Capacity & ExpansionOperator Updates

    Southern Cross Electrical wins NEXTDC S4 electrical contract

    By Winston Su, Editor · · Add us as a preferred source on Google

    Southern Cross Electrical wins NEXTDC S4 electrical contract
    Southern Cross Electrical's Heyday wins the electrical contract for NEXTDC's S4 Sydney in more than A$300m of awards, as NEXTDC pauses projects without customers.

    At a glance

    • NEXTDC's S4 data centre at Horsley Park in western Sydney has a full electrical contract for its first stage, awarded by builder Multiplex to Southern Cross Electrical's Heyday.

    • Heyday's work covers two four-level data hall buildings with about 60,000m² of combined floor area, plus the high-voltage switching building, with completion expected in early 2028.

    • Southern Cross Electrical announced more than A$300 million of awards on 16 November 2026, which managing director Graeme Dunn called the largest single announcement of works in its history.

    • S4's first 250MW is contracted to customers, while NEXTDC has kept projects without customer contracts on hold since 21 October.

    • NEXTDC has promised the outcome of its capital spending review by its annual general meeting on 20 November 2026.

     

    ASX-listed contractor Southern Cross Electrical Engineering said on 16 November 2026 that its business Heyday has won the electrical design and construct contract for the first stage of NEXTDC's S4 data centre at Horsley Park in western Sydney. Builder Multiplex awarded the package, which follows a letter of authorisation Heyday received in June to start initial works on site.

    NEXTDC has kept projects without customer contracts on hold since 21 October 2026, when a delay to grid power at its M3 campus in Melbourne cut its FY27 guidance. S4's first 250MW is signed to customers, which keeps it outside the pause.

    Heyday's S4 contract covers 60,000m² of data halls

    The first stage of S4 comprises the high-voltage switching building, a security operations centre, ancillary buildings and two of the four planned multi-level data hall buildings, Southern Cross Electrical said when it announced the early works on 15 June 2026. The two have four levels each and about 60,000m² of gross floor area, built for hyperscale tenants.

    Heyday's contract covers site-wide electrical and communications infrastructure across that stage. Its crews will install and manage client-supplied transformers, as well as high-voltage and low-voltage switchboards, generators, UPS units, modular switch room skids and busways. Completion is expected in early 2028.

    Heyday has worked on S4 since 2024, giving Multiplex and NEXTDC cost planning, concept development and technical advice. Multiplex has advised NEXTDC on S4 since 2022 and holds the design and construct contract for the project.

    NEXTDC's contracted 250MW at S4 remains on track

    NEXTDC reported a record 250MW increase in contracted utilisation at S4 on 20 April 2026, lifting its pro forma contracted utilisation, the capacity customers have signed for, by 60 per cent to 667MW. It said it would invest about A$1.5 billion developing that capacity through to the end of FY27. Its FY26 result on 27 August raised S4's total capacity to 365MW, with 250MW in progress and 115MW in planning.

    On 21 October NEXTDC cut its FY27 guidance, paused projects without customer contracts, and put new land acquisitions on hold. It reduced FY27 capital expenditure guidance by A$750 million, to between A$4.5 billion and A$5 billion. In the same investor update, chief executive Craig Scroggie said the S4 250MW delivery program was on track.

    At a UBS conference on 9 November, Scroggie said uncontracted work would not restart until NEXTDC could show it had solved the power problem at M3. Work at S4 continues. A privately funded pipeline is due to deliver up to 16 million litres a day of recycled water for cooling to the site from late 2027.

    Shape hires Force Fire for data centre fire services

    Builder Shape Australia hired Force Fire, a Southern Cross Electrical fire protection business, for wet and dry fire systems at a data centre project, the second data centre award in the 16 November announcement. Force Fire recently completed the design development for that work.

    Heyday also won work on three Canberra building projects. The five awards are worth more than A$300 million in total, which managing director Graeme Dunn said was the largest single announcement of works in the group's history. The Canberra work puts the group "amongst the highest levels of activity" in more than 30 years of building in the city, he said.

    Award

    Builder

    Heyday or Force Fire scope

    NEXTDC S4 first stage, Horsley Park

    Multiplex

    Electrical design and construct, due early 2028

    Data centre, site not named

    Shape

    Wet and dry fire systems

    Commonwealth Office Precinct, Barton

    Lendlease

    Electrical supply and distribution, lighting and controls, due 2029

    220 Northbourne Gateway, Braddon

    GEOCON

    Electrical and communications for 503 apartments, due February 2028

    N-11 build-to-rent, Woden Green

    Hindmarsh

    Electrical and communications for 326 apartments, due June 2028

    Source: Southern Cross Electrical Engineering ASX announcement, 16 November 2026.

    Southern Cross Electrical expects data centre revenue to more than triple

    Southern Cross Electrical's FY26 result on 19 August 2026 put its data centre revenue at A$120 million and forecast that figure to triple in FY27. At its annual general meeting on 27 October it put the FY27 figure at about A$400 million. Dunn said the new data centre awards came from "clients for whom we have done significant works previously", and Heyday's NEXTDC work also includes electrical contracts from Multiplex at S3 in Artarmon. Two of the group's last five months each set a monthly revenue record, Dunn said.

    Southern Cross Electrical is one of the ASX-listed contractors earning from the data centre build, alongside SKS Technologies and NRW Holdings' Fredon. In June it raised A$150 million through an institutional placement, about A$100 million of it for working capital.

    What to watch

    NEXTDC's annual general meeting. The company said it would give further updates on M3 and its build program at its meeting on 20 November 2026, and the outcome of its review of capital spending by then.

    Southern Cross Electrical's half-year result. Expected in February 2027, it will show how much of the forecast A$400 million in data centre revenue has been earned in the six months to 31 December 2026.

    S4's first stage. Recycled water is due to reach the site in late 2027, and Heyday's electrical work is due to finish in early 2028.

    Share this article

    Keep reading the market

    Get The Strategic Brief in your inbox every Thursday.

    The leading Australian data centre and AI infrastructure newsletter.

    One email a week. Unsubscribe in one click.

    Your Next Read

    Latest Headlines

    Interested in reaching this audience? Advertise with us.