    Stockland plans A$5bn Kemps Creek AI data centre with EdgeConneX

    By Winston Su, Editor · · Add us as a preferred source on Google

    Stockland plans A$5bn Kemps Creek AI data centre with EdgeConneX
    Stockland's 365MW Kemps Creek campus with partner EdgeConneX is costed at about A$5 billion and aimed at AI and hyperscale customers.

    At a glance

    • Stockland plans a campus of up to 365MW of IT load on Aldington Road at Kemps Creek, in Western Sydney, with its data centre partner EdgeConneX. The cost is about A$5 billion.

    • Its target customer is "AI/Hyperscaler", according to Stockland, and the halls are designed for both air-cooled and liquid-cooled computing.

    • Under the plan, power comes straight from Transgrid's 330kV network, through a new switching station and a 1,000MVA substation on the site.

    • The cost report estimates the build will support about 1,375 full-time equivalent jobs, and about 84 staff would run the campus.

    • The plan is open for public comment until 17 December 2026.

     

    Stockland plans a A$5 billion data centre campus on Aldington Road at Kemps Creek, in Western Sydney, with its joint venture partner EdgeConneX. Its environmental impact statement (EIS) has been open for public comment since 19 November 2026. It sets out a maximum IT load of 365MW and two buildings with 33 data halls on a 30.5-hectare site in the Mamre Road industrial precinct.

    The ASX-listed property company describes itself as one of Australia's largest diversified property groups, and is turning parts of its logistics land in Sydney and Melbourne into data centre sites. It shares that business 50/50 with EdgeConneX, a global data centre operator.

    Stockland's quarterly update of 19 October lists its 50 per cent Kemps Creek interest with a target customer of "AI/Hyperscaler".

    EdgeConneX partnership targets AI and hyperscale customers

    Chief executive Tarun Gupta told shareholders at the annual meeting that the partnership will "develop, own and operate an Australian portfolio of data centres". The Aldington Road documents name EdgeConneX as Stockland's data centre joint venture partner.

    AI and hyperscale customers would get halls designed for both air-cooled and higher-density liquid-cooled computing. That design will let the campus support "artificial intelligence, cloud computing and other advanced digital workloads", according to the EIS. The EIS plans 228 dry air-cooled chillers on the roofs, with a cooling system designed to use no water. A power usage effectiveness of about 1.25 is possible with that design, the EIS says, and the extra acoustic treatment needed for the chillers takes the expected figure to 1.36.

    Access to the M12 Motorway, Elizabeth Drive and Western Sydney International Airport is among the reasons the EIS gives for choosing the site, along with large industrial land parcels with power and utilities nearby. CDC Data Centres' Kemps Creek campus is also in the Mamre Road area, and both are on our Sydney data centre map.

    Kemps Creek is one of several Stockland data centre sites at different stages. Its Road 1 data centre at Macquarie Park was approved on 1 October, and its Wetherill Park site is waiting on its study requirements from the planning department. The quarterly update also lists about 450MW of secured power at three other sites in the pipeline, MPark Stage 2, Cherry Lane and Brooklyn.

    Stockland plans a direct link to Transgrid's 330kV network

    Under the EIS, a new Ropes Creek switching station would cut into Transgrid's 330kV Line 14, with room for a later connection to Line 30, and feed a 330/33kV substation on the site. Symphony Infrastructure is to deliver the switching station, with Transgrid then operating and maintaining it.

    Of the substation's 1,000MVA, 500MVA is allocated to the data centre, and the scoping report sets the other half aside as future capacity for the neighbouring 200 Aldington Road estate. The same report says the switching station and substation will pass to Transgrid's ownership once commissioned, as shared network infrastructure. Network modelling has been finalised and provided to Transgrid for review, according to the EIS, and the substation is due to run by the time the first building is finished.

    Kemps Creek plan has grown to 365MW since March

    The NSW Investment Delivery Authority, the state's fast-track body for large projects, endorsed the project on 27 March 2026. The planning department's study requirements, issued in April, covered a campus with total power consumption of up to 245MW. By September, amended requirements covered up to 360MW of IT load, and the exhibition notice now lists a maximum power consumption of 444MW.

    The EIS lists the campus at 365MW. Its cost report and greenhouse assessment use 342MW, built up from 15 data halls of 12MW in Building A and 18 of 9MW in Building B.

    Item

    Figure in the planning documents

    Maximum IT load

    365MW (EIS); 342MW (cost report, greenhouse assessment)

    Maximum power consumption

    444MW (exhibition notice)

    Buildings and data halls

    2 buildings, 33 data halls

    Estimated cost

    A$4.99 billion, excluding GST

    Construction

    44 months (cost report), starting 2027

    Operations

    Q1 2029 first stage, full load Q1 2031

    Substation

    Up to 1,000MVA, 500MVA allocated to this campus

    Operating staff

    About 84

    Source: Stockland Development, Aldington Road Data Centre environmental impact statement and appendices, November 2026; exhibition notice, NSW Planning Portal, 19 November 2026. Figures are as each document states them and are not all measured on the same basis.

    Construction is estimated to support about 1,375 jobs

    The cost report estimates the 44-month build will support about 1,375 full-time equivalent jobs, and the EIS expects operations to start in 2029. NSW and Australian suppliers, contractors and service providers will get priority where commercially and technically feasible, Stockland says. Selected NSW apprentices and trainees would get placements at operating international data centres where appropriate, according to the same commitments.

    Consultation in August and September reached about 850 nearby addresses by newsletter, alongside online briefings, an information session and a doorknock. The EIS reports "general agreement that the Site is a suitable location for a data centre". Penrith City Council wants the application sent to the Independent Planning Commission. In September it told the department that the proposed height, then given as 36.4 metres, was "a significant non-compliance" with the 20-metre control. The EIS gives a maximum height of 31.5 metres.

    What to watch

    • Public comment. Comment closes on 17 December 2026, and Stockland then responds to the submissions.

    • Who decides. The Minister for Planning and Public Spaces or the Independent Planning Commission.

    • The Transgrid connection. Transgrid's review of the network modelling for the Ropes Creek switching station.

    • The NSW connection rules. New NSW regulations for data centres include an entry bond of A$30,000 a megawatt, according to a government presentation of 4 November. The regulations are due by 19 December 2026 and final guidelines by 31 January 2027.

     

    Share this article

    Keep reading the market

    Get The Strategic Brief in your inbox every Thursday.

    The leading Australian data centre and AI infrastructure newsletter.

    One email a week. Unsubscribe in one click.

    Your Next Read

    Latest Headlines

    Interested in reaching this audience? Advertise with us.