Sydney Data Centre Infrastructure Map
53 facilities and 15 substations: 27 operational, 9 under construction, 17 planned. Data as at 2 November 2026.
Tap a site for details. Use Controls to filter by status or operator.
Changes since October 2026
- 2 November 2026Capacity figures we could not source now read "Capacity not published", and the totals count only sites with a published figure. Source
- 2 November 2026Substation figures added as the networks publish them: firm rating and peak demand for eight Endeavour Energy and two Ausgrid substations, and Transgrid's available capacity for load at Sydney West and Vineyard. Source
- 2 November 2026coNEXA is extending its AquaNet recycled water network to NEXTDC S4 at Horsley Park, supplying up to 16 million litres a day, with first water expected in late 2027 (29 October 2026). Source
- 2 November 2026Stockland's second Macquarie Park consent, the Road 1 Data Centre, was approved on 1 October 2026 with a power capacity of 34.3MW. Source
- 2 November 2026Microsoft's Honeman Close data centre at Huntingwood was approved on 1 October 2026, for 96MW. Source
- 27 October 2026Goodman Project Mars in Lane Cove West removed from the map. Goodman Group withdrew the 90MW proposal on 28 September 2026, and the NSW Planning Portal lists it as withdrawn. Source
- 27 October 2026Lane Cove DC Alliance at 16-20 Mars Road, Lane Cove West, removed from the map. The proposal was withdrawn from the NSW Investment Delivery Authority before any application was lodged, In the Cove reported on 20 October 2026. Source
- 19 October 2026GreenSquareDC SYD1 Stage 1 is now operational at 15MW in Norwest, in a 1995 former IBM and Kyndryl data centre. First customer: Sharon AI. Source
All Sydney data centres tracked
The facilities on the map above, as a list. Operator names link through to their Certified Strategic profile, or to their listing in the directory.
| Facility | Operator, suburb | MW, status |
|---|---|---|
| AirTrunk SYD3 | AirTrunkHuntingwood | 400 MWTotal campus capacity, measure not statedOperational |
| AirTrunk SYD1 | AirTrunkHuntingwood | 130 MWTotal campus capacity, measure not statedOperational |
| AirTrunk SYD2 | AirTrunkLane Cove West | 120 MWTotal campus capacity, measure not statedOperational |
| NEXTDC S3/S6 | NEXTDCArtarmon | 93.5 MWOperational |
| NEXTDC S2 | NEXTDCMacquarie Park | 30 MWOperational |
| Digital Realty SYD10/SYD11 | Digital RealtyErskine Park | 25 MWOperational |
| Telstra InfraCo St Leonards | Telstra InfraCoSt Leonards | 20 MWOperational |
| Macquarie DC IC2/IC3 | Macquarie Data CentresMacquarie Park | 18 MWOperational |
| NEXTDC S1 | NEXTDCMacquarie Park | 16 MWOperational |
| GreenSquareDC SYD1 | GreenSquareDCNorwest | 15 MW15MW first stage, measure not stated, operator's figureOperational |
| DCI SYD01 | DCI Data CentresEastern Creek | 11 MWOperational |
| Equinix SY6 | EquinixSilverwater | 9 MWIT load, 2012 contract figureOperational |
| Macquarie DC IC1 | Macquarie Data CentresHaymarket | 2 MWIT load, builtOperational |
| 5G Networks NSDC | 5G NetworksSt Leonards | 1.5 MW1.5MW power availability, operator's figureOperational |
| 5G Networks SDC | 5G NetworksPyrmont | 1.5 MW1.5MW of power, measure not stated, operator's figureOperational |
| AWS Eastern Creek | AWSEastern Creek | Capacity not publishedOperational |
| AWS Smeaton Grange | AWSSmeaton Grange | Capacity not publishedOperational |
| CDC EC1-EC4 | CDC Data CentresEastern Creek | Capacity not publishedOperational |
