Melbourne Data Centre Infrastructure Map
47 facilities and 43 zone substations: 33 operational, 6 under construction, 8 planned. Data as at 2 November 2026.
Tap a site for details. Use Controls to filter by status or operator.
Changes since October 2026
- 2 November 2026Capacity figures we could not source now read "Capacity not published", and the totals count only sites with a published figure. Source
- 2 November 2026Zone substation ratings and peak demand now match the networks' latest planning reports. The headroom figures and colours are removed, because none of the Victorian networks publishes them. Source
- 2 November 2026NEXTDC M3 West Footscray: Jemena suspended parts of the 66kV network works in September 2026 and does not expect them to recommence before February 2027, NEXTDC told the ASX on 21 October 2026. Source
- 2 November 2026Centuria Clayton: Monash City Council refused a 38MW building at 1816-1832 Dandenong Road on 29 September 2026. A second building of up to 40MW is still before the council. Source
- 19 October 2026GreenSquareDC Spotswood added: a planned campus of up to 240MW at 44-76 Simcock Avenue, Spotswood. Source
All Melbourne data centres tracked
The facilities on the map above, as a list. Operator names link through to their Certified Strategic profile, or to their listing in the directory.
| Facility | Operator, suburb | MW, status |
|---|---|---|
| NEXTDC M3 | NEXTDCWest Footscray | 225 MWOperational |
| AirTrunk MEL1 | AirTrunkDerrimut | 185 MW185+MW total capacity, operator's figureOperational |
| NEXTDC M2 | NEXTDCTullamarine | 120 MWOperational |
| STACK MEL01A | STACK InfrastructureTruganina | 36 MW36MW building, measure not stated, operator's figureOperational |
| STACK MEL01B | STACK InfrastructureTruganina | 36 MW36MW building, measure not stated, operator's figureOperational |
| Fujitsu Noble Park | FujitsuNoble Park | 28 MWIT load (site supply 12MVA)Operational |
| Telstra Clayton | Telstra InfraCoClayton | 20 MW20MW target power, operator's figureOperational |
| NEXTDC M1 | NEXTDCPort Melbourne | 16 MWOperational |
| Vocus Mitcham | VocusMitcham | 2.5 MW2.5MVA grid supply (2017 spec sheet)Operational |
| 5G Networks Melbourne | 5G NetworksMelbourne CBD | 2 MW2MW of power, measure not stated, operator's figureOperational |
| Datacom @ AirTrunk MEL1 | DatacomDerrimut | 2 MWCapacity, measure not statedOperational |
| AWS Truganina | AWSTruganina | Capacity not publishedOperational |
| CDC Brooklyn BK1/BK2 | CDC Data CentresBrooklyn | Capacity not publishedOperational |
| Digital Realty MEL10 | Digital RealtyDeer Park | Capacity not publishedOperational |
| Digital Realty MEL11 | Digital RealtyDeer Park | Capacity not publishedOperational |
| Digital Realty MEL12 | Digital RealtyDeer Park | Capacity not publishedOperational |
| DXC Technology Melbourne | DXC TechnologyBurwood East | Capacity not publishedOperational |
| Epsilon DC | Epsilon DCPort Melbourne | Capacity not publishedOperational |
| Equinix ME1 | EquinixPort Melbourne | Capacity not publishedOperational |
| Equinix ME2 | EquinixPort Melbourne | Capacity not publishedOperational |
| Equinix ME4 | EquinixDerrimut | Capacity not publishedOperational |
| Equinix ME5 | EquinixWest Melbourne | Capacity not publishedOperational |
| Interactive Melbourne | InteractivePort Melbourne | Capacity not publishedOperational |
| Micron21 | Micron21Kilsyth South | Capacity not publishedOperational |
| Microsoft MEL04 | MicrosoftYarraville | Capacity not publishedOperational |
| Microsoft MEL07 | MicrosoftTullamarine | Capacity not publishedOperational |
| Microsoft Woods Road | MicrosoftTruganina | Capacity not publishedOperational |
| NTT Melbourne 1 | NTTAltona North | Capacity not publishedOperational |
