    AEMC sets 30MW grid connection rules for data centres

    By Winston Su, Editor · · Add us as a preferred source on Google

    AEMC sets 30MW grid connection rules for data centres
    The AEMC's final rule sets grid connection standards for new data centres of 30MW and up, a size about 91 per cent of queued data centres outside Queensland exceed.

    At a glance

    • Australia's energy rule maker set its final grid connection standards for large data centres on 12 November 2026, and they took effect the same day.

    • The standards now apply automatically to new data centre connections of 30MW or more on both the high-voltage grid and local networks, where the March draft left local network sites of 30MW to 100MW to each network's discretion.

    • About 91 per cent of data centres seeking connection in the eastern and southern grid, outside Queensland, are above 30MW, on market operator data.

    • Networks can now assess a new site together with its existing and planned neighbours, so a new hall in Eastern Creek, Macquarie Park or Artarmon can be judged with the campuses beside it.

    • A second consultation, open until 17 December 2026, asks whether data centres should register with the market operator and limit how fast AI loads swing.

     

    The Australian Energy Market Commission (AEMC), which writes the rules for the National Electricity Market covering the eastern and southern states, published its final rule on access standards for large data centres on 12 November 2026. Access standards are the technical terms a site must meet to connect to the grid, and this rule sets how large data centres in Australia must behave when the grid has a fault. The commission had pushed its decision back from 29 October, and its March draft would have left sites of 30MW to 100MW on local distribution networks to each network's discretion.

    The final rule sets one 30MW line for the high-voltage grid and local networks alike, a size about nine in ten data centres seeking connection outside Queensland exceed, and it lets networks assess a cluster of sites as one large load.

    The standards now apply automatically from 30MW on both networks

    The final determination replaces the draft's three size tiers for local network connections with one threshold for both networks. A data centre supplied through power electronics, such as the converters in its backup power system, with a combined nameplate rating of 30MW or more, is now a "large inverter-based load". Every such site, on the high-voltage transmission grid or a local distribution network, now negotiates its connection terms between two levels: a minimum standard and a higher automatic standard, which a network must accept if a site meets it. Below 30MW, the network business decides whether the standards apply, based on whether the connection could affect the power system. The 5MW line in AEMO's system strength guidelines, which had sometimes been used to decide who the standards covered, no longer applies to these loads.

    Transgrid, which owns the NSW high-voltage grid, had told the commission the draft's 100MW line was "too large". The commission cites data from the Australian Energy Market Operator (AEMO), which runs the grid, showing about 91 per cent of data centres in the connection queue, excluding Queensland, have a proposed capacity above 30MW. AEMC chair Anna Collyer said a customer big enough to materially affect the grid "must be treated as part of that grid".

    The automatic standard asks sites to ride through a dip to half of normal voltage

    The ride-through standard sets how far grid voltage can fall before a data centre may briefly stop drawing power, and how fast it must come back. The draft let a site stop drawing power once voltage fell below 70 per cent of normal. The final rule's automatic standard tightens that to half of normal. It asks a site to stay connected through dips between half and 70 per cent of normal for one second, up from 240 milliseconds, to return to at least 90 per cent of its earlier draw within 500 milliseconds after a dip, and to limit how much extra current it draws while the dip lasts. The minimum standard, the usual floor for negotiation, requires a site to ride through dips to 70 per cent of normal for 140 milliseconds, and the rule lets a network and AEMO agree to less in some cases.

    Requirement

    Automatic standard

    Minimum standard

    Voltage dip to ride through

    Dips to half of normal, for one second

    Dips to 70% of normal, for 140 milliseconds

    Power back after a dip

    90% of earlier draw within 500 milliseconds

    No minimum standard

    Current drawn during a dip

    Rise of no more than 20% of rated current

    No more than 120% of rated current

    Source: Australian Energy Market Commission, Improving the NEM access standards, Package 2, final determination, 12 November 2026.

    Most data centres run their servers through an uninterruptible power supply (UPS), which switches to battery when grid voltage drops. The determination says working group feedback indicates "at least some UPS models" can operate down to half of normal voltage, and that 500 milliseconds matches the fastest recovery many UPS models used in data centres can achieve. It describes the minimum standard as non-onerous on key aspects. The rule also confirms a UPS is assessed under the standards for loads rather than as a two-way unit like a battery, and one with an active front end, which controls the current it draws from the grid, is more likely to count as an inverter-based load.

