Australian data centre operator profile covering certified facilities, footprint, capacity signals and latest coverage.
Profile summary
Listing ASX:NXT · Ownership ASX-listed · HQ Brisbane · Founded 2010 · Founder Bevan Slattery · CEO Craig Scroggie · Certified Strategic 13 Enclaves · Australian sites 25 · Contracted capacity 740.1MW (pro forma, 30 June 2026) · Forward order book 565MW · Liquidity A$8.7bn (30 September 2026).
Contracted capacity
740.1MW
Pro forma at 30 June 2026; 175MW billing, 565MW forward order book (FY26 result, 27 Aug 2026)
Liquidity
A$8.7bn
A$8,675m at 30 September 2026, including A$1,275m cash (21 Oct 2026)
Overview
NEXTDC is an ASX-listed Australian data centre operator headquartered in Brisbane. Its Australian profile spans Sydney, Melbourne, Brisbane, Perth, Adelaide, Canberra and Darwin, with a Certified Strategic footprint across major metro and edge locations.
NEXTDC's contracted capacity figure is from its FY26 result, released on 27 August 2026, and its liquidity figure from its 21 October 2026 update.
On 21 October 2026 NEXTDC cut its FY27 guidance after delays to Jemena's electricity network works pushed the next increase in grid supply to M3 Melbourne into FY28. It then expected net revenue of A$475 million to A$500 million, down from A$615 million to A$640 million, and underlying EBITDA of A$245 million to A$265 million, down from A$385 million to A$410 million. On 20 November 2026 NEXTDC upgraded its FY27 guidance to net revenue of A$485 million to A$500 million and underlying EBITDA of A$260 million to A$275 million. It said the higher net revenue range reflects strong sales and revenue growth outside the affected M3 contracts and greater confidence in the timing of customer delivery, and the higher EBITDA range is mainly because of cost savings from focusing operating spending on delivering capacity to customers, together with higher expected net revenue. Both ranges leave out the affected M3 contracts. The capacity remains under contract, subject to the customer's rights, and construction of the data halls is continuing. FY27 capital expenditure guidance is now A$4,500 million to A$5,000 million, down from A$5,250 million to A$5,750 million; the new range includes about A$230 million of capitalised interest, which the earlier range did not. NEXTDC has put all new development projects and land acquisitions on hold for the foreseeable future. On 20 November 2026 NEXTDC said the review of its capital program was complete and reaffirmed that capital expenditure range, the majority of which is focused on existing customer contracts at S4 Sydney, M2 Melbourne, M3 Melbourne and KL1 Kuala Lumpur. Uncontracted projects, including M4, M5, S5, S7, GC1 and AK1, remain on hold. NEXTDC is evaluating a joint venture structure for its S4 Sydney campus. Apart from development sites near homes that it no longer intends to develop, it does not expect to sell sites in the near term, and it said further work is needed before any decision on a site sale. It does not expect to raise capital from shareholders at this time to deliver its current contracted customer capacity. On 26 October 2026 NEXTDC announced a board renewal: chairman Douglas Flynn will retire once a new chairman is in place, after a short handover, and the board expects to appoint a new chairman and one more independent non-executive director in the first quarter of 2027, subject to finding suitable candidates. Director Stuart Davis, re-elected at the annual general meeting on 20 November 2026, intends to stand down once the new directors are in place. At that meeting 72.06 per cent of votes cast were against the remuneration report, a second strike, and shareholders rejected the resulting board spill resolution, with 96.21 per cent of votes against. Chief executive Craig Scroggie has agreed to forgo his FY27 short-term and long-term incentives, with no cash or other award in their place. The non-executive directors have taken an immediate voluntary 10 per cent cut in their fees and withdrawn a proposed A$300,000 increase to their fee pool.
On 28 October 2026 NEXTDC reported that it complied with both of its financial covenants at 30 June 2026, the most recent half-yearly test date. Its interest cover ratio was 5.91 times on a pro forma basis, against a minimum of 1.5 times, and its gearing ratio was 8.2 per cent, against a maximum of 60 per cent. For covenant purposes it left out the contracted, not yet billed, earnings of the affected M3 contracts. It expects to comply with both covenants at the next test date, 31 December 2026. Its earliest senior debt maturity is December 2029, and holders of its A$1.1 billion convertible notes, issued on 17 September 2026, can require NEXTDC to repay them on 17 September 2029.