| NTT Port Melbourne | NTTPort Melbourne | Capacity not publishedOperational |
| OMNIconnect | OMNIconnectCarrum Downs | Capacity not publishedOperational |
| ResetData AI-F1 | ResetDataDocklands | Capacity not publishedOperational |
| Telstra Exhibition | Telstra InfraCoMelbourne CBD | Capacity not publishedOperational |
| Vocus Collins Street | VocusMelbourne CBD | Capacity not publishedOperational |
| CDC Laverton | CDC Data CentresLaverton North | 400 MWFull campus when complete, measure not statedUnder construction |
| STACK MEL02 | STACK InfrastructureTruganina | 250 MW250MW critical capacity, operator's figureUnder construction |
| NEXTDC M4 | NEXTDCPort Melbourne | 150 MWIT load, planned target (162MW whole campus)Under construction |
| STACK MEL01C/D | STACK InfrastructureTruganina | 108 MWTwo 54MW buildings, measure not stated, operator's figureUnder construction |
| AWS Cobblebank | AWSCobblebank | Capacity not publishedUnder construction |
| Microsoft MEL05 | MicrosoftYarraville | Capacity not publishedUnder construction |
| Keppel Morwell | KeppelMorwell | 720 MW720MW of potential gross power for the site, Victorian Government figurePlanned |
| AirTrunk MEL2 | AirTrunkTullamarine | 354 MWOver 354MW capacity, measure not stated, operator's figurePlanned |
| GreenSquareDC Spotswood | GreenSquareDCSpotswood | 240 MWPlanned |
| PGIM Truganina | PGIM Real EstateTruganina | 80 MW80MW, measure not stated, press reportPlanned |
| Vantage MEL1 | Vantage Data CentersTullamarine | 64 MWIT load, plannedPlanned |
| Centuria Clayton Expansion | Centuria Industrial REITClayton | 40 MWPlanned |
| AWS Mickleham AI Superhub | AWSMickleham | Capacity not publishedPlanned |
| CDC Brooklyn BK3 | CDC Data CentresBrooklyn | Capacity not publishedPlanned |
Substations on this map
Figures are as each network publishes them. Networks rarely publish spare capacity, so cells without a published figure say not published.
| Substation | Network | Firm rating (N-1) | Peak demand | Network's own figure | Source |
|---|---|---|---|---|---|
| Truganina ZSS | NetworkPowercor | Firm rating (N-1)95.2 MVA | Peak demand128.89 MVA2025 | Network's own figure47.86 MVA50% POE load above N-1 import rating, 2026 | SourcePowercor Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Laverton North ZSS | NetworkPowercor | Firm rating (N-1)79.7 MVA | Peak demand68.36 MVA2025 | Network's own figure1.51 MVA50% POE load above N-1 import rating, 2026 | SourcePowercor Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Laverton ZSS | NetworkPowercor | Firm rating (N-1)79.8 MVA | Peak demand106.4 MVA2025 | Network's own figure37.4 MVA50% POE load above N-1 import rating, 2026 | SourcePowercor Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Werribee ZSS | NetworkPowercor | Firm rating (N-1)82.8 MVA | Peak demand126.81 MVA2025 | Network's own figure49.31 MVA50% POE load above N-1 import rating, 2026 | SourcePowercor Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Melton ZSS | NetworkPowercor | Firm rating (N-1)79.8 MVA | Peak demand101.78 MVA2025 | Network's own figure36.9 MVA50% POE load above N-1 import rating, 2026 | SourcePowercor Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Mount Cottrell ZSS | NetworkPowercor | Firm rating (N-1)not published | Peak demandnot published | Network's own figurenot published | Sourcenot published |
