SSD-113934740 at Prepare EIS (EIS not yet lodged). 612MW in the planning application, three 2-storey buildings, 340 backup generators. AU$7.6B. OpenAI "intends to be an initial offtaker" (NEXTDC, 5 December 2025). Phase 1 target H2 2027. Closed-loop liquid cooling, zero potable water.
Published infrastructure records
1 records in this collection.
| Infrastructure | Operator | State | Status | Source |
|---|---|---|---|---|
| NEXTDC S7 (OpenAI) | NEXTDC | NSW | Planned | Source |
SSD-113934740 at Prepare EIS (EIS not yet lodged). 612MW in the planning application, three 2-storey buildings, 340 backup generators. AU$7.6B. OpenAI "intends to be an initial offtaker" (NEXTDC, 5 December 2025). Phase 1 target H2 2027. Closed-loop liquid cooling, zero potable water.