NEXTDC builder Kapitol expects record data centre starts
By Winston Su, Editor · · Add us as a preferred source on Google

At a glance
Melbourne builder Kapitol, which builds data centres for NEXTDC and Microsoft, expects a company record for new data centre starts in the 12 months from November 2026.
Figures published by the AFR show Kapitol's FY26 revenue more than doubled to A$1.6 billion, 60 per cent of it from data centres, and fellow Melbourne builder Hickory's more than doubled to A$1.34 billion.
ASX-listed Sydney builder FDC's signed data centre work rose from about A$225 million on 30 June to about A$465 million on 31 October 2026.
NEXTDC has put projects with no signed customer on hold, and developer Quantum DC has paused the approval process for its Tungkillo site in the Adelaide Hills.
Kapitol has opened a Brisbane office to win housing, infrastructure and data centre work outside Victoria.
Melbourne builder Kapitol, which has grown by building data centres for NEXTDC and Microsoft, expects the 12 months from November 2026 to be its best year yet for new data centre starts, joint chief executive Andrew Deveson told the Australian Financial Review in an interview published on 15 November 2026. With some developers pausing projects over community opposition and power delays, Kapitol has opened in Brisbane to chase housing, infrastructure and data centre work outside Victoria.
Kapitol is private, but listed Sydney builder FDC reports its signed work by sector. FDC's signed data centre work roughly doubled to about A$465 million in the four months to 31 October 2026.
Economic consultancy Oxford Economics expects data centre construction in Australia to keep rising. In a 7 October 2026 briefing, it forecast construction rising from about A$5.3 billion in FY26 to a peak of about A$14 billion in FY29, in 2023-24 dollars. It says the supply of power, grid connections and workers will decide which projects go ahead.
Data centres made 60 per cent of Kapitol's revenue
Deveson and David Caputo founded Kapitol in Melbourne in 2018 and run it as joint chief executives. Kapitol told the AFR its revenue more than doubled to A$1.6 billion in the year to June 2026, driven by large data centre contracts. Net profit after tax rose to A$56.8 million from A$25.5 million, and data centres made up 60 per cent of revenue.
Construction data company Hubexo ranked Kapitol first in its 2026 Construction League, a list of Australia's top 50 builders by the value of projects started in 2025. Kapitol started 17 projects worth A$3.503 billion. Industrial work, which for Kapitol includes data centres and substations, made up 59 per cent of the value of its 2025 starts. Almost all its activity, 94 per cent, was in Victoria.
Kapitol has built data centres for NEXTDC in Melbourne and Darwin and for Microsoft in Melbourne. Its Stage 6 build at NEXTDC's M2 was highly commended in four categories at the Data Centres Australia Excellence Awards on 8 September 2026. It is also preferred bidder for the expansion of NEXTDC's M3 campus in West Footscray, which is waiting on grid power.
Deveson declined to discuss M3 and said the timing of some starts is uncertain. If the flow of capital into data centres changes, Kapitol wants to be able to do other work, he said.
To find that work, Kapitol has opened a Brisbane office, led by Queensland general manager James Grljusich, formerly of Multiplex. It is in confidential tenders for several Queensland projects and is targeting housing, infrastructure and data centre work in the state. Queensland data centres are proposed from Ipswich, near Brisbane, to Townsville.
Listed builder FDC's data centre contracts roughly doubled in four months
FDC listed on the ASX in July 2026. Its 27 August 2026 results release shows revenue up 13 per cent to A$1.69 billion in FY26, with data centres lifting from 6 per cent to 13 per cent of the total.
FDC calls signed work that is not yet built "work in hand". Its results presentation put data centres at 9 per cent of A$2.5 billion of work in hand at 30 June 2026. Its 11 November update, which raised FY27 guidance, put data centres at 16.3 per cent of A$2.85 billion at 31 October. That is a rise from about A$225 million to about A$465 million. FDC now expects FY27 revenue of A$2.00 billion to A$2.08 billion, up from A$1.9 billion in its prospectus.
Chief executive Russell Grady said in August that FDC's work in hand reflects the date contracts are formally secured. Industrial, at 18.1 per cent, and education, at 17.1 per cent, are larger shares of FDC's work in hand.
Data centre builders' latest results
