Firmus logo
    Neocloud profilePrivate; ASX float withdrawn 9 October 2026

    Firmus

    Firmus is an Australian neocloud and AI-factory developer with two sites operating, in Melbourne and Singapore, and projects in Tasmania, South Australia, Indonesia and Malaysia. It withdrew its planned ASX float on 9 October 2026 and is seeking private funding.

    Founded 2019HQ Sydney, with operations across Australia, Singapore, Indonesia and MalaysiaCo-CEOs Oliver Curtis and Tim RosenfieldOwnership Private; ASX float withdrawn 9 October 2026
    46MW
    Operating now
    Melbourne and Singapore, Firmus figure reported by Startup Daily, 7 October 2026
    900MW+
    Contracted by customers
    across all customers and countries, company, 8 September 2026
    Above US$10.5bn
    Company valuation
    August 2026 round, company figure

    Profile summary

    Profile summary

    Founded

    2019; legal entity Firmus Grid Limited, trading as Firmus Technologies

    Headquarters

    Sydney, with operations across Australia, Singapore, Indonesia and Malaysia

    Ownership

    Private. Withdrew its planned ASX float, a A$7.1 billion base offer or about A$7.9 billion with the over-allotment option, on 9 October 2026, citing market conditions (ABC, 9 October 2026). The Firmus board said Firmus will now pursue capital from the private markets and consider alternative public and private market options (Maas Group ASX announcement, 9 October 2026). The float had been priced at A$11.00 a share (IPO term sheet reported by Reuters, 1 October 2026)

    Leaders

    Co-CEOs Oliver Curtis and Tim Rosenfield; co-founder Jonathan Levee

    Type

    AI-factory developer and operator, immersion cooled

    Flagship

    Project Southgate, three Tasmanian sites: St Leonards at Launceston, Bell Bay at Long Reach and Wesley Vale. Launceston is consented for 90MW across Stage 1a at 44MW and Stage 1b (Launceston City Council, September 2025)

    Tasmanian energy

    Firmus holds a three-year 104MW supply contract for Launceston through Aurora Energy (ABC, 4 September 2026) and expects to contract about 444MW across its three Tasmanian sites at full build. Hydro Tasmania is assessing that request and expects an outcome by the end of 2026 (Firmus and Hydro Tasmania submissions to Tasmania's parliamentary inquiry, September 2026; Hydro Tasmania)

    GPU fleet

    Roughly 36,800 NVIDIA GB300 in Tasmania and about 18,400 in Melbourne (company, 2 March 2026)

    Platform

    Sustainable Metal Cloud immersion plus AI FactoryOS

    Connectivity

    Cornerstone customer on SUBCO's APX East cable between Australia and the United States, committing approximately US$300m for up to 150Tbps of dedicated capacity over 25 years, with the cable expected ready for service in Q4 2028 (company, 3 September 2026). Also a customer on SUBCO's Bernacchi-1 link between Tasmania and the mainland, expected operational Q2 2027

    Backers

    Coatue, NVIDIA (about 7.2 per cent, ABC and Forbes Australia, October 2026), Jane Street, Blackstone funds, Ellerston Capital, Regal Partners, Wilson Asset Management and Maas Group (3.2 per cent, bought in 2026 for about A$410 million; its JLE business has about A$1.1 billion of Firmus work orders across FY26 and FY27, on track for completion by the end of 2027, with A$373 million paid, Maas Group ASX announcements, 9 and 16 October 2026), on equity, with a US$10 billion debt facility led by Blackstone (February 2026)

    Latest capital

    US$2bn equity round announced 7 Aug 2026 and fully subscribed, meaning investors committed to the whole amount offered, valuing the company above US$10.5bn once that money is counted in, by the company's account

    Delivery capability

    Agreed on 13 Aug 2026 to acquire, for A$300 million, the projects, design and fabrication businesses of Benmax, the Australian cooling and modular systems manufacturer it has worked with on AI infrastructure delivery in Australia and Asia since 2020

    Named customers

    Meta, running NVIDIA GB300 systems at the Melbourne AI factory and signed for capacity in Southeast Asia (named September 2026), Fireworks in the company's Asia-based AI Cloud Region (August 2026), OpenAI, anchor customer for two AI factories in Malaysia under a multi-year agreement (September 2026), and Thinking Machines Lab, anchor customer for its Asia AI-Cloud Region on NVIDIA GB300 systems under a multi-year agreement (October 2026)

    Contracted capacity

    More than 900MW across all customers and all countries, by the company's account at 8 September 2026; 912MW according to the Australian Financial Review (9 October 2026)

