Ten days that changed Australian data centres in 2026
By Winston Su, Editor · · Add us as a preferred source on Google

To 18 November, 2026 has run 322 days. Ten of them changed how Australia's data centres are bought, paid for, regulated and built.
On each of them, a single announcement or report brought a new buyer, a new source of money, a new rule or a new limit on how fast capacity can arrive. They run from Canberra's national expectations in March to Jensen Huang's resignation from NVIDIA in November. AI labs and NVIDIA joined the cloud companies as buyers and backers, Canberra committed to mandatory standards, and the setbacks came from a pulled float and a suspended power upgrade in Melbourne, before NVIDIA changed chief executive.
1. The day Canberra set terms for AI's builders

23 March 2026: The federal government publishes national expectations for data centres.
Industry Minister Tim Ayres, Energy Minister Chris Bowen and Assistant Minister Andrew Charlton released five expectations covering the national interest, energy, water, skills and research, and said the Commonwealth would prioritise proposals most closely aligned with them. Ayres said Australia was open for "the kind of business that puts Australia's national interest first". Anthropic signed a memorandum on 1 April committing to align any future Australian operations with them.
2. The day Microsoft put A$25 billion on Australia

23 April 2026: Microsoft commits A$25 billion to Australia.
Chief executive Satya Nadella announced with Prime Minister Anthony Albanese that Microsoft would invest A$25 billion in Australia by the end of 2029 and expand its footprint of 29 sites across three Azure regions by more than 140 per cent. The commitment came with a memorandum affirming the government's new expectations. Nadella called it "our biggest commitment in Australia".
3. The day an AI lab asked for almost as much capacity as Australia runs

5 July 2026: Anthropic's tender for at least 1.4GW is reported.
The Financial Review reported that Anthropic had issued a confidential tender for at least 1.4GW of Australian data centre capacity, a build of up to US$15 billion, with at least 1GW wanted in use by the end of 2027. Australia has 1.6GW of data centres operating, on figures industry body Data Centres Australia published in August. The tender went to CDC Data Centres, AirTrunk, NEXTDC, IREN and STACK, among others. Data Centres Australia chief executive Belinda Dennett told Capital Brief it would be a "significant step-change in demand".
4. The day data centres were told to bring their own power

15 July 2026: Albanese promises mandatory data centre standards.
In a speech at the University of Sydney, Albanese said the next generation of large data centres would have a legal obligation to underwrite new power supply, pay their full share of grid connection costs and put at least as much energy into the grid as they draw. He described the new framework as "clear, consistent and mandatory". First ministers agreed at National Cabinet on 26 August to develop the standards, which the Commonwealth intends to legislate in early 2027.
5. The day NVIDIA put 2GW on the Australian map

10 September 2026, Australian time: NVIDIA names eight Australian partners for up to 2GW.
NVIDIA said it was working with eight Australian partners to expand land, power and shell capacity for its AI factories, with "up to a 2-gigawatt buildout by 2027". The eight are Firmus, Sharon AI, IREN, CDC, NEXTDC, AirTrunk, AI cloud provider ResetData and network company Megaport. NVIDIA has financial ties to three of them. It takes a share of Sharon AI's cloud revenue under a six-year agreement for 72MW of new capacity, worth up to US$4.88 billion in Sharon AI's US filings. It holds a five-year warrant over up to 30 million IREN shares, and added to its Firmus stake in the August equity round.
6. The day Anthropic chose the Western Downs

16 September 2026: Anthropic signs its first Australian lease, in Queensland.
Queensland Premier David Crisafulli announced that Anthropic had signed an agreement to use part of the proposed Western Downs Digital Park near Dalby, a campus the ABC called a $32 billion data centre hub. Singapore-based developer Zerra DC has applied for four buildings totalling 1.44GW. "This is a major win that will deliver more jobs, put more energy into Queensland's grid and drive down power prices for Queenslanders," Crisafulli said. When the deal was announced, the lease needed Foreign Investment Review Board approval and Western Downs Regional Council was still assessing the application.
7. The day a float second only to Telstra's was pulled

9 October 2026: Firmus withdraws its ASX float.
Australian AI infrastructure company Firmus had offered shares at A$11 each in a float with a base offer of about A$7.1 billion, which would have been the second-largest IPO on the ASX on record, behind Telstra's in 1997. It withdrew the listing, citing market volatility, and said it would pursue a private fundraising round instead. On 20 October, Thinking Machines Lab, the AI company founded by former OpenAI chief technology officer Mira Murati, was named as an anchor customer for its AI cloud region in Asia.
8. The day a stalled Melbourne power upgrade held up NEXTDC's M3

21 October 2026: A power delay at M3 cuts NEXTDC's FY27 guidance.
NEXTDC told the ASX that the next increase in grid supply to M3, its West Footscray campus in Melbourne, is now expected in FY28. Electricity distributor Jemena suspended parts of its works in September, citing community and stakeholder opposition, and does not expect to resume before February 2027. NEXTDC cut its FY27 net revenue guidance to A$475 million to A$500 million, from A$615 million to A$640 million, and shelved new development projects and land acquisitions. Its shares closed 41.7 per cent lower, at A$5.35.
9. The day two rivals paid up for 9.9 per cent of NEXTDC

4 November 2026: Goodman and Digital Realty move for up to 9.9 per cent of NEXTDC.
Australian property and data centre developer Goodman and US data centre owner Digital Realty offered A$9.50 a share for up to 9.9 per cent of NEXTDC in an after-market book build, a move NEXTDC's board called opportunistic. On 9 November the pair confirmed they held 9.9 per cent at an average of A$9.22 a share. That average was 41 per cent above NEXTDC's A$6.53 close on 4 November, and slightly above the A$9.18 it last traded at before its 19 October trading halt.
10. The day Jensen Huang left NVIDIA

12 November 2026, US time: Jensen Huang resigns as NVIDIA's chief executive.
NVIDIA announced that its co-founder had resigned as president, chief executive and a director, effective immediately, after 33 years in charge. Chief financial officer Colette Kress is interim chief executive. NVIDIA's first results under Kress, on 18 November, Australian time, named Australia as the only country in NVIDIA's data centre highlights, for a planned buildout of up to 2GW by 2027.
Keep reading the market
Get The Strategic Brief in your inbox every Thursday.
The leading Australian data centre and AI infrastructure newsletter.
Your Next Read

NVIDIA's Jensen Huang resigns: what it means for Australia

Jensen Huang says an AI gigawatt costs US$50bn

Rene Haas: the Arm CEO in the frame to succeed Jensen Huang
Latest Headlines
Tasmania's lower house backs AI data centre moratorium
19 Nov 2026US pushes ahead with ban on new Chinese optical transceivers
18 Nov 2026Chalmers' super test reset could reach AI's power supply
18 Nov 2026NVIDIA's US$115.8bn quarter names Australia's planned 2GW AI build
18 Nov 2026Dataspace launches with 14.5MW across five ex-Fujitsu sites