Capacity & ExpansionMarket Intelligence

    Australian data centre capacity: the 2026 to 2030 guide

    By Winston Su, Editor · · Add us as a preferred source on Google

    Updated 3 November 2026

    Australian data centre capacity: the 2026 to 2030 guide
    Australia has about 1.6GW of data centre capacity running and a 3.9GW forecast for 2030. Every project with an opening date, by year and by state.

    At a glance

    • Australia has about 1.6GW of data centre capacity running, and industry body Data Centres Australia and researcher DC Byte forecast 3.9GW by 2030. Ten data centre projects and stages across four states are due in 2027, four of them campuses of 200MW or more.

    • Five follow in 2028, four in New South Wales and one in South Australia.

    • Headline capacity due to start is about 1.7GW in 2027 and 1.3GW in 2028, including several full-campus sizes.

    • New South Wales carries 13 of the 25 projects with a published date, with projects due in every year from 2026 to 2029.

    • Large campuses without a date include gigawatt-scale proposals in New South Wales, Victoria, South Australia and the Northern Territory.

     

    This guide lists every Australian data centre project and stage with a published target year, taken from the operator, its builder or press reporting, with sources under each table. Financial-year dates are converted to the calendar months they cover. Sites already operating are in the list of data centres in Australia.

    Ten projects and stages are due in 2027 and five in 2028, and New South Wales holds eight of the 15. Two Sydney campuses carry 2029 dates, and no project yet has a published 2030 date.

    Year

    Projects and stages

    By state

    2026

    8

    NSW 3, Victoria 2, Tasmania 1, WA 1, NT 1

    2027

    10

    NSW 4, Queensland 3, Victoria 2, Tasmania 1

    2028

    5

    NSW 4, South Australia 1

    2029

    2

    NSW 2

    Source: operator releases and results, builders and trade press, compiled 20 September 2026. CDC's Marsden Park program, running from April 2027 to March 2029, is counted in 2029.

    The next table groups headline capacity by the year each project's stage is due, using the published figure for that stage, or for the whole project where no stage figure is given. Most campuses come online in stages over several years, and each company measures capacity its own way.

    Year

    Headline capacity due

    By state (MW)

    2026

    About 90MW, plus three projects without a MW figure

    Tasmania 44, NSW 26, Victoria 20, NT 1.5

    2027

    About 1.7GW

    NSW 938, Queensland 381, Victoria 355, Tasmania 1

    2028

    About 1.3GW

    South Australia 800, NSW 516

    2029

    About 0.7GW

    NSW 704

    Source: capacity as published by each company, on different bases: planned capacity, IT load (the power available to computing equipment), first phase or whole campus. S4, S7, MEL2, the SYD3 extension and IREN Bundey are full-campus sizes that will be built over years, so the totals are indicative and do not measure capacity switching on in that year. Victoria's largest projects have no date yet: Syncline Energy's Plumpton proposal at 2.4GW, NEXTDC M5 at up to 1.2GW, Keppel's Hazelwood campus at 720MW, CDC Laverton at more than 400MW, STACK MEL02 at 252MW and NEXTDC M4 at 150MW.

    2026: eight projects and about 90MW across five states and territories

    Eight Australian data centre projects and stages carry a 2026 date. Three were delivered in the first eight months of the year, and about 90MW of capacity is involved.

    Timeline of Australian data centres due online in 2026 and 2027 by state and half-year. 2026: DigiCo SYD1, Macquarie IC3 SuperWest and GreenSquareDC SYD1 in NSW, NEXTDC M3 and Firmus Brooklyn in Victoria, Firmus St Leonards in Tasmania, CDC Maddington in WA and NEXTDC D2 in Darwin. 2027: NEXTDC S4 and S7 in Western Sydney, AirTrunk MEL2 and NEXTDC GE1 in Victoria, Zerra's Western Downs Building One, DigiCo BNE3 and NEXTDC SC2 in Queensland. Headline capacity is about 90MW in 2026 and 1.7GW in 2027.

     

    Project

    Capacity as published

    When

    NEXTDC M3, West Footscray, Melbourne

    20MW added, taking the site to 60MW built

    Delivered January to June 2026

    DigiCo SYD1, Ultimo, Sydney

    20MW upgrade

    Completed by June 2026

    Firmus Brooklyn cluster, Melbourne

    About 18,400 NVIDIA GB300 processors

    Handed over August 2026

    Macquarie Data Centres IC3 SuperWest, Macquarie Park, Sydney

    6MW, first stage of a 47MW building

    Due September 2026

    GreenSquareDC SYD1, Western Sydney

    First facility on a campus of more than 100MW

    Due July to September 2026

    Firmus St Leonards Stage 1a, Launceston

    44MW of the 90MW Stage 1

    Due 2026 on Firmus's timetable; the ABC reported early 2027

    CDC Maddington, Perth

    First stage of a campus of up to 200MW

    Due 2026, as reported when announced in August 2025

    NEXTDC D2, Darwin

    About 1.5MW initial, 6MW planned

    Due by December 2026

    Source: NEXTDC FY26 results, DigiCo FY26 results, Firmus, Macquarie Technology FY26 results, GreenSquareDC, Firmus and Tasmanian Government, ABC, DCD.

