Certified Strategic
CDC Marsden Park
105 Hollinsworth Rd. 504MW (scalable to 1GW). Ground broken Oct 2024. SSD approved by NSW DPHI November 28, 2025. Initial capacity already contracted. AU$3.1B. 720MVA substation.
Published infrastructure records
1 records in this collection.
| Infrastructure | Operator | State | Status | Source |
|---|---|---|---|---|
| CDC Marsden Park | CDC Data Centres | NSW | Construction | Source |
105 Hollinsworth Rd. 504MW (scalable to 1GW). Ground broken Oct 2024. SSD approved by NSW DPHI November 28, 2025. Initial capacity already contracted. AU$3.1B. 720MVA substation.