Founded
2018 as Iris Energy, renamed IREN Limited in November 2024

IREN is an Australian-founded, Sydney-headquartered, Nasdaq-listed neocloud and bitcoin miner, with operating data centres in the United States and Canada, a planned 800MW campus in South Australia, a proposed 900MW campus near Wagga Wagga in New South Wales, and development sites in Texas, Oklahoma and Spain.
Profile summary
Founded
2018 as Iris Energy, renamed IREN Limited in November 2024
Headquarters
Sydney
Listing
NASDAQ:IREN
Co-CEOs
Daniel Roberts and William Roberts
Type
AI cloud, GPU-as-a-service and bitcoin miner
Data centres
Operating at Childress, Texas and in British Columbia, Canada, with development at Sweetwater in Texas, Kiowa in Oklahoma, Bundey in South Australia and Badajoz in Spain; Redbank, a proposed 900MW campus near Wagga Wagga in New South Wales, is in early assessment and outside the company's announced 5GW secured-power portfolio
Power
Running today: Canal Flats 30MW, Prince George 50MW and Mackenzie 80MW in British Columbia (gross), and Horizon 1 at Childress, 50MW of IT load, accepted by Microsoft in August 2026. Childress has 750MW of planned power capacity (gross); across the United States, Canada, Spain and Australia, IREN had about 5GW of power capacity under grid connection agreements or equivalents at 30 June 2026, plus a further multi-GW development pipeline, by the company's account
AI cloud target
About 300MW, the program behind the more than US$4bn revenue run-rate target, now targeted for January 2027 and possibly the end of February 2027, and about 800MW by the end of 2027, by the company's account. Both figures are measured as IT load, which is the power drawn by the computing equipment itself, a smaller figure than the whole building's draw
Anchor contract
Microsoft AI cloud services contract of about US$9.7bn through 2031 over a five-year average term, with 20 per cent of each tranche's value paid before delivery
Disclosed customers
Microsoft, NVIDIA, Cohere, Prometheus, Perplexity, Figure AI, Together AI, Fluidstack, Fireworks AI, Fal AI, Hume AI and Higgsfield AI, together with an AI research lab the company describes only as a leading frontier lab. On 5 November 2026 IREN said it had customer contracts with NVIDIA, Microsoft and 13 other customers
Contracted revenue run-rate
US$1bn of annualised run-rate revenue was operating at 5 Nov 2026. Contracts take it to more than US$4bn, now targeted to be operating by 31 January 2027 and possibly the end of February 2027, after a customer-requested change and supplier timing moved it from the end of 2026. Annualised run-rate revenue is the company's own forward measure, arrived at by scaling current contracted pricing up to a full year. It sits outside the statutory accounts, and the company states that the revenue it eventually reports may be materially lower
FY26 revenue
US$707.0m for the year ended 30 June 2026, of which US$128.8m was AI Cloud Services revenue and US$578.2m was bitcoin mining revenue
Key figures
Planned Australian campus
800MW
Planned power capacity (gross), Bundey, South Australia
Microsoft AI cloud contract
US$9.7bn
Over five years
Power secured, operating and future sites
About 5GW
United States, Canada, Spain and Australia, at 30 June 2026, company figure
Overview
IREN was founded in 2018 as Iris Energy by brothers Daniel and William Roberts, who remain co-chief executives, and took its current name in November 2024. It is headquartered in Sydney and listed on the Nasdaq under IREN, and it combines a neocloud AI cloud business with bitcoin mining.
In June 2026 IREN announced its first Australian data centre campus, an 800MW site at Bundey in South Australia, about 125 kilometres north-east of Adelaide, where it has secured an 800MW transmission connection through four 330kV feeder exits. The company expects energisation to begin from 2028 and says the campus will create more than 200 ongoing roles and 500 construction jobs. In NVIDIA's 9 September 2026 release co-CEO Daniel Roberts said IREN is applying the NVIDIA DSX AI factory reference architecture across its development portfolio, including Bundey.