    NEXTDC and DigiCo added their 2026 capacity inside existing sites, and Macquarie Data Centres says the power and water supply for the full IC3 SuperWest building has been commissioned.

    Firmus, one of the neocloud providers in Australia that rent out the computing capacity inside an AI data centre, said on 27 August that its Melbourne cluster had been installed, commissioned and handed over.

    Canberra Data Centres (CDC) supplies the data centre infrastructure for Firmus's Project Southgate. Its Brooklyn campus in Melbourne, operating since 2024, was officially opened by Premier Jacinta Allan in February 2026.

    2027: ten projects, four of them 200MW or more

    Ten Australian data centre projects and stages carry a 2027 target date, four of them campuses of 200MW or more, and about 1.7GW of headline capacity starts that year.

    Project

    Capacity as published

    When

    NEXTDC GE1, Corio, Geelong

    About 4MW, 1MW initial

    January to June 2027

    VIRIDIS edge site, Burnie, Tasmania

    About 1MW

    January to June 2027

    Macquarie IC3 SuperWest stage two, Sydney

    13MW

    By June 2027

    DigiCo SYD1 first tranche, Sydney

    10MW

    By June 2027

    NEXTDC S4, Horsley Park, Western Sydney

    365MW planned, 250MW in progress

    Mid-2027, builder Multiplex

    NEXTDC S7, Eastern Creek, Western Sydney

    550MW+; 612MW in the planning application

    First phase July to December 2027, subject to approvals

    AirTrunk MEL2, Melbourne's north-west

    Over 354MW

    July to December 2027

    NEXTDC SC2, Maroochydore, Queensland

    About 1MW initial, 6MW planned

    July to December 2027

    Zerra Western Downs Building One, Kogan, Queensland

    One of four 360MW buildings, 1.44GW in the application

    2027, for Anthropic

    DigiCo BNE3, Brisbane Airport

    19.6MW IT load

    Construction complete in 2027

    Source: NEXTDC FY26 results, VIRIDIS, Macquarie Technology, DigiCo, Multiplex, NEXTDC, NSW Planning Portal, CRN, Capacity, DigiCo BNE3.

    NEXTDC's S7 has OpenAI as anchor tenant, and NEXTDC set its 2027 date in December 2025.

    Anthropic is leasing Building One at Singapore developer Zerra DC's Western Downs campus, subject to council approval of the development application and Foreign Investment Review Board approval of the lease.

    2028: five projects and about 1.3GW, four of them in New South Wales

    Five Australian data centre projects and stages carry a 2028 target date, covering about 1.3GW of headline capacity, four of them in New South Wales.

    Australian data centres due online in 2028 and 2029 by state, and a selection of large projects with no published date.

    Project

    Capacity as published

    When

    Starwood, Doma and Telstra InfraCo, Minchinbury, Western Sydney

    62MW IT load

    January to March 2028

    Goodman SYD01, Artarmon, Sydney

    12.2MW first phase of 61MW IT load

    April to June 2028

    DigiCo SYD1 second tranche, Sydney

    42MW

    By June 2028

    AirTrunk SYD3 extension, Western Sydney

    More than 400MW

    Mid-2028, builder Bouygues

    IREN Bundey, South Australia

    800MW

    Power connection from 2028

    Source: Starwood, Doma and Telstra InfraCo, w.media, DigiCo, Bouygues, IREN.

    Works on AirTrunk's SYD3 extension began in July 2026. IREN announced its Bundey campus, about 125km north-east of Adelaide, on 3 June 2026, with its transmission connection agreement already signed.

    2029 and 2030: two Sydney campuses, then forecasts

    Two Sydney campuses carry a 2029 date. No Australian operator has published a 2030 opening date, so 2030 is covered by forecasts.

    Project

    Capacity as published

    When

    CDC Marsden Park, Western Sydney

    504MW approved across six buildings

    Multiple buildings, April 2027 to March 2029

    Macquarie Technology campus, Macquarie Park, Sydney

    Proposed 200MW

    First completion late 2029, subject to approvals

    Source: Infratil, NSW Planning Portal, Macquarie Technology.

    Australia intends to legislate data centre standards in early 2027, and most of the pipeline would be built under them.

    The Australian Energy Market Operator (AEMO) forecasts data centre electricity use in the National Electricity Market, the grid serving every state except Western Australia, to triple to about 15TWh in the year to June 2030. The forecast for total operating capacity, reaching 3.9GW in 2030, is set out at the end of this guide.

