    Sydney's data centre pipeline sheds four early-stage plans

    By Winston Su, Editor · · Add us as a preferred source on Google

    Sydney's data centre pipeline sheds four early-stage plans
    AirTrunk and Goodman at Lane Cove West and Stockland at Arncliffe dropped data centre plans before approval, while CDC expanded Kemps Creek to about 1.4GW.

    At a glance

    • Four Sydney data centre plans were dropped before approval, three at Lane Cove West and one at Arncliffe.

    • AirTrunk said its 140MW Lane Cove West site was too steep and too small.

    • Goodman cited changed policy when it withdrew its 90MW Project Mars.

    • NSW will require a bond of A$30,000 a megawatt from data centres applying for grid connections.

    • CDC Data Centres has expanded its Kemps Creek plan in Western Sydney to about 1.4GW.

     

    Four Sydney data centre plans have been dropped in six weeks, three of them in one business park at Lane Cove West. AirTrunk confirmed on 6 November 2026 that it will not build a 140MW data centre on Mars Road in Lane Cove West, and property group Stockland and developer John Boyd Properties have taken a data centre out of their plans for the former Kogarah Golf Club at Arncliffe. Industrial property group Goodman withdrew Project Mars, also in Lane Cove West, on 28 September, and another Lane Cove West proposal was reported in October to have left the NSW fast-track.

    All four plans were still at the planning stage, and residents were campaigning against data centres at both locations. Over the same weeks, CDC Data Centres expanded its Western Sydney plan at Kemps Creek to about 1.4GW, and Microsoft won approval for a 96MW data centre at Huntingwood. New South Wales is finalising rules that charge data centres for the grid capacity they request, with regulations due by 19 December.

    Plan and developer

    Site and size

    What happened

    Project Mars, Goodman

    12 Mars Road, Lane Cove West. 90MW, A$1.2 billion, in assessment

    Withdrawn 28 September. Goodman cited changed policy and community views

    Lane Cove DC Alliance, Ford Land Company and Aurora Property Partnership

    16-20 Mars Road, Lane Cove West. Size not given, never lodged

    Left the NSW fast-track, reported 20 October. Aurora cited commercial reasons

    Mars Road data centre, AirTrunk

    87-91 Mars Road and 3-4 Apollo Place, Lane Cove West. 140MW, preliminary planning

    Dropped, confirmed 6 November. AirTrunk said the site was too steep and too small

    Kogarah Golf Club data centre, Stockland and John Boyd Properties

    Former Kogarah Golf Club, Arncliffe. 80MW, concept plan in assessment

    Data centre removed, reported 8 November. Stockland called it a market-led decision

    Source: NSW Planning Portal; company statements to the ABC and Capital Brief; In the Cove, 20 October 2026.

    AirTrunk and Stockland drop data centres at Lane Cove West and Arncliffe

    AirTrunk had planned a 140MW data centre at 3-4 Apollo Place and 87-91 Mars Road, in the same business park as its SYD2 campus. Its planning filings put the development cost at A$1 billion. A spokesperson told Capital Brief that the site's "steep terrain and limited scale" made it technically unsuitable for the facilities AirTrunk's customers need, and that the company is focusing on Kurri Kurri in NSW and Mickleham in Melbourne's north. AirTrunk's website says it has no plans for more data centres in Lane Cove beyond its current SYD2 projects.

    At Arncliffe, Stockland and John Boyd Properties are planning an estimated A$3.5 billion logistics precinct on the 18.3-hectare Kogarah Golf Club site, beside the Cooks River and close to Sydney Airport and Port Botany. A Stockland spokesperson told the ABC the amended concept masterplan is for a logistics precinct that does not include a data centre. Stockland called it a market-led business decision, saying the data centre had not progressed far enough to join its development pipeline. The original masterplan included options for every use the site's zoning permits, among them an 80MW data centre. Residents have campaigned against the data centre since August.

    Stockland has approval for its Road 1 data centre at Macquarie Park, granted on 1 October, and has data centre projects at Kemps Creek and Wetherill Park on the NSW fast-track list.

    Goodman cites changed policy in withdrawing Project Mars

    AirTrunk's decision followed a withdrawal in September on the same street. Goodman withdrew Project Mars, a 90MW, A$1.2 billion data centre at 12 Mars Road, on 28 September. The building would have stood about 20 metres from the nearest house, and the application drew 374 submissions, 358 of them objections. Goodman said the "policy and regulatory environment for large-scale data centre development has evolved significantly", and that it had weighed those changes with the views of the local community. Elsewhere in Sydney, Goodman's Project Pluto at Guildford West was approved on 23 July 2026 and Project Apollo at Macquarie Park on 2 September, and its Project Atlas at Eastern Creek is in assessment.

    In October a third Lane Cove West proposal, at 16-20 Mars Road, was reported to have left the NSW Investment Delivery Authority's fast-track before it was lodged for planning. Its proponents were landholders Ford Land Company and Aurora Property Partnership, and Aurora said they chose not to proceed for commercial reasons.

    NSW sets a A$30,000-a-megawatt bond to join the grid connection queue

    The NSW Parliament passed the legislation behind the state's new connection rules on 14 October, and a government presentation to a data centre investment event on 4 November gives the timetable. Regulations and draft guidelines are due by 19 December 2026, and final guidelines by 31 January 2027.

    Connection applicants will pay an entry bond of A$30,000 a megawatt of requested capacity and put demand forecasts into their connection agreements. Data centres are also to pay a major network upgrade fee and commit to paying network charges whether or not they use the capacity. Under a new Data Centre Reliability Obligation, they must contract new NSW renewable generation to cover their supply for at least 10 years, and show they can cut demand by 25 per cent for two hours. The reliability obligation will apply to all data centres not yet connected to power when its guidelines are published.

