DAMAC in serious talks for Australian data centre land
By Winston Su, Editor · · Add us as a preferred source on Google

At a glance
Dubai property group DAMAC is in "serious negotiation" for a big parcel of land in Australia to build data centres, founder Hussain Sajwani said on 12 November 2026.
Its data centre arm, DAMAC Digital, focuses on campuses of 100MW and up for AI chips, Sajwani said. It wants its global plan to reach 10GW by the end of 2027.
Sajwani started in catering in the early 1980s and founded DAMAC Properties in 2002. It has handed over more than 50,000 homes.
Sajwani says about US$9 billion of his US$20 billion US data centre pledge has been invested.
In Asia, DAMAC's named projects run from a 19.2MW building in Jakarta to a campus of up to 250MW under study in the Philippines.
Dubai property group DAMAC is negotiating to buy a large site in Australia for data centres. "We are in serious negotiation in Australia for a big parcel of land," founder Hussain Sajwani told the Bloomberg Invest Dubai conference on 12 November 2026. He said DAMAC is also in talks for a site in the UK.
DAMAC builds data centres through DAMAC Digital, which has projects in 14 countries. Sajwani said its focus is campuses of 100MW and up, designed mainly for AI chips and liquid cooling. DAMAC Digital plans 6GW of capacity and expects more than 700MW to be running by early 2027. It is owned by DAMAC Group, whose developer DAMAC Properties has handed over more than 50,000 homes since 2002. Sajwani says about US$9 billion of his US$20 billion US data centre pledge has been invested.
Sajwani founded DAMAC Properties in 2002 and Edgnex in 2021
Sajwani started a catering business in the early 1980s, with customers including the US military and construction company Bechtel. In the 1990s he moved into Dubai hotels and property.
He founded DAMAC Properties in 2002, when Dubai opened property ownership to foreign buyers. By March 2025 it had delivered more than 48,000 units. DAMAC and the Trump Organization opened the Trump International Golf Club Dubai in February 2017, and Sajwani's investment company bought Italian fashion house Roberto Cavalli in 2019. In June 2021 he offered to take DAMAC Properties private.
He launched the data centre business in 2021 as Edgnex, and renamed it DAMAC Digital in June 2025. Sajwani said in March 2022 that the idea came to him during Covid-19 lockdowns in 2020, and that his property background gave the business an edge. "We can build data centres at a more reasonable cost than our competitors," he said.
The business began with a 12MW campus. By February 2023 it was expanding its data centres in Riyadh and Dammam, in Saudi Arabia, from 20MW to 55MW. DAMAC Digital says it has data centres running in Saudi Arabia and Thailand, and on 2 June 2026 it said it had broken ground on 10 more sites in the previous five months. It aims to have 2GW running by the end of March 2028.
The company says it has partnerships with five global hyperscalers. More than 90 per cent of its data centres are designed for liquid cooling, and they are built to take NVIDIA's next-generation Vera Rubin systems.
DAMAC aims to grow its pipeline to 10GW by the end of 2027
At the Bloomberg conference, Sajwani said DAMAC will keep buying land outside the US over the next 12 to 18 months. The group's plan stands at about 6,000MW, and Sajwani set a target of 10GW by the end of 2027.
Region | Planned capacity | Named markets or sites |
|---|---|---|
Asia | About 2,500MW | Thailand, Indonesia, Malaysia, the Philippines |
Europe | About 2,500MW | Spain, Italy, Greece, Türkiye, Finland |
United States | About 1,000MW | Three sites with about 600MW of IT load |
Source: Hussain Sajwani at Bloomberg Invest Dubai, via TradeArabia and Arabian Business; DAMAC Digital, 2 June 2026.
Sajwani pledged US$20 billion for US data centres in January 2025, alongside then President-elect Donald Trump. He expects the US to stay the largest data centre market. But he said limits on power, land and environmental approvals there could push companies to invest in other countries.
DAMAC's Asian projects range from 19MW in Jakarta to 250MW in Laguna
In Bangkok, DAMAC Digital is building a 20MW campus in two buildings in the Rama 9 business district. It is a joint venture with Thai IT company Proen, and DAMAC owns 70 per cent.
In Jakarta, its 19.2MW JKT01 building on MT Haryono road topped out in early 2026, and its first phase was scheduled for the third quarter of the year. A larger 144MW AI campus is planned at Cikarang, east of Jakarta. In June 2025 its first phase was scheduled for December 2026.
In the Philippines, DAMAC Digital is studying a campus of up to 250MW in Laguna, south of Manila. Sajwani discussed it with President Ferdinand Marcos Jr. in Abu Dhabi in January 2026.
