Japan Data Centre Infrastructure Map
41 facilities: 22 operational, 8 under construction, 9 planned, 2 not confirmed. Data as at 14 November 2026.
Cite this map: Certified Strategic, “Japan Data Centre Infrastructure Map”, 14 November 2026, updated 14 November 2026. certifiedstrategic.com/maps/japan
All Japan data centres tracked
| Facility | Operator, suburb | MW, status |
|---|---|---|
| TOK1 Tokyo East | AirTrunk Inzai, Chiba | 300 MW Total campus capacity at full build-out Operational |
| Cosmosquare Data Centre campus | ESR Suminoe, Osaka City | 130 MW Facility load, campus (three phases) Operational |
| NRT campus | MC Digital Realty Inzai, Chiba | 120 MW Planned IT load, campus total with future buildings, over 120MW Operational |
| TOK2 Tokyo West | AirTrunk West Tokyo | 110 MW Total campus capacity at full build-out Operational |
| Telehouse Tokyo Tama campus | KDDI (Telehouse) Tama, Tokyo | 100 MW Total power receiving capacity, Tama area, up to Operational |
| TY1 | Princeton Digital Group Saitama City, Saitama | 96 MW Operational |
| KIX campus | MC Digital Realty Minoh and Ibaraki, Osaka | 74 MW Planned IT load, campus total, over 74MW Operational |
| Tokyo campus (TYO1, TYO2) | STT GDC Inzai, Chiba | 70.8 MW Operational |
| Tokyo Inzai campus (Inzai 1 to 4) | Colt DCS Inzai, Chiba | 70 MW Our sum of four buildings' IT load Operational |
| TY12x | Equinix xScale Inzai, Chiba | 54 MW Operational |
| Fuchu data centre | SoftBank Fuchu, Tokyo | 50 MW Maximum power receiving capacity Operational |
| Osaka Sakai Data Center | KDDI Sakai, Osaka | 50 MW Maximum power receiving capacity, approximate (press report) Operational |
| Shiroi Data Center Campus | IIJ Shiroi, Chiba | 50 MW Power receiving capacity, campus Operational |
| Osaka Keihanna | Colt DCS Keihanna Science City | 45 MW Operational |
| TY13x | Equinix xScale Inzai, Chiba | 36 MW Operational |
| Keihanna OSK11 | NTT DATA Seika, Kyoto | 30 MW Operational |
| OSK1 Osaka West | AirTrunk West Osaka | 20 MW Total capacity, measure not stated Operational |
| Ishikari Renewable Energy Data Center No.1 | Ishikari Saiene Data Center No.1 GK Ishikari, Hokkaido | 15 MW Power receiving capacity Operational |
| OS2x and OS4x | Equinix xScale Minoh, Osaka | 14.4 MW Operational |
| Inzai data center | Google Inzai, Chiba | Capacity not published Operational |
| Ishikari Data Center | Sakura Internet Ishikari, Hokkaido | Capacity not published Operational |
| Kitakyushu Data Center (Asian Frontier) | SoftBank Yahatahigashi, Kitakyushu | Capacity not published Operational |
| Tsukuba Tech Central (TYO05) | Goodman Tsukuba, Ibaraki | 1,000 MW Total campus power (first building 50MW) Under construction |
| Osaka Sakai AI Data Center | SoftBank Sakai, Osaka | 140 MW Power receiving capacity Under construction |
| Hibikino data centre campus | Asia Pacific Land and Global Compute Infrastructure Wakamatsu, Kitakyushu | 120 MW Total power load, two buildings Under construction |
| Tochigi TCG11 | NTT DATA Tochigi Prefecture | 100 MW Under construction |
| Hokkaido Tomakomai AI Data Center | SoftBank Tomakomai, Hokkaido | 50 MW Power receiving capacity, first data hall building Under construction |
| Tokyo TKY11 | NTT DATA Shiroi, Chiba | 50 MW Under construction |
| OSK1 Keihanna | CyrusOne KEP Keihanna | 48 MW Under construction |
| TK1 Tokyo | NEXTDC Minato, Tokyo | 30 MW Under construction |
| AI data centre at Circular Park Kyushu | Kai Shin Digital Infrastructure Satsumasendai, Kagoshima | 350 MW Cumulative after staged expansion, measure not stated Planned |
| Itoshima data centre campus | Asia Pacific Land Itoshima, Fukuoka | 300 MW Measure not stated Planned |
| Imari campus | DayOne Imari, Saga | 200 MW Grid power (160MW secured) Planned |
| Tokyo TKY12 | NTT DATA Shiroi, Chiba | 200 MW Planned |
| Minoh hyperscale site | ESR and Colt DCS Minoh, Osaka | 130 MW Facility load, whole site (first phase 65MW) Planned |
| Osaka OSK12 | NTT DATA Ibaraki, Osaka | 36 MW Planned |
| Tokyo Inzai 5 | Colt DCS Inzai, Chiba | 32 MW Planned |
| Hakata Data Center | NTT West Hakata, Fukuoka City | 5 MW Planned |
| Sagamihara data centre campus | Goodman Sagamihara, Kanagawa | Capacity not published Planned |
| KIX01 Keihanna | STACK Infrastructure Keihanna | 72 MW Campus, measure not stated Not confirmed |
| TKY01 Inzai | STACK Infrastructure Inzai, Chiba | 36 MW Campus, measure not stated (two 18MW buildings) Not confirmed |
Not on the map: OSK2 Osaka Downtown East, AirTrunk, East Osaka, location not published. Planned, 100 MW (Total campus IT load, up to). Other figure: 50+MW, measure not stated (AirTrunk OSK2 page). Source
Government data centre regions
On 11 September 2026 Japan's Ministry of Economy, Trade and Industry (METI) certified nine regions, at ten points, as data centre clusters in its first round of GX strategic regions. Boundaries and plans are not published yet, so the map marks each named town.