    The bond targets what the government's August consultation paper called "speculative and duplicative connection applications". The same paper said data centres were seeking connections of up to 28GW across NSW, about 13GW of it in advanced discussions. It proposed the upgrade fee at a default A$200,000 a megawatt in the Sydney, Newcastle and Wollongong region, and A$100,000 elsewhere. For a 140MW Sydney application, that means a A$4.2 million bond when the developer applies and, at the default rate, an upgrade fee of up to A$28 million before it signs a connection agreement.

    Requirement

    When it is paid

    140MW Sydney application

    Entry bond, A$30,000/MW

    With the connection application

    A$4.2 million

    Major network upgrade fee, proposed default A$200,000/MW

    Before the connection agreement is signed

    Up to A$28 million

    Source: NSW Government, Data Centre Reliability Obligation presentation, 4 November 2026; consultation paper on network connection and cost recovery for data centres, August 2026. The upgrade fee rate is the August default and is still to be set.

    Planning rules are under review too. The NSW upper house inquiry into data centres tabled its report on 5 November with 26 recommendations. It recommended designated data centre and innovation precincts rather than a moratorium. The Australian Financial Review reported on 29 October that draft federal AI laws would ban new data centres in the suburbs.

    Larger campuses advance in Western Sydney and the Hunter

    CDC Data Centres expanded its Kemps Creek plan at 845-901 Mamre Road from one building to six in an updated planning document dated 2 October. The campus is rated at about 1.4GW at peak, about 1GW of it computing capacity. In the Hunter, AirTrunk's Kurri Kurri campus is planned at 550.5MW of peak demand, and its environmental impact statement was open for public comment from 14 October to 11 November. AirTrunk has an exclusivity agreement with European Energy Australia over up to 610MW of new Hunter solar and wind to help supply the site.

    Amazon's Glendenning Road campus in Western Sydney was approved at 202.4MW on 14 September. Microsoft's 96MW Honeman Close data centre at Huntingwood followed on 1 October, under a condition that its demand be matched at all times by additional NSW renewable supply. NEXTDC reported in August that it had begun building its S4 campus at Horsley Park.

    Withdrawals are unlikely to move Sydney's 2030 forecast

    The four withdrawals are unlikely to change the industry's forecast for Sydney. Data Centres Australia and data centre researcher DC Byte forecast 2.0GW of capacity in Sydney by 2030 in their Australian Data Centre Forecast Report of 30 October, unchanged from April, even though Sydney's tracked pipeline fell 3.6GW over the same six months. The report put that fall down to "Sydney's announced energy constraints, less certain policy approval timelines and recent policy announcements". Its data runs to 30 September, before three of the four withdrawals.

    The four plans were also a long way from operating. Goodman's Project Apollo and Project Pluto, and Stockland's Road 1, each took 13 to 18 months to win approval in 2026, and a grid connection takes about two years from application. Reaching the report's national forecast of 3.9GW by 2030 depends on projects that are further along being built faster, at about 0.5GW of new capacity a year against about 0.2GW a year in the six months to September.

    Residents and councils oppose other projects

    Opposition has also reached projects that have approval. Residents organised a rally at Merrylands on 7 November against Goodman's Project Pluto at Guildford West, approved on 23 July. Residents at Mascot have organised against Goodman's Project Duke, approved on 22 December 2025.

    AirTrunk's Kurri Kurri campus drew 671 formal objections, more than 88 per cent of submissions, and Cessnock City Council voted unanimously to object. The state, not the council, will decide it. At Macquarie Park, where NEXTDC's S5 is in assessment, Ryde Council told the NSW inquiry the precinct was "dangerously nearing saturation point".

    In South Australia, Melbourne developer Quantum DC paused its Tungkillo plan, a 1.2GW campus in the Adelaide Hills, on 12 November. Chief executive Alby Tomassi said the company had misread the strength of feeling about the proposal and would not lodge a development application in 2026. South Australia's upper house voted on 11 November to hold an inquiry into data centres.

    The RBA says investors are scrutinising some data centre firms

    The Reserve Bank said in its November Statement on Monetary Policy that some data centre firms have faced more investor scrutiny, with equity price falls and higher borrowing costs, while a range of others have seen little change in their cost of capital. It said weaker sentiment is having "only a limited effect" on funding for most Australian data centre operators. Operators have raised at least A$30 billion in the bond and syndicated loan markets so far in 2026, about a fifth of the year's increase in business debt. The RBA board heard at its meeting on 2 and 3 November that investors had become more discriminating in pricing firms exposed to AI investment, marking down the shares and debt of some firms more reliant on borrowing.

    What to watch

    • The NSW regulations. Regulations and draft guidelines are due by 19 December 2026 and final guidelines by 31 January 2027. They will set the conditions for forfeiting an entry bond, and the Consumer Trustee, a body set up under the state's electricity infrastructure roadmap, is to set the final upgrade fee rate.

    • The NSW Government's response to the inquiry. It has until February 2027 to respond, including to the recommendation for designated data centre precincts.

    • The draft AI laws. The Australian Government's draft, including the reported suburban ban, is due for public consultation by the end of 2026.

    • Kurri Kurri and Kemps Creek. AirTrunk's response to the submissions on Kurri Kurri, and CDC's application for the full six-building Kemps Creek campus, are the next steps for the two plans.

     

    Share this article

    Keep reading the market

    Get The Strategic Brief in your inbox every Thursday.

    The leading Australian data centre and AI infrastructure newsletter.

    One email a week. Unsubscribe in one click.

    Your Next Read

    Latest Headlines

    Interested in reaching this audience? Advertise with us.