Finland Data Centre Infrastructure Map

44 facilities: 10 operational, 15 under construction, 17 planned, 2 paused. Data as at 27 November 2026.

Cite this map: Certified Strategic, “Finland Data Centre Infrastructure Map”, 27 November 2026, updated 27 November 2026. certifiedstrategic.com/maps/finland

All Finland data centres tracked

FacilityOperator, suburbMW, status
Mäntsälä data centerNebius
Kapuli, Mäntsälä
75 MW
Capacity after expansion, measure not stated
Operational
Helsinki campusVerne
Vantaa
70 MW
Site capacity Verne plans to develop, measure not stated
Operational
FIN02 Espoo (with FIN01 Helsinki)atNorth
Sinimäentie, Espoo
40 MW
Campus power capacity, FIN02 only
Operational
Telia Helsinki Data CenterTelia
Pitäjänmäki, Helsinki
24 MW
Operational
Pori bunker data centre (the Rock)Glesys
Ulvila, Pori area
11 MW
Total, measure not stated (press report)
Operational
Tampere data centre (the Deck)Glesys
Tampere
1 MW
Up to, measure not stated (press report)
Operational
CSC Kajaani Data Center (LUMI)CSC
Renforsin Ranta, Kajaani
Capacity not published
Operational
Data Center Park Helsinki (HEL1)Hetzner
Tuusula
Capacity not published
Operational
Hamina data centerGoogle
Summa, Hamina
Capacity not published
Operational
Helsinki campus (HE3 to HE7)Equinix
Espoo, Helsinki and Vantaa
Capacity not published
Operational
SJK01 Seinäjoki AI campusPure DC
Kivenneva, Seinäjoki
550 MW
Full campus, over 550MW, measure not stated (first phase 110MW)
Under construction
FIN04 Kouvola (Myllykoski)atNorth
Myllykoski, Kouvola
430 MW
Campus power capacity, planned total
Under construction
Pori campus (Copper Industrial Park)ASP DC
Kupariteollisuuspuisto, Pori
400 MW
Up to: 300 to 400MW of modular capacity (first phase 150MW; press report)
Under construction
Lappeenranta AI factoryNebius
Pajarila, Lappeenranta
310 MW
Up to, measure not stated
Under construction
Keskikylä campusHyperco
Keskikylä, Pyhäjoki
284 MW
Under construction
Utajärvi AI data centreAmpTank (Data Tank)
Mustikkakangas, Utajärvi
200 MW
Building permit size, measure not stated (company release, through Yle)
Under construction
Vihti datacenterMicrosoft
Nummela, Vihti
192 MW
Under construction
Espoo datacenter (Hepokorvenkallio)Microsoft
Espoo
172.8 MW
Under construction
Mikkeli AI data centreCompute Nordic (for Cerebras)
Visulahti, Mikkeli
165 MW
Contracted IT load, full build in phases (first phase 50MW)
Under construction
Kirkkonummi datacenterMicrosoft
Masala, Kirkkonummi
144 MW
Under construction
Lahti Kiveriö campus (TikTok Lahti)DayOne
Kiveriö, Lahti
128 MW
Under construction
Mäntsälä campusVerne
Kapuli, Mäntsälä
70 MW
Initial capacity, measure not stated
Under construction
Kajaani data centre campusXTX Markets
Kajaani
22.5 MW
Under construction
Koria DC1 (TikTok Kouvola)Hyperco and DayOne
Koria, Kouvola
Capacity not published
Under construction
Loviisa Eastern Junction campusHyperco
Loviisa
Capacity not published
Under construction
Vaala data center campusGoogle
Nuojuankangas, Vaala
830 MW
Maximum grid power draw at full build, preliminary
Planned
Jämsä AI campus (former Kaipola mill)Sesterce
Kaipola, Jämsä
600 MW
After the second phase, measure not stated (first phase 200MW; press report)
Planned
Sudentulli campus, KlaukkalaDayOne
Klaukkala, Nurmijärvi
560 MW
Total electrical power, tentative and phased
Planned
Rovaniemi Hietavaara data centreFCDC
Hietavaara, Rovaniemi
500 MW
Measure not stated (press report)
Planned
QTS Forssa data centreQTS (Blackstone)
Pikku-Muolaa, Forssa
441 MW
Planned
Kittfall data centre, VirkkalaHyperco
Virkkala, Lohja
300 MW
Planned
FIN05 SaloatNorth
Salo
230 MW
Gross campus power capacity (up to 160MW IT)
Planned
Järvenpää data centrePrime Data Centers
Emalikatu, Järvenpää
130 MW
Planned
Koria DC2Hyperco
Hiivuri, Kouvola
100 MW
Planned
Varkaus hyperscale campusAPL Group
Ranta-Luttila, Varkaus
100 MW
Up to, measure not stated (first phase 60MW)
Planned
Herva data centreMeta (Valoa Networks)
Ii
Capacity not published
Planned
Jokela data centreJokelan Vihreä Maa
Jokela, Tuusula
Capacity not published
Planned
Koskelonniitty siteHyperco
Espoo
Capacity not published
Planned
Kymin Ruukki data centre projectNova Complex
Kymin Ruukki, Kouvola
Capacity not published
Planned
Mykänmaa data centrePohjan Voima
Keminmaa
Capacity not published
Planned
Vaasa datacenter site (GigaVaasa)Microsoft
Vaasa and Mustasaari
Capacity not published
Planned
Voikkaa site (former UPM mill)Novagen Data Centre
Voikkaa, Kouvola
Capacity not published
Planned
Kajaani data center (Otanmäki)Google
Otanmäki, Kajaani
Capacity not published
Paused
Muhos data centerGoogle
Muhos
Capacity not published
Paused