    Operating sites

    Two, in Melbourne (its Brooklyn cluster in CDC's Brooklyn campus, running for Meta) and Singapore, about 46MW between them (Firmus figure reported by Startup Daily, 7 October 2026), with five more in development across the Asia-Pacific (company, 27 August and 8 September 2026)

    Key figures

    Profile summary

    Southgate Launceston, approved size

    90MW

    Consented September 2025; under construction, due to start operating in early 2027

    Planned South Australian IT load

    About 2.3GW

    Tailem Bend and Stirling North, on about 2.7GW of planned grid connection

    South Australian power deal

    600MW

    12-year Gunvor agreement for 600MW of firm electricity for the planned Tailem Bend and Stirling North campuses

    Overview

    What Firmus does

    Firmus was founded in 2019 by Oliver Curtis, Tim Rosenfield and Jonathan Levee, and began as a bitcoin miner in Launceston, Tasmania, before moving into AI infrastructure. It is headquartered in Sydney with operations across Australia, Singapore, Indonesia and Malaysia, and Curtis and Rosenfield are co-chief executives.

    In August 2026 Firmus announced a fully subscribed US$2 billion equity round, with follow-on participation from Coatue and NVIDIA, new investment from Blackstone Tactical Opportunities and other Blackstone funds, and participation from Jane Street. The company says the round values it above US$10.5 billion once the new money is counted in, and takes total new equity raised in the twelve months to August 2026 above US$3 billion. It says the capital will fund the Project Southgate rollout across Australia alongside expansion into other Asia-Pacific markets. Firmus also has a US$10 billion debt facility led by Blackstone, agreed in February 2026. It withdrew a planned A$7.1 billion ASX float on 9 October 2026, saying the terms on offer would not reflect its long-term growth prospects, and is seeking private funding.

    Its flagship Australian project is Project Southgate in Tasmania, which is now three separate sites: St Leonards at Launceston, Bell Bay on the former Gunns pulp mill land at Long Reach, and Wesley Vale. Launceston was consented in September 2025 at a combined 90MW of AI infrastructure, made up of Stage 1a at 44MW and Stage 1b, and a further 300MW second stage was planned at the time, subject to final approvals. Firmus runs a Melbourne deployment, its Brooklyn cluster in CDC's Brooklyn campus, where Meta runs NVIDIA GB300 systems, and is developing South Australian campuses at Tailem Bend and Stirling North, planned at about 2.3GW of computing load on about 2.7GW of grid connection, with Firmus seeking state sponsorship for their approvals. A national rollout of up to 1.6GW on CDC Data Centres' infrastructure, announced with NVIDIA in October 2025, will not go ahead. Firmus says the two companies agreed earlier in 2026 not to proceed, after about 42MW was deployed in Melbourne (W.Media, 6 October 2026).

    Deployment

    Facilities and capacity

    Firmus runs about 42MW in Melbourne (October 2026), in CDC's Brooklyn campus. Its Australian build is centred on Project Southgate, three Tasmanian sites at Launceston, Bell Bay and Wesley Vale. Bell Bay was approved by George Town Council on 25 August 2026; appeals against the approval and one of its conditions are before the Tasmanian Civil and Administrative Tribunal.

    Site

    Project Southgate, St Leonards

    Host or location

    Tasmania campus

    City/region

    Launceston

    Scale or hardware

    90MW consented across Stage 1a at 44MW and Stage 1b (Launceston City Council, September 2025); 84MW of critical IT load, by Firmus's account

    Status

    Under construction, due to start operating in early 2027 (offer documents, Startup Daily, 7 October 2026)

    Site

    Project Southgate, Bell Bay

    Host or location

    Former Gunns pulp mill land at Long Reach

    City/region

    Bell Bay, Tasmania

    Scale or hardware

    288MW, which the company describes as the site's draw

    Status

    Approved by George Town Council 25 August 2026 with 15 conditions; under appeal at TASCAT

    Site

    Project Southgate, Wesley Vale

    Host or location

    Tasmania

    City/region

    Wesley Vale

    Scale or hardware

    Initial approximately 26MW growing to approximately 52MW of capacity, or 23MW growing to about 46MW of critical IT load, company figures

    Status

    Development application lodged; Latrobe Council asked the state to declare it a major project in September 2026, and the state has asked Firmus for more information before deciding (Pulse Tasmania, 25 September 2026). Firmus has until 15 December 2026 to lodge a complete major project proposal, The Urban Developer reported on 19 October 2026

