IREN starts NSW approval for 900MW Wagga Wagga data centre
By Winston Su, Editor · · Add us as a preferred source on Google

At a glance
IREN has lodged a scoping report for its Redbank data centre campus near Wagga Wagga, which starts the NSW approval process for large projects.
The campus is designed to draw up to 900MW at peak and support about 600MW of IT load across five data halls.
Capacity is planned in 75MW blocks at roughly six-monthly intervals, from 75MW in 2029 to the full 900MW in 2035.
The report expects about 1,100 workers on site at the construction peak, with a camp of up to 750 beds for workers from outside the area, and more than 200 full-time equivalent staff once the campus is finished.
The company also wants Wagga Wagga's planning rules changed so a data centre is allowed on the rural site.
IREN has lodged the first planning document for its 900MW Redbank data centre campus near Wagga Wagga, in southern New South Wales.
The Nasdaq-listed AI cloud company was founded in Sydney in 2018 by brothers Daniel and Will Roberts. It announced Redbank on 14 October, its second Australian campus after the planned 800MW site at Bundey in South Australia. Together, Redbank and Bundey total 1.7GW.
Planning firm Urbis prepared the scoping report, dated 10 November, for IREN subsidiary TAS 1 Holdings. The report asks the NSW planning department for the Secretary's Environmental Assessment Requirements (SEARs), the list of studies the full application must include.
The department is now preparing that list, with advice from Wagga Wagga City Council and state agencies, under its published process. The company then writes its environmental study, which goes out for public comment before a decision is made.
If the project is approved after that public comment, the report expects about 1,100 people on site at the construction peak and more than 200 full-time equivalent staff once the campus is finished.
The filing puts Redbank's IT load at about 600MW, two thirds of the 900MW headline figure.
Redbank's capacity is planned in 75MW blocks from 2029
The 900MW is the most the campus could draw at any one moment. The design supports about 600MW of IT load at a design PUE (power usage effectiveness) of about 1.3, an average draw of about 780MW at full load.
Those 600MW sit in five data halls on Stantec's concept plans. One is labelled 200MW of IT and the other four 100MW each, and the plans show none taller than about 12.5 metres. A warehouse and an administration and security building are planned on the western side, behind a landscaped buffer along Plumpton Road.
After early works, capacity is planned to arrive in blocks of about 75MW, or about 50MW of IT, at roughly six-monthly intervals. The report gives "an indicative cumulative gross load ramp of 75 MW in 2029 and 900 MW in 2035", with construction continuing while the earlier blocks operate.
All those blocks are proposed under a single application, with staged delivery inside that one consent. For Bundey, IREN's power tender also has load coming online in 75MW steps, energy publication PeakLoad reported on 6 November.
IREN picks Wagga Wagga land already crossed by high-voltage lines
The campus is planned for a site of roughly 600 hectares at Rowan, south-east of Wagga Wagga and next to the Gregadoo Waste Management Centre. It is mostly cleared grazing land that already hosts high-voltage transmission lines, and the wider area carries three 330kV and two 132kV lines. The report says the land is not identified as high-value farmland.
On that land, data centres are not allowed under the current rural zones. The planning proposal asks to add the data centre and a temporary workers' camp as permitted uses on this site only. The rural zoning stays in place, and the land is not rezoned for industry.
In October, executive director Lindsay Ward gave the company's reasons for the site. "We are attracted to the site as it is not on prime agricultural land, it's near an electricity network and Wagga has all the required support services," he told The Daily Advertiser.
Three underground cables are planned to Transgrid's Wagga Wagga substation
The site lies about 2.5 kilometres from Transgrid's Wagga Wagga substation. The plan calls for three new 330kV feeder bays there and three 330kV underground cables to an on-site 330/132kV substation with four 375MVA transformers.
Connection planning with Transgrid has run since May 2026 "on the basis of a proposed 900 MW connection", the report says. IREN will pay for the dedicated connection assets. In October, it said Redbank was not part of its 5GW secured-power portfolio.
The site sits in a corridor of new energy investment, the report says. Transgrid's HumeLink line, which will connect Wagga Wagga, Bannaby and Maragle, is due to finish construction in 2027. Transgrid's September newsletter put the Wagga Wagga substation upgrade at about 80 per cent complete.