On 14 October 2026 IREN shared early plans for Redbank, a proposed 900MW data centre campus near Wagga Wagga in regional New South Wales, its second proposed Australian campus. IREN says Redbank is in the early assessment phase and that it is working toward a grid connection; the project is not included in its announced 5GW secured-power portfolio. IREN's Redbank project page lists a project scoping report to the NSW planning department as the next step, followed by a federal environmental referral and an environmental impact statement, and targets initial energisation in 2029.
IREN reported revenue of US$707.0 million for the year ended 30 June 2026, against US$501.0 million a year earlier, with AI Cloud Services revenue rising to US$128.8 million from US$16.4 million as sites converted from bitcoin mining. It reported a net loss of US$702.6 million, which it attributes largely to US$638.8 million of write-downs on retiring mining hardware. Those write-downs reduce the reported value of equipment the company is taking out of service, and are a bookkeeping charge, with the cash staying in the business. On its own adjusted measure of trading profit before interest, tax, depreciation, amortisation and those write-downs, IREN reported US$245.7 million. It describes its 2026 capacity as largely sold out and holds cash, committed equipment financing and customer prepayments of US$14 billion by its own account.
On 5 November 2026 IREN reported revenue of US$228 million for the quarter ended 30 September 2026, up 66 per cent on the June quarter, of which US$200 million came from AI cloud and US$28 million from bitcoin mining, and a net loss of US$263 million. Its revenue backlog rose 22 per cent in the quarter to US$20.3 billion, about two-thirds of it with investment-grade counterparties, by the company's account. IREN now targets more than US$4 billion of annualised run-rate revenue by January 2027, possibly the end of February 2027, instead of the end of 2026, after a customer-requested design change and supplier timing; co-CEO Daniel Roberts said on the results call that Microsoft had asked IREN to reconfigure and upgrade some of the network infrastructure after Horizon 1 was handed over. Of the US$15 billion of capital spending IREN plans from 30 September 2026 to the end of its financial year in June 2027, it says US$9 billion is covered by cash, committed GPU financing and customer prepayments, and the other US$6 billion is to come from targeted financing and prepayments, subject to market conditions.
Deployment
IREN's operating data centres are in the United States and Canada. Its Australian campus at Bundey in South Australia is planned, a second Australian campus, Redbank near Wagga Wagga in New South Wales, is in early assessment, and development is also progressing at Sweetwater in Texas, Kiowa in Oklahoma and Badajoz in Spain. Sources: IREN FY26 results and Form 10-K, 27 August 2026; IREN and Capital Brief, 14 October 2026; IREN, 21 October 2026.
Site
Bundey
Host or location
IREN campus
City/region
South Australia
Scale or hardware
Planned 800MW campus, measured as planned power capacity (gross), with an 800MW grid connection secured through four 330kV feeder exits
Status
Planned, energisation expected from 2028
Site
Redbank
Host or location
Proposed IREN campus
City/region
Near Wagga Wagga, New South Wales
Scale or hardware
Proposed 900MW campus; not included in IREN's announced 5GW secured-power portfolio, by the company's account
Status
Early assessment; a scoping report to the NSW planning department is the next step and initial energisation is targeted for 2029 (IREN project page)
Site
Childress
Host or location
IREN campus
City/region
Texas, United States
Scale or hardware
750MW of planned power capacity (gross); Horizon 1, the first of four 50MW (IT load) liquid-cooled deployments planned at the campus, was delivered to and accepted by Microsoft in August 2026, and Horizons 2 to 4 had reached late-stage construction by 5 November 2026, after Microsoft asked IREN to reconfigure and upgrade some of the network infrastructure for the four buildings' 200MW, by the company's account
Status