    Site

    Wesley Vale research facility

    Host or location

    Existing warehouse at the former Wesley Vale pulp mill

    City/region

    Wesley Vale

    Scale or hardware

    26MW, for AI computing and research into grid-responsive operation and how batteries could reduce reliance on diesel backup generators (ABC, 4 November 2026)

    Status

    Approved by Latrobe Council staff (ABC, 4 November 2026); separate from the Wesley Vale AI factory application

    Site

    Southgate Melbourne

    Host or location

    Brooklyn cluster, in CDC's Brooklyn campus

    City/region

    Melbourne

    Scale or hardware

    About 18,400 NVIDIA GB300 (company, 2 March 2026); about 42MW deployed (W.Media, 6 October 2026)

    Status

    Operating; runs for Meta (company, 29 September 2026)

    Site

    Singapore AI factory, outside Australia

    Host or location

    Not disclosed

    City/region

    Singapore

    Scale or hardware

    Not disclosed

    Status

    Operating (company, 8 September 2026)

    Site

    Batam AI factory, outside Australia

    Host or location

    Built with DayOne under an NVIDIA partnership

    City/region

    Batam, Indonesia

    Scale or hardware

    360MW, sized for up to 170,000 NVIDIA GPUs. Firmus is in talks for about US$10 billion to buy the chips: about US$7.5 billion of debt and US$2.5 billion of equity, with NVIDIA sharing revenue and providing credit support (Bloomberg, 23 September 2026)

    Status

    In development; first capacity targeted for the first quarter of 2027 (company, June 2026)

    Site

    Malaysian AI factories, outside Australia

    Host or location

    Firmus AI Factory sites

    City/region

    Malaysia

    Scale or hardware

    Two sites with OpenAI as anchor customer under a multi-year agreement. The offer documents named them as KVTP at 192MW, due in 2027, and SVTP at 206MW, due in 2027 to 2028, both in Kuala Lumpur (Startup Daily, 7 October 2026); which site serves OpenAI and the contract value are undisclosed. NVIDIA Vera Rubin NVL72 on the DSX platform integrated with the Firmus HyperCube

    Status

    Announced 8 Sep 2026

    Map of Firmus data centre and AI factory locations in Australia and Asia: operating sites in Melbourne and Singapore, and announced projects at Batam in Indonesia (360MW), Bell Bay (288MW), St Leonards in Launceston (90MW) and Wesley Vale (about 52MW) in Tasmania, planned campuses at Tailem Bend and Stirling North in South Australia (2.7GW), plus two sites in Malaysia with OpenAI as anchor customer
    Where Firmus is building AI factories. Source: Firmus announcements, October 2025 to September 2026; George Town Council; Launceston City Council; Reuters (24 September 2026).

    Map

    Australian deployment map

    Pins show metros with deployed or contracted Australian capacity. States with a mapped deployment are tinted blue.

    SATASVIC
    1Launceston1Melbourne1Tailem Bend1Stirling North
    Deployment pin States with a presence

    Capital and partners

    Funding and investors

    Date

    Oct to Nov 2026

    Round or instrument

    Private raise, in talks

    Amount

    About US$3bn (A$4.4bn) through new shares, debt and customer prepayments (AFR, 15 Nov 2026); earlier reported as up to about US$3bn from existing investors (Bloomberg via Reuters, 9 Oct 2026)

    Valuation / terms

    Talks with NVIDIA and existing backers after the float was withdrawn (AFR and Bloomberg, 9 Oct 2026). Prepayments covering about 12.5% of contracts sought from customers including NVIDIA and Meta, the most advanced part of the plan (AFR, 15 Nov 2026). Equity raised to date about A$4.7bn (AFR)

    Lead / anchor investors

    NVIDIA and existing backers; customers including NVIDIA and Meta for prepayments (AFR)

    Date

    9 Oct 2026

    Round or instrument

    ASX IPO, withdrawn

    Amount

    A$7.1bn base offer (about US$4.94bn), or up to about US$5.5bn (about A$7.9bn, AFR) with the over-allotment option of up to US$500m (IPO term sheet reported by Reuters, 1 Oct 2026)

    Valuation / terms

    Priced at A$11.00 a share, a US$30.6bn equity value (Reuters, 1 Oct 2026). As bids closed on 8 Oct the banks were working on around A$8.25 a share (AFR). Withdrawn 9 Oct 2026; Firmus is seeking private funding

    Lead / anchor investors

    Lead managers Morgan Stanley, Bank of America, JPMorgan and Morgans

    Date

    7 Aug 2026

    Round or instrument

    Equity round

    Amount

    US$2bn

    Valuation / terms

    Fully subscribed; values the company above US$10.5bn once the new money is counted in, by the company's account. These investors receive more shares if Firmus does not list by 30 November 2026 (AFR)