- Hokkaido: Ishikari METI, 11 September 2026
- Hokkaido: Tomakomai METI, 11 September 2026
- Akita: Akita METI, 11 September 2026
- Miyagi: Tomiya METI, 11 September 2026
- Tochigi: Yaita METI, 11 September 2026
- Ibaraki: Joso / Tsukuba METI, 11 September 2026
- Toyama: Nanto METI, 11 September 2026
- Kagawa: Ayagawa / Sakaide / Marugame METI, 11 September 2026
- Fukuoka: Kitakyushu / Nogata / Kurate METI, 11 September 2026
- Kagoshima: Satsumasendai METI, 11 September 2026
15 towns: Ishikari, Tomakomai, Akita, Tomiya, Yaita, Joso, Tsukuba, Nanto, Ayagawa, Sakaide, Marugame, Kitakyushu, Nogata, Kurate, Satsumasendai.
Cables to Australia
Two cable routes link Japan and Australia today, both through Guam. The map draws them as straight dashed lines between landing points: an indicative route, not the path on the seabed.
- Australia-Japan Cable (AJC) In service since December 2001, according to its owner. Lands at Shima and Maruyama in Japan, Tanguisson and Tumon Bay in Guam, and Oxford Falls and Paddington in Sydney. Drawn as straight lines through Guam: an indicative route, not the path on the seabed. The Japanese ends are town points, not the stations. Source
- Japan-Guam-Australia (JGA) Two cables joined at Piti, Guam: JGA North from Minami-Boso (completed July 2020) and JGA South to Sydney, with a branch to Maroochydore (in service March 2020). Lightstorm now owns JGA North and significant portions of JGA South. Drawn as straight lines: an indicative route, not the path on the seabed. Source
- APX North (SUBCO) SUBCO announced APX North on 22 September 2026: 9,500km from Sydney to Japan via Guam, with some fibre pairs bypassing Guam, targeted for 2029. Its landing sites are not published yet, so it is not drawn. Source
Changes since October 2026
- Japan map added. Source
About This Map
This map is a special: it looks past Australia to Japan, where Australian operators AirTrunk, Goodman and NEXTDC are building. It tracks data centre campuses from Hokkaido to Kyushu, the two subsea cable routes that link Japan and Australia through Guam, and the towns in Japan's new government data centre regions. Capacity is shown with the measure its source uses, and campuses without a published figure are marked "Capacity not published".
Records come from operators' own pages and announcements, city and prefecture releases, cable owners' pages and the announcement of Japan's GX strategic regions by the Ministry of Economy, Trade and Industry (METI) on 11 September 2026. Where two sources disagree, the map uses the operator's own current page and gives the other figure, with its source, in the site's details.
Most campuses are placed at the town their operator names, not at the exact site, and are marked "Location approximate". Cloud regions are left off because their providers do not say where their buildings are. Cable routes are straight dashed lines between landing points: they show what each cable connects, not its path on the seabed.
Map researched and maintained by CertifiedStrategic.com.
Government data centre regions: Ministry of Economy, Trade and Industry (METI), GX strategic regions, 11 September 2026. Campus and cable records: each operator's or owner's own pages, linked from each record. Base map: OpenFreeMap, OpenMapTiles, OpenStreetMap contributors.
Related Analysis
Japan's data centres: 3.8GW live, US$8bn AirTrunk bet
AirTrunk plans up to US$30bn for Japan
Goodman signs 20-year Tokyo lease behind an eight-to-ten-year grid wait
NEXTDC's A$8.4 billion liquidity underpins four-city Asia data centre pipeline after KL1