Not on the map: Finnish AI Factory campus, Applied Digital, location not published. Announced, 1,000 MW (Potential power capacity (press report)). Source

Not on the map: Sarvenmaa data centre, Polarnode, Keminmaa, location not published. Planned, 1,000 MW (Peak power demand of the whole area). Source

Not on the map: Uus-Olkkola data centre, Solano Renovables Finlandia, Pyhäjärvi, location not published. Planned, 900 MW (Capacity of the buildings, measure not stated (first phase 100MW)). Other figure: 100MW to start, scalable to several hundred megawatts (up to 800MW) (Solano release, through Pyhäjärvi municipality). Source

Subsea cables

The subsea cables that land in Finland, drawn as straight dashed lines between the towns each one lands at: an indicative route, not the path on the seabed. Cables with no Finnish landing town named yet are listed without a line.

  • C-Lion1 Cinia's cable from Helsinki to Rostock in Germany, with a branch to Hanko, in service since 2016. Cinia repaired faults in late 2024 and early 2025. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • Eastern Light Sweden-Finland I Eastern Light's cable from Stockholm to Utö, Hanko, Helsinki and Kotka, in service since 2019. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • Eastern Light Sweden-Finland II A second Eastern Light route from Stockholm to the Helsinki area through Åland, under construction; Eastern Light gives no service date. The Kökar and Hanko landings come from government permit records. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • GlobalConnect Sweden to Finland cable GlobalConnect's fourth cable from Sweden to Finland, landing in Sweden, on Åland and at Turku, under construction for service by the end of 2026. No go-live notice found yet. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • GlobalConnect Baltic Sea cables Four new GlobalConnect cables from Gotland to Saaremaa and Hiiumaa, through Estonia to Tallinn and on to Helsinki. Seabed surveys started in October 2026, with service planned in 2027. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • Elisa Helsinki to Tallinn cables Elisa's submarine cables between Helsinki and Tallinn. In June 2026 Elisa, the Border Guard and the Navy tested acoustic monitoring of cables in the Gulf of Finland. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • Baltic Sea Submarine Cable Helsinki, Stockholm and Tallinn, in service since 2000, according to TeleGeography's listing. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • BCS North Phase 1 Hanko, Haradsholm, Helsinki and Mariehamn to Stavsnäs in Sweden, in service since 1998, according to TeleGeography's listing. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • BCS North Phase 2 Helsinki and Kotka to Logi in Russia, in service since 2000, according to TeleGeography's listing. Whether it is still in use is not confirmed. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • Botnia Vaasa to Umeå in Sweden, in service since 1994, according to TeleGeography's listing. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • Finland-Estonia 2 (EESF-2) Helsinki to Tallinn, in service since 1992, according to TeleGeography's listing. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • Finland-Estonia 3 (EESF-3) Helsinki to Meremõisa in Estonia, in service since 1994, according to TeleGeography's listing. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • E-FINEST Espoo to Tallinn, in service since late 2019, according to TeleGeography's listing. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • Finland Estonia Connection 1 (FEC-1) Helsinki to Tallinn, in service since January 2000, according to TeleGeography's listing. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • Finland Estonia Connection 2 (FEC-2) Helsinki to Tallinn, in service since 2000, according to TeleGeography's listing. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • STO-HEL-One Hamnäs, Lokalahti and Skatörarna to Nothamnsbacken in Sweden, in service since 2008, according to TeleGeography's listing. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • Mjolner East Planned for 2027, from Helsinki to Tallinn, Kihelkonna and Fårösund, according to TeleGeography's listing. Probably the same project as GlobalConnect's Baltic Sea cables; not confirmed. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • Mjolner West Planned for 2027, from Lokalahti to Östhammar in Sweden, according to TeleGeography's listing. Possibly the same cable as GlobalConnect's Sweden to Finland cable via Åland; not confirmed. Drawn as straight dashed lines between landing towns: an indicative route, not the path on the seabed. Source
  • C-Lion2 Announced by Cinia to link Finland, Sweden and Germany. No landing towns or date published yet, so it is not drawn. Source
  • Midgard Infra Sweden to Finland cable Announced on 8 October 2026: about 200km from the coast north-east of Stockholm to south-west Finland, building from early 2027 and in service in 2029. No Finnish landing town named yet, so it is not drawn. Source
  • Amber Cable A planned Baltic Sea cable with nine landing stations in six countries, Finland among them, in its study phase (Datacenter Forum, June 2026). No Finnish landing town named, so it is not drawn. Source
  • Far North Fiber A planned cable from Japan to Europe through the Northwest Passage, ready for service in 2029, with Cinia a partner. Its European landings are in Norway and Ireland, not Finland, so it is not drawn. Source
  • Merikarhu repair project Not a cable: a Finland, Sweden and Estonia project to keep cable repair equipment ready in the Baltic Sea, with EUR9.55 million of EU co-funding (Cinia, November 2026). Source
  • Elisa's planned new cables A Finnish government release on Elisa's applications for EU funding for new cables could not be read, so no details are given here yet. Source