    Lead / anchor investors

    Coatue and NVIDIA follow-on, Blackstone Tactical Opportunities and other Blackstone funds, Jane Street

    Date

    Apr 2026

    Round or instrument

    Equity round

    Amount

    US$505m

    Valuation / terms

    US$5.5bn post-money, by the company's account

    Lead / anchor investors

    Led by Coatue, with NVIDIA

    Date

    9 Feb 2026

    Round or instrument

    Debt facility

    Amount

    US$10bn

    Valuation / terms

    Debt financing facility

    Lead / anchor investors

    Blackstone Tactical Opportunities, Blackstone Credit and Insurance and affiliated funds, with support from Coatue

    Date

    14 Nov 2025

    Round or instrument

    Equity round

    Amount

    A$500m

    Valuation / terms

    About A$6bn post-money, by the company's account

    Lead / anchor investors

    Morgans as sole lead manager

    Date

    16 Sep 2025

    Round or instrument

    Equity round

    Amount

    A$330m

    Valuation / terms

    A$1.85bn post-money, by the company's account

    Lead / anchor investors

    Ellerston Capital as cornerstone; NVIDIA joined as an investor

    Technology

    Technology and platform

    Firmus uses immersion and liquid cooling for high-density GPU deployments and attributes energy-reduction claims to its platform.

    Sustainable Metal Cloud Hypercubes are used across STT GDC-linked deployments in Singapore, India and Australia by the company's account.

    AI FactoryOS is the company's software layer for managing AI-factory operations.

    In August 2026 Firmus agreed to acquire, for A$300 million, the projects, design and fabrication businesses of Benmax, the Australian cooling and modular systems manufacturer it has worked with since 2020, bringing that build capability in-house.

    Firmus has named Fireworks as a customer of its AI Cloud under a multi-year agreement, deploying on Firmus AI Factory infrastructure using NVIDIA Grace Blackwell GB300 and Vera Rubin systems in the company's Asia-based AI Cloud Region. On 20 October 2026 it named Thinking Machines Lab as an anchor customer for the same region, on NVIDIA GB300 systems.

    Firmus is a cornerstone customer on SUBCO's APX East cable between Australia and the United States, committing approximately US$300m for up to 150Tbps of dedicated capacity over 25 years, with the cable expected ready for service in Q4 2028 (company, 3 September 2026). Also a customer on SUBCO's Bernacchi-1 link between Tasmania and the mainland, expected operational Q2 2027.

    Comparison

    How Firmus compares

    Neutral peer comparison using stable, sourced axes. Figures that move are attributed to company statements or reports.

    Company

    Sharon AI

    Listing

    NASDAQ:SHAZ

    Australian capacity

    Roughly 1,000 GPUs live at NEXTDC M3 in Melbourne, plus Equinix SY3 and SY5 and GreenSquareDC SYD1 in Sydney. 212MW expected across Australia and New Zealand in 2027, 129MW of it contracted, company figure

    GPU platform

    NVIDIA B200 / B300, GB300 planned

    Deployment & cooling

    Hosted mainly in NEXTDC facilities

    Backing

    Situational Awareness, Oaktree, public markets

    Company

    Firmus

    Listing

    Private; ASX float withdrawn 9 October 2026

    Australian capacity

    About 42MW running in Melbourne. Project Southgate in Tasmania has Launceston consented for 90MW, Bell Bay approved for 288MW (under appeal) and Wesley Vale about 52MW lodged

    GPU platform

    NVIDIA GB300

    Deployment & cooling

    Own immersion-cooled AI factories

    Backing

    Coatue, NVIDIA, Jane Street equity; Blackstone equity and debt

    Company

    IREN

    Listing

    NASDAQ:IREN

    Australian capacity

    None running in Australia yet. Planned 800MW campus at Bundey, SA, and proposed 900MW Redbank campus near Wagga Wagga, NSW. Operating data centres are in the US and Canada

    GPU platform

    NVIDIA GPU clusters

    Deployment & cooling

    Own North American data centres; Bundey campus planned

    Backing

    Public markets; Microsoft, NVIDIA and AI research lab contracts

    Latest coverage

    Firmus in the news

    Common questions

    Questions about Firmus

    What is Firmus?