Project | Capacity | Stage |
|---|---|---|
Rama 9, Bangkok, Thailand | 20MW | First phase due in 2026 |
JKT01, MT Haryono, Jakarta | 19.2MW | Topped out; first phase scheduled for third quarter of 2026 |
Cikarang AI campus, Greater Jakarta | 144MW | Land bought March 2025; first phase scheduled for December 2026 |
Laguna, Philippines | Up to 250MW | Under study |
Source: DAMAC Digital and EDGNEX releases; The Nation Thailand; Indonesia Business Post, 26 March 2026; BusinessWorld, January 2026.
The four projects add up to about 430MW, against the 2,500MW Sajwani gave for Asia. Cikarang and Laguna are the two at 100MW or more.
Sydney costs less to build in than the US and Singapore
Sajwani said data centre building costs have risen about 30 per cent in two years, and could rise another 20 to 30 per cent. He said Asia is cheaper for labour and equipment, but that supply chain delays are the bigger problem.
Construction consultancy Turner & Townsend, majority-owned by property group CBRE, compares building costs in 62 cities. Its 2026 index puts Sydney at US$10.74 a watt and Melbourne at US$10.58.
Singapore is US$15.39, and the American average is US$12.08. Among DAMAC's Asian markets, Bangkok, Manila and the two Malaysian cities in the index cost less than Sydney, the Malaysian pair by about 6 per cent. Jakarta costs more.
These figures cover the building and its power and cooling plant. Land, the grid connection and the computers are extra. In Turner & Townsend's survey of 400 people who build data centres, 53 per cent said a grid connection takes one to two years, and another 32 per cent said longer.
Approval and connection take up to two years in Victoria
Industry body Data Centres Australia and researcher DC Byte track a 26.8GW pipeline of data centres in Australia, from running sites to early-stage proposals. Their October 2026 forecast counts 5.2GW of that as committed.
Investors told Certified Strategic in October 2026 that due diligence, planning approval and grid connection take 18 to 24 months in Victoria. In New South Wales, they said, planning approval alone takes 12 to 18 months. In Indonesia, DAMAC bought its Cikarang site in March 2025 and scheduled the first phase to open 21 months later.
Energy rule maker the Australian Energy Market Commission (AEMC) set new grid connection standards for large data centres on 12 November 2026. They apply to new connections of 30MW or more, and Sajwani said DAMAC focuses on campuses of 100MW and up.
Princeton Digital Group, a Singapore-based developer, is new to Australia too. It has told the competition regulator, the ACCC, that it owns no data centres here. Planning documents name it as the client for a 100MW campus, Project Genesis, at Campbelltown in Sydney's south-west, costed at more than A$1 billion. The developer is backed by Abu Dhabi's Mubadala, Warburg Pincus and Stonepeak.
Sydney developer Morehuman Property Group filed the scoping report in October 2026, the first step in the New South Wales planning process. Endeavour Energy, the Western Sydney electricity network, offered the site a grid connection in December 2025.
What to watch
The Australian site. Sajwani said DAMAC will buy land outside the US over the next 12 to 18 months. The UK is the other market where it is negotiating for a large site.
South-East Asia by year end. Reports put DAMAC Digital's target for the region at between 250MW and more than 300MW running by the end of 2026. Cikarang's first phase was scheduled for December 2026.
DAMAC Digital's 700MW milestone. The company expects more than 700MW running by the first quarter of 2027. That would be about a third of its 2GW target for March 2028.
The AEMC's next consultation. The AEMC is asking whether data centres should register with the market operator and limit how fast their power use can rise or fall. Submissions close on 17 December 2026, and a draft decision is due on 1 April 2027.
Keep reading the market
Get The Strategic Brief in your inbox every Thursday.
The leading Australian data centre and AI infrastructure newsletter.
Your Next Read

Data centre construction costs: how Australia compares with Asia

CDC reported front-runner for Anthropic’s 500MW Australia data centre contract

RBA staff expect A$115bn more data centre investment by 2028
Latest Headlines
Dataspace launches with 14.5MW across five ex-Fujitsu sites
17 Nov 2026US acts to stop China renting AI chips in Asian data centres
17 Nov 2026Firmus seeks upfront payments from NVIDIA and Meta in A$4.4bn raise
17 Nov 2026Sharon AI misses on revenue as its price per megawatt climbs
17 Nov 2026IREN starts NSW approval for 900MW Wagga Wagga data centre
17 Nov 2026
Interested in reaching this audience? Advertise with us.