| Bacchus Marsh ZSS | NetworkPowercor | Firm rating (N-1)19.1 MVA | Peak demand33.13 MVA2025 | Network's own figure14.9 MVA50% POE load above N-1 import rating, 2026 | SourcePowercor Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Altona ZSS | NetworkPowercor | Firm rating (N-1)0 MVA | Peak demand21.79 MVA2025 | Network's own figure22.67 MVA50% POE load above N-1 import rating, 2026 | SourcePowercor Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Sunshine East ZSS | NetworkPowercor | Firm rating (N-1)89.7 MVA | Peak demand68.81 MVA2025 | Network's own figurenot published | SourcePowercor Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Tullamarine ZSS | NetworkJemena | Firm rating (N-1)38 MVA | Peak demand28.09 MW2025 | Network's own figure2 MVAMax load at risk, 2026 (10% POE) | SourceJemena planning map (2025 Distribution Annual Planning Report), 2 December 2025Jemena Distribution Annual Planning Report 2025, Table 4-7, 2 December 2025 |
| Airport West ZSS | NetworkJemena | Firm rating (N-1)100.5 MVA | Peak demand69.91 MW2025 | Network's own figure0 MVAMax load at risk, 2026 (10% POE) | SourceJemena planning map (2025 Distribution Annual Planning Report), 2 December 2025Jemena Distribution Annual Planning Report 2025, Table 4-7, 2 December 2025 |
| Melbourne Airport ZSS | NetworkJemena | Firm rating (N-1)not published | Peak demandnot published | Network's own figurenot published | Sourcenot published |
| Essendon ZSS | NetworkJemena | Firm rating (N-1)38 MVA | Peak demand47.41 MW2025 | Network's own figure15.6 MVAMax load at risk, 2026 (10% POE) | SourceJemena planning map (2025 Distribution Annual Planning Report), 2 December 2025Jemena Distribution Annual Planning Report 2025, Table 4-7, 2 December 2025 |
| Braybrook ZSS | NetworkJemena | Firm rating (N-1)32 MVA | Peak demand42.65 MW2025 | Network's own figure26.5 MVAMax load at risk, 2026 (10% POE) | SourceJemena planning map (2025 Distribution Annual Planning Report), 2 December 2025Jemena Distribution Annual Planning Report 2025, Table 4-7, 2 December 2025 |
| Little Queen ZSS | NetworkCitiPower | Firm rating (N-1)131.8 MVA | Peak demand67.2 MVA2025 | Network's own figurenot published | SourceCitiPower Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Little Bourke Street ZSS | NetworkCitiPower | Firm rating (N-1)127.8 MVA | Peak demand106.94 MVA2025 | Network's own figure6.07 MVA50% POE load above N-1 import rating, 2026 | SourceCitiPower Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Southbank ZSS | NetworkCitiPower | Firm rating (N-1)59.7 MVA | Peak demand38.8 MVA2025 | Network's own figurenot published | SourceCitiPower Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Port Melbourne ZSS | NetworkCitiPower | Firm rating (N-1)17.4 MVA | Peak demand13.79 MVA2025 | Network's own figurenot published | SourceCitiPower Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Fisherman's Bend ZSS | NetworkCitiPower | Firm rating (N-1)0 MVA | Peak demand1.27 MVA2025 | Network's own figure1.81 MVA50% POE load above N-1 import rating, 2026 | SourceCitiPower Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Montague ZSS | NetworkCitiPower | Firm rating (N-1)64.3 MVA | Peak demand30.56 MVA2025 | Network's own figurenot published | SourceCitiPower Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Victoria Market ZSS | NetworkCitiPower | Firm rating (N-1)57.88 MVA | Peak demand56.12 MVA2025 | Network's own figure7.76 MVA50% POE load above N-1 import rating, 2026 | SourceCitiPower Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Bouverie ZSS | NetworkCitiPower | Firm rating (N-1)64.9 MVA | Peak demand77.15 MVA2025 | Network's own figure22.39 MVA50% POE load above N-1 import rating, 2026 | SourceCitiPower Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Collingwood ZSS | NetworkCitiPower | Firm rating (N-1)29 MVA | Peak demand34.3 MVA2025 | Network's own figure7.96 MVA50% POE load above N-1 import rating, 2026 | SourceCitiPower Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Collingwood CW ZSS | NetworkCitiPower | Firm rating (N-1)34.4 MVA | Peak demand25.22 MVA2025 | Network's own figurenot published | SourceCitiPower Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Bayswater ZSS | NetworkAusNet | Firm rating (N-1)66.8 MVA | Peak demand52.3 MVAsummer 2024/25 | Network's own figure93%Overload, summer 2026 | SourceAusNet Distribution Annual Planning Report 2026-2030 (Issue 2.0) and planning portal, 4 May 2026AusNet Distribution Annual Planning Report 2026-2030, Table 35, 4 May 2026 |