Beyond the grid connection, IREN intends to buy renewable energy and firming products as each stage comes online.
Each GPU hall is designed for liquid cooling
Each stage's halls are designed to circulate coolant through cold plates on the GPUs and other high-performance chips, with heat leaving through dry coolers or chillers. Top-up water is expected to be about 1 per cent of the closed system's volume a year. Talks with Riverina Water began in March.
Alongside that cooling system, IREN plans about 444 diesel generators for backup, holding about 7.3 megalitres of fuel, enough for about 34 hours at full load. With that much fuel, the campus is expected to need an environment protection licence from the state.
About 1,100 workers are expected at the construction peak
To house that workforce, a camp of up to 750 beds is planned for workers from outside the area, opening with about 300 beds and growing to full size by month 12. It is planned with one person per room and a 24-hour medical centre. The report expects operational jobs to grow from about 50 at first power to more than 200.
Wagga Wagga City Council has met the company regularly since February 2026, according to the report's consultation table. Council asked for the workers' camp to be part of the project, for construction traffic to avoid unsuitable local roads and for IREN to deliver any road upgrades. It also encouraged the company to look at moving major equipment by rail.
Beyond the council, IREN wrote to neighbours, offered one-on-one meetings to the nearest landowners and held drop-in sessions in Wagga Wagga on 4 and 5 November. A community benefit program will be developed with the council while the full study is prepared, and the two are discussing a planning agreement. Its Redbank website says IREN expects to pay the council more than A$200 million over 30 years, including council rates.
An estimated cost report will accompany the development application, according to the scoping report. Capital Brief reported in October that Redbank would cost more than A$10 billion, citing a source familiar with the project.
NSW's planning department will decide which studies IREN must complete
IREN's full study is called an environmental impact and rezoning statement. It covers the environmental assessment and the case for the planning rule change, so both are assessed together.
The scoping report proposes the matters for that study. They include an economic impact and cost-benefit assessment, traffic and oversize transport routes, noise, air quality from generator testing, visual impact, flooding, bushfire, Aboriginal cultural heritage and greenhouse gas emissions.
Early surveys found vegetation consistent with a critically endangered box gum woodland, according to the report. The company will assess it in a biodiversity report, and a referral under the federal environment law is proposed. The layout has generally sought to avoid higher-value biodiversity features where practicable, the report adds.
CDC's 1.4GW campus next door is already preparing its environmental study
The same department issued study requirements on 15 October for CDC Data Centres' proposed campus of up to 1.4GW at Gregadoo, about 750 metres east of Redbank, according to IREN's report. CDC is now preparing its environmental study.
CDC has offered Wagga Wagga a community benefits package worth up to A$225 million, and its founder and chief executive, Greg Boorer, has called Wagga Wagga the best location in NSW for a project like this.
What to watch
The study requirements: NSW rules say the department issues them within 28 days of the scoping report being published on the portal.
The federal referral: IREN proposes to refer Redbank under the federal environment law shortly after the scoping report.
A grid agreement: connection planning with Transgrid continues, and IREN said in October that Redbank sits outside its 5GW of secured power.
HumeLink: Transgrid expects construction to finish in 2027.
Keep reading the market
Get The Strategic Brief in your inbox every Thursday.
The leading Australian data centre and AI infrastructure newsletter.
Your Next Read

IREN plans 900MW Redbank data centre at Wagga Wagga

CDC offers A$225m community benefits for Wagga data centre

Wagga Wagga is the best NSW data centre site, CDC's Greg Boorer says
Latest Headlines
US acts to stop China renting AI chips in Asian data centres
17 Nov 2026Firmus seeks upfront payments from NVIDIA and Meta in A$4.4bn raise
17 Nov 2026Sharon AI misses on revenue as its price per megawatt climbs
17 Nov 2026Jensen Huang eyes NVIDIA comeback as allies lobby the board
17 Nov 2026Tasmanian data centres would use 0.04% of TasWater's water
16 Nov 2026
Interested in reaching this audience? Advertise with us.