    Firmus is an Australian AI infrastructure company that builds and runs AI factories, data centres designed to run large clusters of NVIDIA GPUs, and rents that capacity to technology companies. It was founded in 2019, has two sites operating, in Melbourne and Singapore, and five more in development across the Asia-Pacific. It withdrew its planned ASX float on 9 October 2026 and is seeking private funding.

    What happened to the Firmus IPO?

    Firmus withdrew its planned ASX float on 9 October 2026, the day after bidding from large investors closed. It had priced its shares at A$11.00 to raise A$7.1 billion, about US$4.94 billion, in its base offer, or about A$7.9 billion with the over-allotment option, with trading due to start on 23 October (Reuters, 1 October 2026, and the AFR). When bids closed on 8 October the banks were working on a price of around A$8.25 a share, the AFR reported; Firmus never confirmed a new price. The company said the terms on offer would not reflect its long-term growth prospects; its board said Firmus will now pursue capital from the private markets and consider alternative public and private market options, Maas Group told the ASX on 9 October. The AFR and Bloomberg reported it is in talks with NVIDIA and existing backers about a private round. Bloomberg also reported, via Reuters, that it was exploring raising up to about US$3 billion from existing investors. On 15 November 2026 the AFR reported that Firmus hopes to raise about US$3 billion (A$4.4 billion) privately through new shares, debt and customer prepayments, and that talks on prepayments covering about 12.5 per cent of its contracts, with customers including NVIDIA and Meta, are the most advanced part of the plan.

    What is Firmus valued at?

    Firmus's last private round, a US$2 billion raise that closed on 7 August 2026, valued the company above US$10.5 billion, by its own account. That followed US$5.5 billion in April 2026, about A$6 billion in November 2025 and A$1.85 billion in September 2025. For the float, the AFR and The Australian reported a valuation near A$50 billion on 14 September 2026. Research from Morgan Stanley and Bank of America, two of the banks that managed the float, put Firmus's enterprise value, which includes debt, at US$65 billion to US$90 billion and US$58 billion to US$70.4 billion respectively, the AFR reported on 24 September 2026. At the A$11 offer price, Firmus's equity would have been valued at US$30.6 billion (about A$44 billion at Reuters' exchange rate), Reuters reported from the term sheet on 1 October 2026. Reuters also reported that analysts at the banks on the deal estimate about US$30 billion of debt, which puts the value of the whole business near US$60 billion. The float was withdrawn on 9 October 2026, before trading began.

    Who owns Firmus?

    Firmus is privately owned. It withdrew its planned ASX float on 9 October 2026 and is seeking private funding. It was founded by Oliver Curtis, Tim Rosenfield and Jonathan Levee, and Curtis and Rosenfield are co-chief executives. Its equity investors include Coatue, NVIDIA (about 7.2 per cent, according to the ABC and Forbes Australia), Blackstone funds, Jane Street, Ellerston Capital, Regal Partners and Wilson Asset Management, and Maas Group, which paid A$410 million for a 3.2% stake in 2026, Capital Brief reported. The AFR's Street Talk column reported on 14 September 2026 that the founders and backers including Ellerston Capital, Regal Partners and Wilson Asset Management would keep their shares out of the float's offer book.

    What does Firmus expect to earn?

    Firmus estimates its data centres, once developed, will earn a combined US$5 billion a year within five years, according to a person cited by Reuters on 24 September 2026. A draft prospectus forecasts an after-tax loss of US$77 million, on a pro forma basis, for the six months to 31 December 2026, according to two people familiar with it, with the money raised in the float funding further capital spending. Firmus declined to comment to Reuters.

    Where is Project Southgate?

    Project Southgate is Firmus's flagship Australian project in Tasmania. It is three separate sites: St Leonards at Launceston, consented for 90MW; Bell Bay at Long Reach, approved for 288MW; and Wesley Vale, where a development application has been lodged for about 52MW at full build. Separately, Latrobe Council staff have approved a 26MW Firmus AI research and development facility in an existing warehouse at Wesley Vale, the ABC reported on 4 November 2026.

    How does Firmus power its Australian campuses?

    Its two planned South Australian campuses, at Tailem Bend and Stirling North, are covered by a 12-year agreement with Gunvor Group for 600MW of firm electricity, tied to about 1.2GW of new renewable generation and about 1.5GWh of new battery storage. In Tasmania, Launceston runs on a three-year 104MW contract through Aurora Energy, and Firmus expects to contract about 444MW across its three Tasmanian sites at full build, a request Hydro Tasmania is assessing and expects to decide by the end of 2026.

    Profile updates

    Add to this profile

    Represent this company or have updated source material? Send a correction, right of reply or profile update to the editorial team.

    Last updated: 18 Nov 2026