| CDC EC5/EC6 | CDC Data CentresEastern Creek | Capacity not publishedOperational |
| DigiCo SYD1 | DigiCoUltimo | Capacity not publishedOperational |
| Equinix SY1/SY2 | EquinixMascot | Capacity not publishedOperational |
| Equinix SY3 | EquinixAlexandria | Capacity not publishedOperational |
| Equinix SY4/SY5 | EquinixAlexandria | Capacity not publishedOperational |
| Keppel Gore Hill | Keppel DCArtarmon | Capacity not publishedOperational |
| Unisys Rhodes | UnisysRhodes | Capacity not publishedOperational |
| Vocus SYD01 | Vocus CommunicationsAlexandria | Capacity not publishedOperational |
| Vocus SYD04 | Vocus CommunicationsRosebery | Capacity not publishedOperational |
| CDC Marsden Park | CDC Data CentresMarsden Park | 504 MWUnder construction |
| NEXTDC S4 | NEXTDCHorsley Park | 365 MWIT load, full campus (250MW in progress)Under construction |
| Project Blue Tongue | Operator not namedWetherill Park | 132 MWIT load, two buildings (160.85MW maximum power)Under construction |
| Goodman SYD01 | Goodman GroupArtarmon | 80 MWIT load at the 2025 consent (consent now 90MVA)Under construction |
| DCI SYD02 | DCI Data CentresEastern Creek | 63 MWIT load, approved capUnder construction |
| Starwood/Doma/Telstra | Starwood/Doma/TelstraMinchinbury | 62 MWUnder construction |
| DigiCo SYD1 expansion | DigiCoUltimo | 52 MW52MW expansion, measure not stated, operator's figureUnder construction |
| Macquarie IC3 Super West | Macquarie Data CentresMacquarie Park | 47 MWUnder construction |
| Microsoft Kemps Creek | MicrosoftKemps Creek | Capacity not publishedUnder construction |
| AirTrunk/ISPT Mamre Rd | AirTrunk / ISPTKemps Creek | 1,000 MW1GW power capacity on the NSW Planning Portal; the application's own figures run from 600MW to 1.2GWPlanned |
| NEXTDC S7 (OpenAI) | NEXTDCEastern Creek | 550 MWIT load, planned (612MW in the planning application)Planned |
| STACK SYD01 | STACK InfrastructureErskine Park | 450 MWTotal power consumption, proposal under assessmentPlanned |
| Goodman Project Atlas | Goodman GroupEastern Creek | 348 MWTotal power consumption (500MVA supply)Planned |
| Stockland Kemps Creek | StocklandKemps Creek | 342 MWIT load, 342 to 360MW range (amended scheme)Planned |
| Microsoft Honeman Close | MicrosoftHuntingwood | 96 MWIT load, approved (140MVA total)Planned |
| Goodman Project Duke | Goodman GroupMascot | 85 MWIT load, approved (120MW total power)Planned |
| GreenSquareDC SYD1 Stage 2 | GreenSquareDCNorwest | 80 MWPlanned |
| NEXTDC S5 | NEXTDCMacquarie Park | 80 MWIT load, plannedPlanned |
| ISPT Julius Avenue | ISPTNorth Ryde | 76 MWIT load, amended scheme (120MW total power)Planned |
| Digital Realty SYD12 | Digital RealtyMacquarie Park | 70 MWTotal power consumption, proposalPlanned |
| Goodman Project Pluto | Goodman GroupGuildford West | 68 MWIT load, approved (100MW total power)Planned |
| AWS Gregory Hills | AWSGregory Hills | 53 MWPlanned |
| Stockland/EdgeConneX MPark | Stockland / EdgeConneXMacquarie Park | 51.4 MWIT load, approved building (76.4MW maximum power)Planned |
| 192 Narellan Road, Campbelltown (planned) | Operator not namedCampbelltown | 100MW total loadTotal load, proposal (no IT load published)Planned |
| AIMS Bella Vista | AIMS CapitalBella Vista | Capacity not publishedPlanned |
| Stockland Wetherill Park | StocklandWetherill Park | Capacity not publishedPlanned |
Substations on this map
Figures are as each network publishes them. Networks rarely publish spare capacity, so cells without a published figure say not published.
