
Hyperscale
City
Sydney
State
NSW
EC5
Certification
Not certifiedScale band
Hyperscale
City
Sydney
State
NSW
EC6
Certification
Not certifiedScale band
Hyperscale
City
Sydney
State
NSW
F1
Certification
Strategic FacilityScale band
Wholesale
City
Canberra
State
ACT
F2
Certification
Strategic FacilityScale band
Wholesale
City
Canberra
State
ACT
Gregadoo, Wagga Wagga
Certification
Not certifiedScale band
Hyperscale
City
Wagga Wagga
State
NSW
H1
Certification
Strategic FacilityScale band
Hyperscale
City
Canberra
State
ACT
H2
Certification
Strategic FacilityScale band
Hyperscale
City
Canberra
State
ACT
H3
Certification
Strategic FacilityScale band
Hyperscale
City
Canberra
State
ACT
H4
Certification
Strategic FacilityScale band
Hyperscale
City
Canberra
State
ACT
H5
Certification
Strategic FacilityScale band
Hyperscale
City
Canberra
State
ACT
Hazelmere
Certification
Not certifiedScale band
Directory pending
City
Perth
State
WA
HU6 (Hume 6)
Certification
Not certifiedScale band
Directory pending
City
Canberra
State
ACT
Kemps Creek
Certification
Not certifiedScale band
Directory pending
City
Sydney
State
NSW
Laverton
Certification
Not certifiedScale band
Directory pending
City
Melbourne
State
VIC
Maddington
Certification
Not certifiedScale band
Directory pending
City
Perth
State
WA
MP1
Certification
Not certifiedScale band
Hyperscale
City
Sydney
State
NSW
Pins are grouped by metro or region and sized by total tracked sites. States with at least one tracked site are tinted blue.
Latest coverage
20 Nov 2026
AirTrunk and Goodman at Lane Cove West and Stockland at Arncliffe dropped data centre plans before approval, while CDC expanded Kemps Creek to about 1.4GW.
13 Nov 2026
CDC has expanded its Kemps Creek data centre at 845-901 Mamre Road from one building to a six-building campus with about 1GW of computing capacity.
11 Nov 2026
CDC Data Centres plans to take its Marsden Park campus in western Sydney from 504MW to 743.5MW on the same land. The change now with the NSW planning department rebuilds the campus around two 144MW buildings.
28 Oct 2026
CDC Data Centres leads the October 2026 Power Rankings on contracted and approved capacity. NEXTDC is second and AirTrunk third.
Common questions
Canberra Data Centres, known as CDC, is a privately held Australian data centre operator headquartered in Canberra and founded in 2007, focused on government, defence and enterprise workloads.
CDC has 23 sites across Canberra, Sydney, Melbourne, Perth and Wagga Wagga, including Hume 6 (HU6), lodged with the ACT as development application 202443633. CDC is also building in Perth, at Maddington, where operations are due to start in January 2027.
Yes. CDC holds Certified Strategic Facility status at 12 sites under the Hosting Certification Framework, the Australian Government's highest certification tier.
CDC is privately held. Infratil holds 49.69 per cent at 30 September 2026. As at February 2025 the Australian Government's Future Fund held 34.55 per cent and the Commonwealth Superannuation Corporation 12.04 per cent, with management holding the rest. Infratil is the listed major shareholder; CDC itself is not listed.
Infratil reported that at 30 September 2026 CDC had 550MW of leasable operating capacity and 810MW under construction, across Australia and New Zealand together, and contracted capacity of 1.1GW, up 70MW in the quarter. Leasable means capacity that is contractable or revenue generating. CDC's independent valuation was A$18.45 billion, the midpoint of a A$17.4 billion to A$19.6 billion range, and it holds a Moody's Baa2 (Stable) rating. Infratil puts the development pipeline at about 4.2GW of leasable capacity to 2040.