Operational and build-out
Site
Sweetwater
Host or location
IREN campus under development
City/region
West Texas, United States
Scale or hardware
2GW hub across Sweetwater 1 (1,400MW) and Sweetwater 2 (600MW), conditionally classed as base load by ERCOT in September 2026; 300MW gross under construction for delivery targeted in Q4 2027, by the company's account
Status
Under construction and planned
Site
Kiowa
Host or location
IREN campus under development
City/region
Oklahoma, United States
Scale or hardware
1,600MW of planned power capacity (gross), company figure
Status
Planned
Site
Badajoz
Host or location
IREN campus under development
City/region
Extremadura, Spain
Scale or hardware
About 300MW of planned power capacity (gross), acquired with Nostrum Group in June 2026; grid-connected power and the civil works licence secured, designed around closed-loop liquid cooling and for compatibility with the NVIDIA DSX AI Factory Platform, company figures
Status
Planned, initial operations targeted for 2028
Site
British Columbia sites
Host or location
IREN renewable-powered sites
City/region
Canada
Scale or hardware
Canal Flats 30MW, Prince George 50MW and Mackenzie 80MW of power capacity (gross), company figures; new liquid-cooled deployments planned at all three during 2027
Status
Operational
Site
Announced sites
Host or location
IREN portfolio
City/region
United States, Canada, Spain and Australia
Scale or hardware
About 5GW of power capacity under grid connection agreements or equivalents at 30 June 2026, plus a further multi-GW pipeline
Status
Secured and in development
| Site | Host or location | City/region | Scale or hardware | Status |
|---|---|---|---|---|
| Bundey | IREN campus | South Australia | Planned 800MW campus, measured as planned power capacity (gross), with an 800MW grid connection secured through four 330kV feeder exits | Planned, energisation expected from 2028 |
| Redbank | Proposed IREN campus | Near Wagga Wagga, New South Wales | Proposed 900MW campus; not included in IREN's announced 5GW secured-power portfolio, by the company's account | Early assessment; a scoping report to the NSW planning department is the next step and initial energisation is targeted for 2029 (IREN project page) |
| Childress | IREN campus | Texas, United States | 750MW of planned power capacity (gross); Horizon 1, the first of four 50MW (IT load) liquid-cooled deployments planned at the campus, was delivered to and accepted by Microsoft in August 2026, and Horizons 2 to 4 had reached late-stage construction by 5 November 2026, after Microsoft asked IREN to reconfigure and upgrade some of the network infrastructure for the four buildings' 200MW, by the company's account | Operational and build-out |
| Sweetwater | IREN campus under development | West Texas, United States | 2GW hub across Sweetwater 1 (1,400MW) and Sweetwater 2 (600MW), conditionally classed as base load by ERCOT in September 2026; 300MW gross under construction for delivery targeted in Q4 2027, by the company's account | Under construction and planned |
| Kiowa | IREN campus under development | Oklahoma, United States | 1,600MW of planned power capacity (gross), company figure | Planned |
| Badajoz | IREN campus under development | Extremadura, Spain | About 300MW of planned power capacity (gross), acquired with Nostrum Group in June 2026; grid-connected power and the civil works licence secured, designed around closed-loop liquid cooling and for compatibility with the NVIDIA DSX AI Factory Platform, company figures | Planned, initial operations targeted for 2028 |
| British Columbia sites | IREN renewable-powered sites | Canada | Canal Flats 30MW, Prince George 50MW and Mackenzie 80MW of power capacity (gross), company figures; new liquid-cooled deployments planned at all three during 2027 | Operational |
| Announced sites | IREN portfolio | United States, Canada, Spain and Australia | About 5GW of power capacity under grid connection agreements or equivalents at 30 June 2026, plus a further multi-GW pipeline | Secured and in development |
Map
Pins show metros with deployed or contracted Australian capacity. States with a mapped deployment are tinted blue.