    State by state

    Each state's dated projects run in date order, followed by a selection of the large projects that have no date yet. For the operating fleet, see the ranking of data centres in Australia, and for how each state stands on pipeline, power, policy and workforce, the state-by-state assessment.

    New South Wales

    • 2026: DigiCo SYD1 20MW, Macquarie IC3 SuperWest 6MW, GreenSquareDC SYD1

    • 2027: Macquarie IC3 SuperWest 13MW, DigiCo SYD1 10MW, NEXTDC S4 365MW planned, NEXTDC S7 550MW+

    • 2028: Starwood, Doma and Telstra InfraCo Minchinbury 62MW, Goodman SYD01 12.2MW, DigiCo SYD1 42MW, AirTrunk SYD3 extension 400MW+

    • 2029: CDC Marsden Park 504MW, Macquarie Technology's Macquarie Park campus 200MW

    • No date yet: AirTrunk's 1.2GW Kemps Creek proposal, AWS Glendenning at 235MW (approved 16 September 2026), Goodman's Project Atlas at 500MVA (megavolt-amperes) of grid supply, Project Apollo at 135MW and Project Pluto at 126MW, NEXTDC S5 at 80MW+, Stockland's 76.4MW at Macquarie Park

    Six of the state's 13 dated projects are data centres in Western Sydney.

    Victoria

    • 2026: NEXTDC M3 20MW, Firmus Brooklyn cluster

    • 2027: NEXTDC GE1 Geelong about 4MW, AirTrunk MEL2 354MW+

    • No date yet: Syncline Energy's Victorian AI Hub at Plumpton at 2.4GW of power demand, with no opening date for its first phase and full build targeted for 2035, NEXTDC M5 at up to 1.2GW and M4 at 150MW, Keppel's Hazelwood campus near Morwell at 720MW, CDC Laverton at more than 400MW, STACK MEL02 at 252MW, Vantage MEL1 at 64MW of IT load, and AirTrunk's seven-building Mickleham campus, lodged for planning in July 2026 with no MW figure published

    Queensland

    • 2027: Zerra Western Downs Building One 360MW for Anthropic, DigiCo BNE3 19.6MW, NEXTDC SC2 Maroochydore about 1MW

    • No date yet: the other three Western Downs buildings, Quinbrook's Supernode at Brendale with up to 800MW of power supply

    South Australia

    • 2028: IREN Bundey 800MW

    • No date yet: Firmus's Tailem Bend and Stirling North sites, about 1.0GW and 1.3GW of IT load at full build, and 1414 Degrees' Aurora precinct at up to 1GW

    Tasmania

    Western Australia

    • 2026: CDC Maddington, first stage of up to 200MW

    Northern Territory

    • 2026: NEXTDC D2 Darwin about 1.5MW

    • No date yet: Beetaloo Digital's 2GW gas-powered proposal at Weddell, Energy North's 1GW Project Ares at Murranji Station

    Operating capacity is forecast to reach 3.9GW by 2030

    Total operating capacity for each year is published only as a forecast, and only nationally and for Sydney and Melbourne. Industry body Data Centres Australia and researcher DC Byte forecast it on one measure, the power available to servers in finished data halls.

    Year

    Australia

    Sydney / Melbourne

    2025

    1.4GW

    0.8GW / 0.4GW

    2026

    1.8GW

    1.0GW / 0.6GW

    2027

    2.3GW

    1.2GW / 0.8GW

    2028

    2.7GW

    1.5GW / 1.0GW

    2029

    3.4GW

    1.8GW / 1.2GW

    2030

    3.9GW

    2.0GW / 1.4GW

    Source: Data Centres Australia and DC Byte, Australian Data Centre Forecast Report, Issue 2, October 2026, data to 30 September 2026. Figures for 2026 to 2030 are forecasts. The report does not forecast other cities or states, and its figures are rounded to 0.1GW, so the rest of the country cannot be worked out by subtracting Sydney and Melbourne from the national total.

    Frequently Asked Questions

    How much data centre capacity does Australia have?

    Australia had about 1.6GW of data centre capacity running in September 2026, on figures from industry body Data Centres Australia and researcher DC Byte. Most of it is in Sydney and Melbourne, which held 1.2GW of the 1.4GW running at the end of 2025.

    How much data centre capacity will Australia have by 2030?

    Data Centres Australia and DC Byte forecast 3.9GW of operating capacity by 2030, with Sydney at 2.0GW and Melbourne at 1.4GW. Ten projects and stages carry 2027 opening dates and five carry 2028 dates, so most of the growth after that still has to be announced.

    Share this article

    Keep reading the market

    Get The Strategic Brief in your inbox every Thursday.

    The leading Australian data centre and AI infrastructure newsletter.

    One email a week. Unsubscribe in one click.

    Your Next Read

    Latest Headlines

    Interested in reaching this audience? Advertise with us.