Rules and the grid

What Finland's government and its grid operator, Fingrid, have decided or proposed for data centres, with the source for each.

  • Data centre register On 29 October 2026 the government gave Parliament a bill for a national data centre register (HE 282/2026). Data centres with at least 0.5MW of installed IT power would have to register, existing ones by 30 June 2027, and the law is planned to start on 1 April 2027. Government bill HE 282/2026 (Finlex), 29 October 2026
  • Data centre register The same bill estimates that Finland has over 40 operating data centres in 2026, over 30 of them with at least 1MW of IT power, and about 20 to 25 more projects pending. Government bill HE 282/2026 (Finlex), 29 October 2026
  • Grid connection priority A draft change to the Electricity Market Act, sent out for comment by the Ministry of Economic Affairs and Employment on 18 September 2026, would give grid connections an order of priority. Data centres over 10MW would be in the third priority group, and could move up to the second by committing to flexibility covering at least 80% of their peak demand. It is planned to start on 1 January 2027 and was still a draft in late November 2026. Fingrid, 13 November 2026; pv magazine, 21 September 2026
  • Electricity tax Since 1 July 2026 electricity used in data centres is taxed in class I instead of the lower class II. That took the energy tax part from 0.05 to 2.24 cents per kWh, or 2.325 cents with the security of supply fee. Finnish Tax Administration; Finnish Tax Administration, tax rates
  • State support On 1 September 2026 the government decided not to go ahead with a planned new support scheme for data centres, Finance Minister Riikka Purra said after the 2027 budget talks. Xinhua, through The Star, 2 September 2026
  • Grid connections By mid-October 2026, data centre projects with signed grid connection agreements planned a final size of over 5 gigawatts in total, based on developers' own figures and counting projects on local networks. Fingrid notes that a signed agreement does not guarantee a project is built in full. Fingrid, 23 October 2026; Fingrid, 18 August 2026

Changes since October 2026

  1. Finland map added. Source

About This Map

This map tracks Finland's big data centre campuses from Helsinki to Lapland and the subsea cables that land in Finland. Capacity is shown with the measure its source uses, and campuses without a published figure are marked "Capacity not published".

Records come from owners' and operators' own pages and releases, Finnish government and regulator releases, environmental assessment documents and cable owners' pages. Where two sources disagree, the map uses the owner's or the government's figure and gives the other figure, with its source, in the site's details.

Many campuses are placed at a street, suburb or nearby landmark rather than the exact site, and are marked "Location approximate". Cable routes are straight dashed lines between landing towns: they show what each cable connects, not its path on the seabed.

Map researched and maintained by CertifiedStrategic.com.

Campus records: each owner's or operator's own pages and Finnish government and regulator releases, linked from each record. Cable records: owners' pages and TeleGeography's Submarine Cable Map listing; the lines are our own indicative drawing. Site and town locations: OpenStreetMap contributors, through the Photon geocoder. Base map: OpenFreeMap, OpenMapTiles, OpenStreetMap contributors.