Capital and partners
Date
3 Nov 2025
Round or instrument
AI cloud services contract
Amount
About US$9.7bn
Valuation / terms
Five years, about US$1.94bn annualised run-rate once fully commissioned, company figure
Lead / anchor investors
Microsoft
Date
May 2026 (closing announced 1 Jun 2026)
Round or instrument
Associated financing
Amount
About US$3.65bn
Valuation / terms
Investment-grade GPU financing for the Microsoft contract at a blended 6.0%, rated A by Fitch; with customer prepayments it funds 96% of the related GPU spend, by the company's account
Lead / anchor investors
Goldman Sachs and J.P. Morgan, joint lead managers and arrangers
Date
May 2026
Round or instrument
NVIDIA arrangement
Amount
About US$3.4bn five-year cloud services contract
Valuation / terms
NVIDIA also has the right to invest up to US$2.1bn in IREN shares, buying up to 30 million shares at US$70 each over five years, subject to conditions including GPU deliveries and regulatory approvals
Lead / anchor investors
NVIDIA
Date
Jul 2026
Round or instrument
AI cloud services contracts
Amount
About US$2.8bn total contract value
Valuation / terms
Multi-year
Lead / anchor investors
Prometheus, Perplexity, Together AI and others
Date
27 Aug 2026
Round or instrument
GPU financings
Amount
About US$2.8bn
Valuation / terms
Announced with the FY26 results; includes about US$2.4bn led by Blue Owl and PIMCO at a 9.0% fixed rate for the Mackenzie expansion, by the company's account
Lead / anchor investors
Blue Owl and PIMCO, for the US$2.4bn
| Date | Round or instrument | Amount | Valuation / terms | Lead / anchor investors |
|---|---|---|---|---|
| 3 Nov 2025 | AI cloud services contract | About US$9.7bn | Five years, about US$1.94bn annualised run-rate once fully commissioned, company figure | Microsoft |
| May 2026 (closing announced 1 Jun 2026) | Associated financing | About US$3.65bn | Investment-grade GPU financing for the Microsoft contract at a blended 6.0%, rated A by Fitch; with customer prepayments it funds 96% of the related GPU spend, by the company's account | Goldman Sachs and J.P. Morgan, joint lead managers and arrangers |
| May 2026 | NVIDIA arrangement | About US$3.4bn five-year cloud services contract | NVIDIA also has the right to invest up to US$2.1bn in IREN shares, buying up to 30 million shares at US$70 each over five years, subject to conditions including GPU deliveries and regulatory approvals | NVIDIA |
| Jul 2026 | AI cloud services contracts | About US$2.8bn total contract value | Multi-year | Prometheus, Perplexity, Together AI and others |
| 27 Aug 2026 | GPU financings | About US$2.8bn | Announced with the FY26 results; includes about US$2.4bn led by Blue Owl and PIMCO at a 9.0% fixed rate for the Mackenzie expansion, by the company's account | Blue Owl and PIMCO, for the US$2.4bn |
Technology
IREN runs GPU-as-a-service AI cloud infrastructure alongside bitcoin mining, siting capacity around large power campuses with access to renewable generation. Its disclosed anchor contract is a five-year AI cloud services agreement with Microsoft valued at about US$9.7 billion, announced in November 2025. NVIDIA has separately contracted IREN for about US$3.4 billion of managed GPU cloud services, to be served from about 60MW at the Childress campus in Texas and ramping from early 2027, and holds a five-year warrant to buy up to 30 million IREN shares at US$70 each.
IREN completed the acquisitions of cloud software provider Mirantis in August 2026 and of Nostrum Group, adding software and services capability and extending the platform into Europe. On 21 October 2026, at NVIDIA GTC Berlin, IREN established IREN Europe, the holding company for its European operations, and said it plans to offer AI cloud services, including managed services, from Badajoz to customers with European data residency requirements, alongside the k0rdent AI software it gained with Mirantis. The company says NVIDIA awarded it Exemplar Cloud status, a designation NVIDIA gives cloud providers whose deployments pass its own testing, on the GB300 NVL72 platform following testing of the Horizon 1 deployment at Childress.
Comparison
Neutral peer comparison using stable, sourced axes. Figures that move are attributed to company statements or reports.