S4 at Horsley Park in western Sydney is NEXTDC's largest contracted development: customers have contracted 250MW of its planned 365MW IT load. Its first phase, 115MW, is under construction and is expected to begin billing in FY28, and its second phase is in the NSW planning process. Recycled water company coNEXA is extending its AquaNet recycled water network from Smithfield to NEXTDC's S4 Sydney data centre at Horsley Park. The NSW Independent Pricing and Regulatory Tribunal (IPART) has approved the expansion, and coNEXA expects major construction to start in November 2026.
On 5 November 2026 NEXTDC told the ASX that Ackland Investments No.1, a vehicle owned in equal shares by Goodman Group and Digital Realty, ran an aftermarket book build on 4 November 2026 to buy NEXTDC shares at A$9.50 each, up to a maximum holding of 9.9 per cent. NEXTDC said it did not know the outcome. Goodman and Digital Realty told investors through their broker that they have "no intention of submitting a control proposal or making a takeover bid for the Company at this time, but reserve their right to do so". The board called the share raid an opportunistic move and said it held no takeover proposal; it will consider any bona fide approaches on their merits. NEXTDC has appointed Barrenjoey and UBS as joint lead financial advisers, Cadence Advisory as independent financial adviser and Mallesons as legal adviser. On 9 November 2026 Goodman and Digital Realty told the ASX that their jointly owned vehicle had acquired a 9.9 per cent interest in NEXTDC at an average price of A$9.22 a share. Ackland's substantial holding notice, lodged the same day, shows it bought all 75,215,528 shares between 3 and 6 November 2026, paying at most A$10.40 a share. The pair said neither has "any present intention of submitting a control proposal, or making a takeover offer for NEXTDC", though each reserves the right to do so, and that they look forward to a "potential collaboration" with NEXTDC's board and management. NEXTDC said the same day that its board held no proposal from Goodman, Digital Realty or Ackland and would consider any bona fide proposal on its merits.
Australian facilities
Live Supabase directory
View NEXTDC in the Certified Strategic directoryA1
Certification
Strategic EnclaveScale band
Wholesale
City
Adelaide
State
SA
B1
Certification
Strategic EnclaveScale band
Enterprise
City
Brisbane
State
QLD
B2
Certification
Strategic EnclaveScale band
Wholesale
City
Brisbane
State
QLD
C1
Certification
Strategic EnclaveScale band
Enterprise
City
Canberra
State
ACT
D1
Certification
Strategic EnclaveScale band
Enterprise
City
Darwin
State
NT
D2
Certification
Not certifiedScale band
Directory pending
City
Darwin
State
NT
GC1
Certification
Not certifiedScale band
Directory pending
City
Gold Coast
State
QLD
GE1
Certification
Not certifiedScale band
Directory pending
City
Geelong
State
VIC
M1
Certification
Strategic EnclaveScale band
Wholesale
City
Melbourne
State
VIC
M2
Certification
Strategic EnclaveScale band
Hyperscale
City
Melbourne
State
VIC
M3
Certification
Strategic EnclaveScale band
Hyperscale
City
Melbourne
State
VIC
M4
Certification
Not certifiedScale band
Directory pending
City
Melbourne
State
VIC
NE1 Newman
Certification
Not certifiedScale band
Directory pending
City
Newman
State
WA
P1
Certification
Strategic EnclaveScale band
Wholesale
City
Perth
State
WA
P2
Certification
Strategic EnclaveScale band
Wholesale
City
Perth
State
WA
PH1 Port Hedland
Certification
Not certifiedScale band
Directory pending
City
Port Hedland
State
WA
S1
Certification
Strategic EnclaveScale band
Wholesale
City
Sydney
State
NSW
S2
Certification
Strategic EnclaveScale band
Wholesale
City
Sydney
State
NSW
S3
Certification
Strategic EnclaveScale band
Hyperscale
City
Sydney
State
NSW
S4
Certification
Not certifiedScale band
Directory pending
City
Sydney
State
NSW
S5
Certification
Not certifiedScale band
Directory pending
City
Sydney
State
NSW
S6
Certification
Not certifiedScale band
Wholesale
City
Sydney
State
NSW
S7
Certification
Not certifiedScale band
Directory pending
City
Sydney
State
NSW
SC1 Sunshine Coast
Certification
Not certifiedScale band
Directory pending
City
Sunshine Coast
State
QLD
SC2
Certification
Not certifiedScale band
Directory pending
City
Sunshine Coast
State
QLD
Pins are grouped by metro or region and sized by total tracked sites. States with at least one tracked site are tinted blue.