| Substation | Network | Firm rating (N-1) | Peak demand | Network's own figure | Source |
|---|---|---|---|---|---|
| Sydney West Bulk Supply Point | NetworkTransgrid | Firm rating (N-1)not published | Peak demandnot published | Network's own figure64 MW now, 0 MW in 5 yearsAvailable capacity for load, 132 kV | SourceTransgrid Transmission Annual Planning Report portal, September 2026 |
| Kemps Creek Substation | NetworkTransgrid | Firm rating (N-1)not published | Peak demandnot published | Network's own figurenot published | Sourcenot published |
| Vineyard Bulk Supply Point | NetworkTransgrid | Firm rating (N-1)not published | Peak demandnot published | Network's own figure130 MW now, 0 MW in 5 yearsAvailable capacity for load, 132 kV | SourceTransgrid Transmission Annual Planning Report portal, September 2026 |
| Macquarie Park Zone Substation | NetworkAusgrid | Firm rating (N-1)114.32 MVA | Peak demand61.84 MVAsummer 2024/25 | Network's own figurenot published | SourceAusgrid Distribution and Transmission Annual Planning Report 2025, Substation Capacity and Demand Forecast, December 2025 |
| Lane Cove Switching Station | NetworkAusgrid | Firm rating (N-1)not published | Peak demandnot published | Network's own figurenot published | Sourcenot published |
| Mason Park Switching Station | NetworkAusgrid | Firm rating (N-1)not published | Peak demandnot published | Network's own figurenot published | Sourcenot published |
| Alexandria Subtransmission Substation | NetworkAusgrid | Firm rating (N-1)142.9 MVA | Peak demand24.54 MVAsummer 2024/25 | Network's own figurenot published | SourceAusgrid Distribution and Transmission Annual Planning Report 2025, Substation Capacity and Demand Forecast, December 2025 |
| Eastern Creek Substation | NetworkEndeavour Energy | Firm rating (N-1)45 MVA | Peak demand21.52 MVA2025 | Network's own figurenot published | SourceEndeavour Energy Distribution Annual Planning Report 2025 portal, December 2025 |
| Mamre Zone Substation | NetworkEndeavour Energy | Firm rating (N-1)90 MVA | Peak demand65.02 MVA2025 | Network's own figurenot published | SourceEndeavour Energy Distribution Annual Planning Report 2025 portal, December 2025 |
| Marsden Park Substation | NetworkEndeavour Energy | Firm rating (N-1)45 MVA | Peak demand22.73 MVA2025 | Network's own figurenot published | SourceEndeavour Energy Distribution Annual Planning Report 2025 portal, December 2025 |
| Huntingwood Substation | NetworkEndeavour Energy | Firm rating (N-1)90 MVA | Peak demand46.22 MVA2025 | Network's own figurenot published | SourceEndeavour Energy Distribution Annual Planning Report 2025 portal, December 2025 |
| Rooty Hill Zone Substation | NetworkEndeavour Energy | Firm rating (N-1)45 MVA | Peak demand30.16 MVA2025 | Network's own figurenot published | SourceEndeavour Energy Distribution Annual Planning Report 2025 portal, December 2025 |
| Wetherill Park Substation | NetworkEndeavour Energy | Firm rating (N-1)45 MVA | Peak demand27.23 MVA2025 | Network's own figurenot published | SourceEndeavour Energy Distribution Annual Planning Report 2025 portal, December 2025 |
| Arndell Park Substation | NetworkEndeavour Energy | Firm rating (N-1)45 MVA | Peak demand25.53 MVA2025 | Network's own figurenot published | SourceEndeavour Energy Distribution Annual Planning Report 2025 portal, December 2025 |
| Blacktown Transmission Substation | NetworkEndeavour Energy | Firm rating (N-1)360 MVA | Peak demand204.15 MVA2025 | Network's own figurenot published | SourceEndeavour Energy Distribution Annual Planning Report 2025 portal, December 2025 |
About This Map
This map tracks data centres across Greater Sydney, from operating campuses to sites under construction and projects that have been announced, lodged or approved. Capacity is IT load in megawatts unless the site's entry names another measure. Figures are as the operator or the planning application states them, and sites without a published figure are marked "Capacity not published".
Records come from operator announcements and ASX releases, the NSW Planning Portal, and the planning reports published by Transgrid, Ausgrid and Endeavour Energy. Each record carries the source it came from.
The map is refreshed on the first business day of each month, and the date above the map is the date the data was last checked, not the date you opened the page.
Substation locations: NSW Spatial Services. Constraint and augmentation detail: Transgrid Western Sydney RIT-T reports 2024, Transgrid network capacity update June 2026, Ausgrid Wallumatta contingent project application 2025, NSW distributors' submission to the NSW data centres inquiry 2026.
Map researched and maintained by CertifiedStrategic.com.
Related Analysis
Insights
Australian data centre capacity: the 2026 to 2030 guide
Read the full analysisInsights
Data centres in Western Sydney: who is building where
Read the full analysisInsights
Transgrid says data centres stop the NSW grid emptying at midday
Read the full analysisInsights
NSW trades 75-day data centre approvals for wind and storage
Read the full analysisInsights
A rare Macquarie Park site shows what data centres look for
Read the full analysisInsights
OpenAI's Sydney deal is still a memorandum of understanding
Read the full analysisCapacity
Australian capacity requirements
For neoclouds, AI labs and enterprises planning an Australian deployment. We shortlist sites against your GPU platform, scale, market and ready-for-service date. Operators with capacity coming online are welcome to get in touch.
Connect on LinkedInKeep reading the market
Get The Strategic Brief in your inbox every Thursday.
The leading Australian data centre and AI infrastructure newsletter.