Company
Listing
NASDAQ:SHAZ
Australian capacity
Roughly 1,000 GPUs live at NEXTDC M3 in Melbourne, plus Equinix SY3 and SY5 and GreenSquareDC SYD1 in Sydney. 212MW expected across Australia and New Zealand in 2027, 129MW of it contracted, company figure
GPU platform
NVIDIA B200 / B300, GB300 planned
Deployment & cooling
Hosted mainly in NEXTDC facilities
Backing
Situational Awareness, Oaktree, public markets
Company
Listing
Private; ASX float withdrawn 9 October 2026
Australian capacity
About 42MW running in Melbourne. Project Southgate in Tasmania has Launceston consented for 90MW, Bell Bay approved for 288MW (under appeal) and Wesley Vale about 52MW lodged
GPU platform
NVIDIA GB300
Deployment & cooling
Own immersion-cooled AI factories
Backing
Coatue, NVIDIA, Jane Street equity; Blackstone equity and debt
Company
IREN
Listing
NASDAQ:IREN
Australian capacity
None running in Australia yet. Planned 800MW campus at Bundey, SA, and proposed 900MW Redbank campus near Wagga Wagga, NSW. Operating data centres are in the US and Canada
GPU platform
NVIDIA GPU clusters
Deployment & cooling
Own North American data centres; Bundey campus planned
Backing
Public markets; Microsoft, NVIDIA and AI research lab contracts
| Company | Listing | Australian capacity | GPU platform | Deployment & cooling | Backing |
|---|---|---|---|---|---|
| Sharon AI | NASDAQ:SHAZ | Roughly 1,000 GPUs live at NEXTDC M3 in Melbourne, plus Equinix SY3 and SY5 and GreenSquareDC SYD1 in Sydney. 212MW expected across Australia and New Zealand in 2027, 129MW of it contracted, company figure | NVIDIA B200 / B300, GB300 planned | Hosted mainly in NEXTDC facilities | Situational Awareness, Oaktree, public markets |
| Firmus | Private; ASX float withdrawn 9 October 2026 | About 42MW running in Melbourne. Project Southgate in Tasmania has Launceston consented for 90MW, Bell Bay approved for 288MW (under appeal) and Wesley Vale about 52MW lodged | NVIDIA GB300 | Own immersion-cooled AI factories | Coatue, NVIDIA, Jane Street equity; Blackstone equity and debt |
| IREN | NASDAQ:IREN | None running in Australia yet. Planned 800MW campus at Bundey, SA, and proposed 900MW Redbank campus near Wagga Wagga, NSW. Operating data centres are in the US and Canada | NVIDIA GPU clusters | Own North American data centres; Bundey campus planned | Public markets; Microsoft, NVIDIA and AI research lab contracts |
Latest coverage
17 Nov 2026
IREN has lodged the first planning document for its Redbank campus near Wagga Wagga. It shows five data halls, about 600MW of IT load and first power in 2029.
15 Nov 2026
Jensen Huang has resigned as NVIDIA chief executive amid the Megaspeed spying allegations. What it means for Australia's AI builds and NVIDIA's chips to 2028.
6 Nov 2026
Sydney-based IREN's Q1 FY27 results push its US$4bn revenue goal to January 2027 after a Microsoft change in Texas. Its SEC filing says it pays no late penalty for the Microsoft change.
6 Nov 2026
Microsoft is tightening oversight of IREN, Nscale and Nebius after delays in Texas and Essex. IREN's Bundey campus in SA has a signed grid deal for up to 800MW.
Common questions
IREN is an Australian-founded, Sydney-headquartered AI cloud and bitcoin-mining company listed on the Nasdaq.
Yes. It was founded in Australia and is headquartered in Sydney, though its operating data centres are in North America.
Not one that is running yet; its operating data centres are in North America. It announced its first Australian campus in June 2026, an 800MW site at Bundey in South Australia, with energisation expected from 2028. On 14 October 2026 it shared early plans for a second, Redbank, a proposed 900MW campus near Wagga Wagga in New South Wales, which is in early assessment and not included in its announced 5GW secured-power portfolio.
A five-year AI cloud services contract valued at about US$9.7 billion, announced in November 2025, covering four 50MW buildings at Childress, Texas. Microsoft accepted the first, Horizon 1, in August 2026, and IREN said on 5 November 2026 that Horizons 2 to 4 had reached late-stage construction.
Yes. In the year ended 30 June 2026 IREN reported US$578.2 million of bitcoin mining revenue and US$128.8 million of AI Cloud Services revenue, and describes itself as transitioning sites from mining to AI Cloud.