| Boronia ZSS | NetworkAusNet | Firm rating (N-1)77.8 MVA | Peak demand68.7 MVAsummer 2024/25 | Network's own figure101%Overload, summer 2026 | SourceAusNet Distribution Annual Planning Report 2026-2030 (Issue 2.0) and planning portal, 4 May 2026AusNet Distribution Annual Planning Report 2026-2030, Table 35, 4 May 2026 |
| Croydon ZSS | NetworkAusNet | Firm rating (N-1)83 MVA | Peak demand64.4 MVAsummer 2024/25 | Network's own figure99%Overload, summer 2026 | SourceAusNet Distribution Annual Planning Report 2026-2030 (Issue 2.0) and planning portal, 4 May 2026AusNet Distribution Annual Planning Report 2026-2030, Table 35, 4 May 2026 |
| Eltham ZSS | NetworkAusNet | Firm rating (N-1)80.7 MVA | Peak demand74.4 MVAsummer 2024/25 | Network's own figure106%Overload, summer 2026 | SourceAusNet Distribution Annual Planning Report 2026-2030 (Issue 2.0) and planning portal, 4 May 2026AusNet Distribution Annual Planning Report 2026-2030, Table 35, 4 May 2026 |
| Ringwood North ZSS | NetworkAusNet | Firm rating (N-1)41 MVA | Peak demand43.5 MVAsummer 2024/25 | Network's own figure122%Overload, summer 2026 | SourceAusNet Distribution Annual Planning Report 2026-2030 (Issue 2.0) and planning portal, 4 May 2026AusNet Distribution Annual Planning Report 2026-2030, Table 35, 4 May 2026 |
| Ferntree Gully ZSS | NetworkAusNet | Firm rating (N-1)81.6 MVA | Peak demand42.9 MVAsummer 2024/25 | Network's own figure61%Overload, summer 2026 | SourceAusNet Distribution Annual Planning Report 2026-2030 (Issue 2.0) and planning portal, 4 May 2026AusNet Distribution Annual Planning Report 2026-2030, Table 35, 4 May 2026 |
| Lilydale ZSS | NetworkAusNet | Firm rating (N-1)90.1 MVA | Peak demand63.4 MVAsummer 2024/25 | Network's own figure80%Overload, summer 2026 | SourceAusNet Distribution Annual Planning Report 2026-2030 (Issue 2.0) and planning portal, 4 May 2026AusNet Distribution Annual Planning Report 2026-2030, Table 35, 4 May 2026 |
| Chirnside Park ZSS | NetworkAusNet | Firm rating (N-1)48.8 MVA | Peak demand47.5 MVAsummer 2024/25 | Network's own figure108%Overload, summer 2026 | SourceAusNet Distribution Annual Planning Report 2026-2030 (Issue 2.0) and planning portal, 4 May 2026AusNet Distribution Annual Planning Report 2026-2030, Table 35, 4 May 2026 |
| Woori Yallock ZSS | NetworkAusNet | Firm rating (N-1)46.2 MVA | Peak demand31.4 MVAsummer 2024/25 | Network's own figure75%Overload, summer 2026 | SourceAusNet Distribution Annual Planning Report 2026-2030 (Issue 2.0) and planning portal, 4 May 2026AusNet Distribution Annual Planning Report 2026-2030, Table 35, 4 May 2026 |
| Watsonia ZSS | NetworkAusNet | Firm rating (N-1)101 MVA | Peak demand65.3 MVAsummer 2024/25 | Network's own figure74%Overload, summer 2026 | SourceAusNet Distribution Annual Planning Report 2026-2030 (Issue 2.0) and planning portal, 4 May 2026AusNet Distribution Annual Planning Report 2026-2030, Table 35, 4 May 2026 |
| Thomastown ZSS | NetworkAusNet | Firm rating (N-1)58.6 MVA | Peak demand75.2 MVAsummer 2024/25 | Network's own figure140%Overload, summer 2026 | SourceAusNet Distribution Annual Planning Report 2026-2030 (Issue 2.0) and planning portal, 4 May 2026AusNet Distribution Annual Planning Report 2026-2030, Table 35, 4 May 2026 |
| Epping ZSS | NetworkAusNet | Firm rating (N-1)87.8 MVA | Peak demand83.4 MVAsummer 2024/25 | Network's own figure124%Overload, summer 2026 | SourceAusNet Distribution Annual Planning Report 2026-2030 (Issue 2.0) and planning portal, 4 May 2026AusNet Distribution Annual Planning Report 2026-2030, Table 35, 4 May 2026 |