FDC's data centre book is smaller than those of the sector's largest builders. In Oxford Economics data published by the AFR, Kapitol, Multiplex, Lendlease, Hickory and A W Edwards are the five largest builders of data centres in Australia. Each has more than A$2 billion of data centre projects that started since 2020, are under way or are committed.
Figures published by the AFR show Hickory, also from Melbourne, more than doubled its revenue to A$1.34 billion in the year to June 2026, and its net profit after tax nearly quadrupled to A$102.1 million. Data centres make up 40 per cent of its order book.
Multiplex says it has delivered five data centres for NEXTDC over seven years, with more than 500MW of capacity between them. It started construction at NEXTDC's S4 campus at Horsley Park in Western Sydney in March 2026, and counts DCI Data Centres among its other data centre clients.
A W Edwards, a Sydney builder owned by France's Bouygues since 2018, holds the expanded €1.2 billion contract (about A$1.9 billion) for AirTrunk's SYD3 campus in Western Sydney. It is also building Goodman's SYD01 in Artarmon, a 61MW IT facility whose first phase Goodman expects to be ready in 2028.
Builder | Latest full-year result | Data centre work |
|---|---|---|
Kapitol, Melbourne | A$1.6bn revenue, up more than 100%; A$56.8m net profit, year to June 2026 | 60% of revenue; NEXTDC and Microsoft |
Hickory, Melbourne | A$1.34bn revenue, up more than 100%; A$102.1m net profit, year to June 2026 | 40% of order book |
FDC, Sydney | A$1.69bn revenue, up 13%; A$70.8m normalised net profit, year to June 2026 | 13% of revenue; 16.3% of signed work at 31 October |
A W Edwards, Sydney | A$834.6m revenue, up 12.8%; A$34m net profit, year to December 2025 | |
Multiplex | A$3.5bn revenue, down 12%, year to December 2025 | NEXTDC, including S4 at Horsley Park |
Source: FDC ASX announcements; Australian Financial Review, 15 November 2026; Multiplex; Goodman; Bouygues Construction.
Developers pause or withdraw projects
Kapitol's push into other work follows a run of pauses by data centre developers since September, including at one of its own clients. NEXTDC also hires Multiplex. It is keeping on hold any project without a signed customer until it has solved M3's power problem and won back trust, chief executive Craig Scroggie told investors on 9 November 2026.
Electricity distributor Jemena stopped work in September on the power poles that would carry new lines to M3, after residents objected, and does not expect to restart before February 2027. Work on M3's contracted data halls continues, and NEXTDC will report the outcome of a review of its capital spending at its annual general meeting on 20 November.
Melbourne developer Quantum DC has also paused the approval process for its 1.2GW Tungkillo data centre in the Adelaide Hills and will not lodge a development application in 2026. In Sydney, Goodman withdrew its Project Mars application at Lane Cove in September.
Peter Colacino heads the Australian Constructors Association, which represents the country's largest builders. He told the AFR the NEXTDC pause points to a broader but short-term slowdown in building work.
What to watch
NEXTDC's annual general meeting on 20 November 2026. NEXTDC will report the outcome of its capital spending review to shareholders.
FDC's first half-year result. FDC reports its first half-year result as a listed company by the end of February 2027. If it splits work in hand by sector again, the data centre share at 31 December 2026 will show whether the rise to 16.3 per cent has held.
NEXTDC's power supply and planning approval for M3. Scroggie says NEXTDC will announce how M3 will be powered once the supply is contracted. The Victorian Government is expected to decide on planning approval for M3 Stages 6 and 7 in 2027, after the state election on 28 November 2026. Both bear on when Kapitol, preferred bidder for the M3 expansion, can start work.
Keep reading the market
Get The Strategic Brief in your inbox every Thursday.
The leading Australian data centre and AI infrastructure newsletter.
Your Next Read

Goodman and Digital Realty raid NEXTDC shares at A$9.50

Southern Cross Electrical wins NEXTDC S4 electrical contract

NEXTDC enters trading halt over M3 Melbourne power delay
Latest Headlines
Dataspace launches with 14.5MW across five ex-Fujitsu sites
17 Nov 2026US acts to stop China renting AI chips in Asian data centres
17 Nov 2026Firmus seeks upfront payments from NVIDIA and Meta in A$4.4bn raise
17 Nov 2026Sharon AI misses on revenue as its price per megawatt climbs
17 Nov 2026IREN starts NSW approval for 900MW Wagga Wagga data centre
17 Nov 2026
Interested in reaching this audience? Advertise with us.