Queensland Data Centre Infrastructure Map

19 facilities: 13 operational, 1 under construction, 5 planned. Data as at 2 November 2026.

Cite this map: Certified Strategic, “Queensland Data Centre Infrastructure Map”, 8 October 2026, updated 14 November 2026. certifiedstrategic.com/maps/queensland

All Queensland data centres tracked

The facilities on the map above, as a list. Operator names link through to their Certified Strategic profile, or to their listing in the directory.

FacilityOperator, suburbMW, status
Polaris Data CentreSpringfield City Group
Springfield Central
9 MW
Operational
B2 BrisbaneNEXTDC
Fortitude Valley
6 MW
Operational
Brisbane Data Centre (BDC)5G Networks
Fortitude Valley
3 MW
total site power
Operational
Pulse DC (Wellcamp Data Centre)Pulse DC
Wellcamp, Toowoomba
2.5 MW
basis not stated
Operational
B1 BrisbaneNEXTDC
Brisbane City
2.3 MW
Operational
Eight Mile Plains Data CentreFujitsu Australia
Eight Mile Plains
2 MW
Operational
BNE1 (formerly iseek LDR1)DigiCo Infrastructure REIT
Brisbane Airport
1.8 MW
Operational
BNE2 (formerly iseek LDR2)DigiCo Infrastructure REIT
Brisbane Airport
1.7 MW
Operational
SC1 Sunshine CoastNEXTDC
Maroochydore
1 MW
Operational
TSV1 (formerly iseek NQRDC)DigiCo Infrastructure REIT
Garbutt, Townsville
0.5 MW
Operational
BNE (formerly BNE3, iseek Woolloongabba)DigiCo Infrastructure REIT
Woolloongabba
0.3 MW
Operational
BR1 BrisbaneEquinix
Fortitude Valley
Capacity not published
Operational
Woolloongabba Data CentreTelstra InfraCo
Woolloongabba
Capacity not published
Operational
NEXTDC SC2 Sunshine CoastNEXTDC
Maroochydore
6 MW
Under construction
Western Downs Digital Park (Zerra DC)Zerra DC (applicant WDDP Pty Ltd)
Kogan
1,440 MW
Planned
Supernode DC, BrendaleQuinbrook Infrastructure Partners
Brendale
500 MW
Planned
DigiCo BNE3, Brisbane AirportDigiCo Infrastructure REIT (HMC Capital)
Brisbane Airport
19.6 MW
Planned
NEXTDC GC1 Gold CoastNEXTDC
Southport
6 MW
Planned
Swanbank data centre, Leaf StreetNorthern Concept Swanb Pty Ltd (applicant)
Swanbank, Ipswich
Capacity not published
Planned

Substations on this map

Figures are as each network publishes them. Networks rarely publish spare capacity, so cells without a published figure say not published.

SubstationNetworkFirm rating (N-1)Peak demandNetwork's own figureSource
BlackstonePowerlinknot publishednot publishednot publishednot published
BraemarPowerlinknot publishednot publishednot publishednot published
South PinePowerlinknot publishednot publishednot publishednot published
Western DownsPowerlinknot publishednot publishednot publishednot published

Changes since October 2026

  1. Queensland will move the planning and assessment of data centres from councils to the state, the ABC reported on 2 October 2026. Applicants will need a social impact assessment and a community benefit agreement with the council before they lodge. The framework is not published yet. Source
  2. Powerlink published its 2026 Transmission Annual Planning Report in October 2026, with an appendix on connecting data centres to the Queensland grid. Source

About This Map

This map tracks data centres across Queensland, the corridors where campuses are being proposed, and the grid and water conditions each one depends on. Capacity is shown with the measure its source uses, because Queensland's largest figures are published on different bases, and sites without a published figure are marked "Capacity not published".

Records come from operator announcements and ASX releases, council development registers, Queensland Government releases and Powerlink's planning reports. The six corridors follow Certified Strategic's scoring of land, power, connectivity, water and workforce against public data. Each record carries the source it came from.

The map is refreshed on the first business day of each month, and the date above the map is the date the data was last checked, not the date you opened the page.

Map researched and maintained by CertifiedStrategic.com.

Power lines and power stations: © Commonwealth of Australia (Geoscience Australia) 2026, Electricity Infrastructure, CC BY 4.0

Related Analysis

Australian data centre capacity: the 2026 to 2030 guide

Where in Queensland can an AI data centre actually be built?

Queensland wins Anthropic's first Australian data centre lease

Zerra files a 1.44GW data centre campus in Queensland

Zerra advances a 1.44GW, A$31.9bn data centre campus in Queensland

Crisafulli offers OpenAI and Anthropic Queensland power on two conditions

Queensland spotlight: 1.4GW and onwards

Bowen to legislate data centre energy rules over Queensland

Queensland Data Centres Council launches as a state advocate

Using our data: read the licence and attribution terms.

Capacity

Australian capacity requirements

For neoclouds, AI labs and enterprises planning an Australian deployment. We shortlist sites against your GPU platform, scale, market and ready-for-service date. Operators with capacity coming online are welcome to get in touch.

Connect on LinkedIn