Latest coverage
20 Nov 2026
NEXTDC lifted FY27 EBITDA guidance to A$260m to A$275m, is exploring a joint venture for S4 Sydney and does not expect to ask shareholders for capital for contracted capacity.
16 Nov 2026
Australia's data centre builders are growing. NEXTDC builder Kapitol expects record starts and FDC's data centre contracts roughly doubled in four months.
16 Nov 2026
Southern Cross Electrical's Heyday wins the electrical contract for NEXTDC's S4 Sydney in more than A$300m of awards, as NEXTDC pauses projects without customers.
10 Nov 2026
Craig Scroggie told investors he is sorry for M3's impact on customers and residents, and says he has a power fix. Uncontracted work stays on hold.
Common questions
NEXTDC is an ASX-listed Australian data centre operator, headquartered in Brisbane and founded in 2010, running a national network of colocation and hyperscale facilities.
NEXTDC operates 25 Australian data centres, across Sydney, Melbourne, Brisbane, Perth, Adelaide, Canberra, Darwin, the Sunshine Coast, Port Hedland and Newman.
Yes. NEXTDC holds Certified Strategic Enclave status at 13 sites under the Hosting Certification Framework, the Australian Government's highest certification tier.
NEXTDC is publicly owned and listed on the Australian Securities Exchange under ASX:NXT. On 4 November 2026 Ackland Investments No.1, a vehicle owned in equal shares by Goodman Group and Digital Realty, sought to buy NEXTDC shares at A$9.50 each, up to a maximum holding of 9.9 per cent. On 9 November 2026 Goodman and Digital Realty told the ASX that the vehicle had acquired a 9.9 per cent interest in NEXTDC, at an average price of A$9.22 a share.
NEXTDC was billing customers for 175MW at 30 June 2026, out of 740.1MW under contract on a pro forma basis, which leaves a forward order book of 565MW. In its FY26 result on 27 August 2026, it expected 197MW to convert to billing in FY27 and a further 221MW in FY28. On 21 October 2026 it said delays to Jemena's network works push the next increase in grid supply to M3 Melbourne into FY28, deferring delivery and billing of contracted capacity there. It reported liquidity of A$8.7 billion at 30 September 2026.
Jemena is the electricity distributor for M3. It suspended parts of its network works in September 2026, citing community opposition. The local council, as road authority, is holding its consent while consultation continues. NEXTDC said on 21 October 2026 that Jemena does not expect to restart the works before February 2027, so the next increase in grid supply to M3 is now expected in FY28. The Victorian Government's planning decision on M3 Stages 6 and 7 is now expected in 2027, after the state election on 28 November 2026. Later increases in grid supply depend on new transformers at the Brooklyn Terminal Station, and NEXTDC now expects the first of those projects to finish later than it previously expected, which affects the timing of capacity converting to billing after FY28. The affected M3 contracts provide for service level credits when capacity is delivered late or is not fully powered and, in some circumstances, give the customer rights to terminate. NEXTDC said those credits could reduce underlying EBITDA below its FY27 guidance, and it is working with the customer on a revised power ramp. On 20 November 2026 NEXTDC said it and Jemena are working on several power options in parallel: alternative routes through industrial streets and underground, alternative substations, upgrades to existing feeders and broader grid options. Once Jemena's technical solution is finalised, Jemena will lead any community consultation and approvals.