AirTrunk lines up 610MW of Hunter renewables for Kurri Kurri
By Winston Su, Editor · · Add us as a preferred source on Google

At a glance
AirTrunk has signed an exclusivity agreement with European Energy Australia over two Hunter projects to help supply its proposed Kurri Kurri data centre.
The projects add 260MW of solar and up to 350MW of wind, with more than 800MWh of batteries, and are due to connect to Ausgrid's upgraded Hunter network.
Solar and batteries are due to operate in 2030 and wind in 2032, and the two companies are discussing a long-term power purchase agreement.
The projects are the kind of new supply, with wind and storage, that NSW's Data Centre Guidelines ask for, and the two companies are discussing a long-term contract.
Public comment on the Kurri Kurri impact statement closed on 11 November 2026 with 759 submissions, and AirTrunk has two months to respond.
AirTrunk has named the developer it wants to supply power to its proposed data centre at Kurri Kurri in the NSW Hunter. The company signed an exclusivity agreement with European Energy Australia, the local arm of Danish renewable developer European Energy, to progress two projects in the Hunter-Central Coast Renewable Energy Zone. The two companies are discussing a long-term power purchase agreement to support AirTrunk's NSW demand, including Kurri Kurri.
The campus is planned for the former Hydro Aluminium smelter site at Loxford, and Anthropic is in advanced talks to anchor it, the Australian Financial Review reported on 22 September 2026. The NSW Data Centre Guidelines expect a project of that size to contract new generation and storage to match its own demand, and AirTrunk told the NSW Government in its planning application that it would do so through power purchase agreements and firming contracts, which secure backup supply for when solar and wind output falls. European Energy's projects are new and include wind and storage, the kind of supply the NSW test asks for, and the two companies are discussing a long-term contract.
European Energy's Hunter projects add up to 610MW of generation
The two projects carry 260MW of solar, up to 350MW of wind and more than 800MWh of battery storage, so up to 610MW of new generation with batteries alongside.
Asset | Size | Due to operate |
|---|---|---|
Solar | 260MW | 2030 |
Batteries | More than 800MWh | 2030 |
Wind | Up to 350MW | 2032 |
Source: AirTrunk, 12 November 2026.
European Energy plans to connect both projects to Ausgrid's upgraded 132kV network, subject to approvals and technical assessments. Ausgrid, the electricity network operator for the Hunter, Sydney and the Central Coast, is upgrading its existing Hunter network with the NSW Government's renewable energy zone coordinator, EnergyCo, so the zone can carry an additional 1GW of renewable energy by 2028.
European Energy also built the 31MW Mulwala Solar Farm in the NSW Riverina. Most of its output goes to AirTrunk, and it was officially opened in November 2026.
"Digital growth must bring new energy with it," AirTrunk founder and chief executive Robin Khuda said in the announcement. AirTrunk's associate vice-president of energy, Sabooh Whitelaw, said more renewable generation and firming will be needed to support Kurri Kurri and the company's wider NSW needs.
NSW guidelines ask AirTrunk for ten-year contracts with new projects
The contract AirTrunk is discussing has to meet the energy test in the NSW guidelines. The test asks a data centre to enter power purchase and firming agreements with new NSW generation, signed for at least ten years with projects that have not reached a final investment decision. At least 40 per cent of the contracted energy has to come from wind, and storage has to equal at least a quarter of the generation capacity for four hours. From the fourth year of operation, contracted supply has to match the data centre's annual average demand.
The announced batteries are larger than the storage test requires on an energy basis: a quarter of 610MW of generation, held for four hours, is about 610MWh, against more than 800MWh announced. Both projects are still in development, so contracts signed before either project's final investment decision would count as new supply, and the wind project counts toward the 40 per cent wind share.
AirTrunk's compliance assessment, lodged with its environmental impact statement, says the company will meet the test through a portfolio of power purchase agreements and firming contracts, signed progressively as the campus's demand grows. It gives contracted new generation priority over renewable energy certificates, the tradeable records of renewable output.
AirTrunk's announcement also cites the Australian Government's expectation that new data centres bring additional clean generation or storage to offset their demand. Energy ministers agreed in July 2026 to progress rules requiring that generation to be built in the state hosting the data centre.
European Energy's projects arrive as Kurri Kurri ramps up
AirTrunk's greenhouse gas assessment, part of its environmental impact statement, assumes the campus opens in the 2027-28 financial year, with tenants using 66 per cent of its capacity in the first year and 90 per cent from 2028-29. On that timetable the fourth year of operation, when contracted supply has to match average demand, is 2030-31. European Energy's solar and batteries are due to start in 2030, and its wind project in 2032, after that fourth year.
The impact statement puts the campus's total power consumption at 550.5MW at worst-case maximum demand, against the 540MW figure in its earlier scoping documents, and its greenhouse gas assessment puts average energy use at about 3.6 million MWh a year on the operating case it was assessed on. AirTrunk matched about 73 per cent of its electricity use with renewables across its portfolio in FY26 and has committed to 100 per cent by 2030.
AirTrunk has two months to answer 759 submissions
The power contracts sit alongside the planning approval the campus still needs. Public comment on the impact statement ended on 11 November 2026, and the NSW planning portal lists 759 submissions. The Department of Planning, Housing and Infrastructure wrote to AirTrunk's planners on 12 November asking for a submissions report within two months, and the time until AirTrunk lodges it does not count toward the assessment period.
Ausgrid told the department in its submission of 11 November that formal connection discussions with AirTrunk are underway, including the design of the proposed 132kV feeder crossings. AirTrunk's compliance assessment describes a flexible connection agreement it is to sign with Ausgrid, under which the network operator could require Kurri Kurri to cut its grid demand by up to 150MW for at least two hours.
What to watch
The power purchase agreement. AirTrunk and European Energy are discussing a long-term contract, and the NSW guidelines require a term of at least ten years.
The submissions report. AirTrunk's response to the 759 submissions and to agency advice is due within two months of the department's letter of 12 November 2026.
More NSW supply. AirTrunk says more renewable generation and firming will be needed as Kurri Kurri ramps up toward 90 per cent utilisation.
Keep reading the market
Get The Strategic Brief in your inbox every Thursday.
The leading Australian data centre and AI infrastructure newsletter.
Your Next Read

Anthropic is in advanced talks for AirTrunk's Kurri Kurri campus

AirTrunk plans up to US$30bn for Japan

AirTrunk signs MoU for 1.8GW of campuses in Andhra Pradesh
Latest Headlines
Dataspace launches with 14.5MW across five ex-Fujitsu sites
17 Nov 2026US acts to stop China renting AI chips in Asian data centres
17 Nov 2026Firmus seeks upfront payments from NVIDIA and Meta in A$4.4bn raise
17 Nov 2026Sharon AI misses on revenue as its price per megawatt climbs
17 Nov 2026IREN starts NSW approval for 900MW Wagga Wagga data centre
17 Nov 2026
Interested in reaching this audience? Advertise with us.