| Clyde North ZSS | NetworkAusNet | Firm rating (N-1)89.2 MVA | Peak demand96.6 MVAsummer 2024/25 | Network's own figure134%Overload, summer 2026 | SourceAusNet Distribution Annual Planning Report 2026-2030 (Issue 2.0) and planning portal, 4 May 2026AusNet Distribution Annual Planning Report 2026-2030, Table 35, 4 May 2026 |
| Deepdene ZSS | NetworkCitiPower | Firm rating (N-1)32.1 MVA | Peak demand45.72 MVA2025 | Network's own figure11.39 MVA50% POE load above N-1 import rating, 2026 | SourceCitiPower Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Kew ZSS | NetworkCitiPower | Firm rating (N-1)27.2 MVA | Peak demand35.97 MVA2025 | Network's own figure9.73 MVA50% POE load above N-1 import rating, 2026 | SourceCitiPower Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Riversdale ZSS | NetworkCitiPower | Firm rating (N-1)24.9 MVA | Peak demand40.6 MVA2025 | Network's own figure14.13 MVA50% POE load above N-1 import rating, 2026 | SourceCitiPower Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Northcote ZSS | NetworkCitiPower | Firm rating (N-1)31.9 MVA | Peak demand37.17 MVA2025 | Network's own figure2.27 MVA50% POE load above N-1 import rating, 2026 | SourceCitiPower Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| West Brunswick ZSS | NetworkCitiPower | Firm rating (N-1)31.8 MVA | Peak demand36.32 MVA2025 | Network's own figure6.68 MVA50% POE load above N-1 import rating, 2026 | SourceCitiPower Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
| Dock Area ZSS | NetworkCitiPower | Firm rating (N-1)30.48 MVA | Peak demand31.36 MVA2025 | Network's own figure11.02 MVA50% POE load above N-1 import rating, 2026 | SourceCitiPower Distribution Annual Planning Report 2025 and Max Demand Template, December 2025 |
About This Map
This map tracks data centres across Greater Melbourne, alongside the zone substations that serve the western corridor and the rest of the city. Capacity is IT load in megawatts unless the site's entry names another measure. Figures are as the operator or the planning application states them, and sites without a published figure are marked "Capacity not published". Substation firm capacity and peak demand come from the distributors' annual planning reports and change once a year.
Records come from operator announcements and ASX releases, Victorian planning decisions, and the planning reports published by AEMO, AusNet, Powercor, CitiPower and Jemena. Each record carries the source it came from.
The map is refreshed on the first business day of each month, and the date above the map is the date the data was last checked, not the date you opened the page.
Map researched and maintained by CertifiedStrategic.com.
Related Analysis
Insights
Australian data centre capacity: the 2026 to 2030 guide
Read the full analysisInsights
Victoria sets a 150-metre buffer and an own-power rule for data centres
Read the full analysisInsights
Melbourne's data centre pipeline breaks out of the west
Read the full analysisInsights
Keppel's 720MW Morwell Campus: Victoria's Hyperscale Pivot
Read the full analysisInsights
GreenSquareDC files 240MW plan for a former Spotswood depot
Read the full analysisInsights
NextDC banks A$165m of Geelong land at Lovely Banks
Read the full analysisCapacity
Australian capacity requirements
For neoclouds, AI labs and enterprises planning an Australian deployment. We shortlist sites against your GPU platform, scale, market and ready-for-service date. Operators with capacity coming online are welcome to get in touch.
Connect on LinkedInKeep reading the market
Get The Strategic Brief in your inbox every Thursday.
The leading Australian data centre and AI infrastructure newsletter.