Tasmanian data centres would use 0.04% of TasWater's water
By Winston Su, Editor · · Add us as a preferred source on Google

At a glance
Six data centre proponents are in discussion with TasWater about water supply: three in Tasmania's north-west, two in the north and one in the south.
TasWater told Certified Strategic the combined demand of the large proposals on its network is about 30 megalitres a year, against the 84,247 megalitres it supplies each year.
Some proposed connections cap use at 15 megalitres a year and allow TasWater water for cooling only between 1 May and 30 September, with supply TasWater can restrict at any time.
Two of the six sit outside TasWater's serviced areas and cannot connect to its network as things stand.
Hansard transcripts of the inquiry hearings may be published within weeks, and the inquiry has no set reporting date.
Tasmania's parliamentary inquiry into AI data centres has heard that six data centre developers seeking water from TasWater, the state's water utility, are preparing development applications. The Greens made the evidence public on 12 November 2026, and Greens MP Tabatha Badger asked how much water the six plan to use.
TasWater gave Certified Strategic its figures in a statement attributable to Matt Derbyshire, its general manager of sustainable infrastructure services. It puts the combined demand of the proposed large data centres at about 30 megalitres (30 million litres) a year, subject to supply conditions. That is about 0.04 per cent of the 84,247 megalitres it supplies each year.
Most proposals seeking TasWater supply are in the north and north-west
Three of the six proposals are in the north-west, two in the north and one in the south of the state, TasWater said. Two cannot connect to its network for now, because they sit outside the areas TasWater services.
Water supply is governed by individual contracts tailored to each customer's operations, TasWater said. "Any approved new data centre connections would be metered and charged in accordance with TasWater's regulated pricing arrangements," Derbyshire said. He added that TasWater would keep working with proponents through the normal planning process, "while exploring opportunities to use alternative water sources where practical".
Some TasWater connections would allow cooling water from May to September
The proposed connections are "relatively standard", under 100mm in diameter, TasWater said. Some come with conditions:
water for cooling may be used only between 1 May and 30 September inclusive
a maximum annual volume of 15 megalitres
a maximum instantaneous flow of 5.0 litres per second
TasWater may restrict or suspend supply at any time, including when the system is constrained
a smart flow meter on the connections, so TasWater can monitor use live
A data centre connected on those terms could not use TasWater water for cooling from October to April. Firmus said in its September submission to the inquiry that its Launceston site is modelled to run without cooling water for 97 to 99 per cent of its operating hours.
TasWater weighs each application against the cumulative load
Each large-load water application gets hydraulic modelling and an assessment of system capacity, and TasWater takes into account "the cumulative impact of all proposals", Derbyshire said. The Greens raised cumulative impact after the hearing, along with community consultation before development applications are lodged.
The state's final expectations for data centre and AI infrastructure developers, released on 13 November 2026, ask each project for forecasts of maximum and average annual water demand. Developers are to engage early with water suppliers, pay the cost of any water connection, plan for supply disruptions in periods of low rainfall, and report every quarter on their water sources and the share that is potable, recycled or non-potable. The same document asks facilities above 20MW for a community fund contribution of at least A$3,000 per MW a year.
Tasmania's proposed data centres could need up to about 1,150MW
On power, the document the government tabled in parliament on 8 September 2026 lists Firmus's three Tasmanian sites, which the company told the inquiry would need 444MW in total. It also lists six confidential proposals that could draw up to 705MW, two of them at 200MW to 300MW each. A Viridis facility in Burnie of under 1MW is also on the list. Together, that puts Tasmania's proposed data centres at up to about 1,150MW.
What to watch
The Hansard transcripts. The inquiry secretariat told Certified Strategic on 16 November 2026 that transcripts of the hearings may be available within the next couple of weeks, once the secretariat and witnesses have checked them and they are cleared for publication. They will carry the evidence given by TasWater and by the Office of the Coordinator-General, the agency that attracts investment to Tasmania.
The development applications. The proponents are preparing applications through local councils, and the state's expectations ask each project for forecasts of maximum and average annual water demand.
The committee's report. The resolution that set up the inquiry gives no reporting date, the secretariat said.
Keep reading the market
Get The Strategic Brief in your inbox every Thursday.
The leading Australian data centre and AI infrastructure newsletter.
Your Next Read

Firmus puts its Tasmanian power need at 444MW in inquiry submission

Tasmanian data centres to pay communities A$3,000/MW a year

What Firmus's pulled IPO means for Tasmania and Maas Group
Latest Headlines
US acts to stop China renting AI chips in Asian data centres
17 Nov 2026Firmus seeks upfront payments from NVIDIA and Meta in A$4.4bn raise
17 Nov 2026Sharon AI misses on revenue as its price per megawatt climbs
17 Nov 2026IREN starts NSW approval for 900MW Wagga Wagga data centre
17 Nov 2026Jensen Huang eyes NVIDIA comeback as allies lobby the board
17 Nov 2026
Interested in reaching this audience? Advertise with us.