Adelaide ADL1
Certification
Strategic EnclaveScale band
Enterprise
City
Adelaide
State
SA

Australian data centre operator profile covering DigiCo sites, HCF certification, HMC Capital management and latest coverage.
Externally managed by HMC Capital.
Profile summary
Listing ASX:DGT (real estate investment trust, externally managed by HMC Capital) · HQ Sydney · Co-heads Simon Mitchell and Ralph Goninan · Certified Strategic 3 sites (1 Facility, 2 Enclaves) · Australian sites 8 · IT capacity billed to customers in Australia 41MW (30 June 2026; 85MW across the group) · SYD1 being upgraded to 88MW (fully funded, whole site), 100 per cent contracted after a 71MW, 15-year contract signed 15 October 2026.
IT capacity billed, Australia
41MW
30 June 2026; 85MW across the group, 44MW in North America
SYD1 upgrade
88MW
Whole site, fully funded; 100% contracted after a 71MW, 15-year contract signed 15 Oct 2026 (subject to conditions); ADL1 15MW expansion in customer talks and 1GW+ of greenfield sites under evaluation (statements of intent)
Overview
DigiCo is an ASX-listed REIT externally managed by HMC Capital. Its Australian profile spans Adelaide, Brisbane, Sydney and Townsville. BNE2 in Brisbane is a Certified Strategic Facility, and ADL1 in Adelaide and SYD1 in Sydney are Certified Strategic Enclaves.
DigiCo is upgrading SYD1 in Ultimo to 88MW. The first 20MW was completed in FY26, a further 10MW is due at the end of FY27 and 42MW through FY28. On 15 October 2026 DigiCo signed a 15-year contract for 71MW at SYD1 with a global technology firm, subject to customary conditions and approvals. The Australian Financial Review reported on 16 October 2026 that the customer is Anthropic. The contract includes 20MW of existing contracted capacity reallocated to the new customer, and leaves SYD1 100 per cent contracted across its 88MW, with the remaining 17MW leased to co-location customers. NSW approved the expansion in December 2025. SYD1 needs 120MVA of grid capacity for the full development; 80MVA is in place and the remaining 40MVA is secured. Shape Australia is head contractor on a fixed-price contract, and Laing O'Rourke is the delivery partner.
In its first full year, to 30 June 2026, DigiCo reported underlying revenue of A$239 million, underlying EBITDA of A$127 million (guidance A$125 million) and a distribution of 12.0 cents. FY27 guidance is EBITDA of A$120 million to A$125 million and a distribution of 15.0 cents, with capital expenditure of A$300 million to A$500 million. DigiCo targets the first 10MW of the SYD1 expansion to be energised late in FY27 and the full 88MW by the end of FY28. Management estimates SYD1 and ADL1 give it a pathway to about A$250 million a year of EBITDA from its Australian platform, once all contracted capacity is online and billing.
Australian facilities
Live Supabase directory
View DigiCo in the Certified Strategic directoryAdelaide ADL1
Certification
Strategic EnclaveScale band
Enterprise
City
Adelaide
State
SA
Adelaide ADL2
Certification
Not certifiedScale band
Enterprise
City
Adelaide
State
SA
Brisbane BNE
Certification
Not certifiedScale band
Enterprise
City
Brisbane
State
QLD
Brisbane BNE1
Certification
Not certifiedScale band
Enterprise
City
Brisbane
State
QLD
Brisbane BNE2
Certification
Strategic FacilityScale band
Enterprise
City
Brisbane
State
QLD
Brisbane BNE3 Data Center
Certification
Not certifiedScale band
Wholesale
City
Brisbane
State
QLD
SYD1
Certification
Strategic EnclaveScale band
Enterprise
City
Sydney
State
NSW
Townsville TSV1
Certification
Not certifiedScale band
Enterprise
City
Townsville
State
QLD
Pins are grouped by metro or region and sized by total tracked sites. States with at least one tracked site are tinted blue.
Latest coverage
11 Nov 2026
NRW's Fredon has won a A$240m data centre electrical contract from builder Shape, whose largest data centre client is DigiCo at SYD1 in Ultimo, Sydney.
28 Oct 2026
CDC Data Centres leads the October 2026 Power Rankings on contracted and approved capacity. NEXTDC is second and AirTrunk third.
20 Oct 2026
Anthropic has pledged community agreements worth tens of millions at every site it owns or leases. Its Australian sites are Zerra's Kogan campus and, reportedly, DigiCo's SYD1.
16 Oct 2026
DigiCo has signed a 15-year, 71MW contract at its SYD1 data centre in Ultimo with an unnamed global technology firm, leaving the site fully contracted.
Common questions
DigiCo is an ASX-listed real estate investment trust, externally managed by HMC Capital, that owns a portfolio of data centres in Australia and North America. To fund the Sydney upgrade it sold its Chicago site, CHI1, on 10 September 2026. Its sale of LAX1 and LAX2 in Los Angeles was in the final stages of due diligence as at 25 September 2026; once that completes it will keep two US sites, KCM1 and DAL1. DigiCo has agreed terms to extend the leases at its Kansas City and Dallas sites to 10-year terms expiring in 2036.
DigiCo's Australian portfolio spans 8 sites, across Brisbane, Adelaide, Sydney and Townsville.
Yes. DigiCo holds three certifications, a Certified Strategic Facility at BNE2 in Brisbane and Certified Strategic Enclaves at ADL1 in Adelaide and SYD1 in Sydney.
DigiCo Infrastructure REIT is listed on the Australian Securities Exchange under ASX:DGT and is externally managed by HMC Capital. Since 21 August 2026 DigiCo has been led by two co-heads, chief financial officer Simon Mitchell and chief development officer Ralph Goninan. HMC Capital owns just over 20 per cent of DigiCo, HMC's Victoria Hardie told the Australian Financial Review Property Summit.
DigiCo bills customers for 41MW of IT capacity in Australia at 30 June 2026, and 85MW across the group, 44MW of it in North America. This is billed IT capacity, not installed capacity. DigiCo is upgrading SYD1 to 88MW (fully funded, whole site), and the site is 100 per cent contracted after DigiCo signed a 15-year, 71MW contract with a global technology firm on 15 October 2026, subject to customary conditions and approvals; an ADL1 expansion of 15MW is in customer talks; and more than 1GW of greenfield sites are under evaluation. The ADL1 and 1GW figures are statements of intent, not committed builds.
Profile updates
Represent this operator or spotted something that needs review? Send a correction, right of reply or profile update to the editorial team.