    Networks can assess a cluster of sites as one large load

    AEMO's December 2025 analysis for the commission found that remote faults in Victoria can push voltage below half of normal across Greater Melbourne, and that a combined response from smaller sites "can match or even exceed the severity of the response from larger individual connections". The final rule lets a network treat any such load as a large one where it considers that reasonable, having regard to "the aggregate impact of that connection together with any other electrically proximate inverter based load connections, including existing and planned new connections". Where smaller sites have a combined effect like a large one, the network may treat the group as a large load and apply the full standards. The draft allowed that test only for the ride-through standard and the standard for detecting grid instability; the final rule allows it for clustered sites of any size, against all the standards.

    Projects built in stages are covered too. Under the commission's industry fact sheet, a campus whose connection agreement covers all stages up to 40MW is a large load from its first stage. Where a 20MW site adds a second 20MW stage, the network either treats it as a change to the first connection, which can make the site a large load, or as a new connection it can assess together with the first.

    The CS directory shows where new connections would sit beside existing ones, much of it in Western Sydney. The table lists suburbs where the directory records sites under 30MW beside sites of 30MW or more. Existing sites keep their connection agreements; the test applies to a new connection beside them. Whether two sites count as electrically proximate depends on where they connect to the network.

    Suburb

    Under 30MW

    30MW or more

    Eastern Creek, NSW

    DCI SYD-01 (11MW)

    CDC Eastern Creek campus (200MW+)

    Erskine Park, NSW

    Digital Realty SYD11 (17.4MW) and SYD14 (12MW)

    STACK Infrastructure Erskine Park (450MW, planned)

    Macquarie Park, NSW

    Macquarie Data Centres IC2 and IC3 (6MW, 12MW); NEXTDC S1 (16MW)

    Macquarie IC3 Super West (47MW, under construction); NEXTDC S2 (30MW)

    Artarmon, NSW

    NEXTDC S6 (13.5MW)

    NEXTDC S3 (80MW)

    Hume, ACT

    CDC Hume Campus One, H1 to H3 (21MW in total)

    CDC Hume Campus Two, H4 and H5 (51MW in total)

    Derrimut, VIC

    Equinix ME4 (18MW)

    AirTrunk MEL1 (185MW+)

    Source: Certified Strategic directory, November 2026. Figures are operator-reported and mix IT load and total site power; the rule's 30MW test uses nameplate rating.

    Advanced projects keep the old standards until 12 May 2027

    The rule does not change existing connection agreements, though a site that later amends the performance standards in its agreement must meet the new standards for the amendment. A project that lodged a valid application before 12 November, had its negotiated technical requirements accepted and was still waiting on an offer to connect keeps the old standards, but only until 12 May 2027. If it has not signed a connection agreement by then, the new standards apply. Proposals to alter existing plant lodged before 12 November get the same deadline, and a project that held an offer before 12 November stays under the old rules.

    AEMO must publish guidelines by 12 November 2027 setting how these sites model their equipment for network studies. Ausgrid and Endeavour Energy, which run the local networks across much of Sydney, told the commission the reforms bring significant change to a connection process they described as complex, and said clear, practical information would help proponents. The commission published the industry fact sheet in response.

    The next consultation covers registration and how fast AI loads can swing

    The commission opened a second consultation the same day, on a request AEMO lodged on 21 July 2026. The consultation paper asks whether large data centres should register with AEMO, send it real-time readings of their power draw, and limit how fast their demand rises or falls. Its starting point is a limit of 40MW a minute on the mainland and 10MW a minute in Tasmania, with faster ramping open to negotiation where a site can show the grid stays secure. The paper notes that AI data centres can have load profiles that are "periodic, repetitive, and sustained in nature".

    The commission is considering applying registration to existing large sites as well as new ones, and asks whether 30MW is the right line for it. Submissions close on 17 December 2026. A draft determination is due by 1 April 2027. The work sits beside the commission's consultation on what data centres pay for grid upgrades, where submissions closed on 5 November 2026.

    Mid-sized sites and clusters are likely to feel the rule most

    The threshold change falls mainly on new data centres of 30MW to 100MW on local networks; large campuses built for hyperscalers in Australia fell inside the standards under the draft as well. New sites in that band now come under the standards as of right, whereas the draft left the decision to each network.

    The cluster test is likely to matter in suburbs where any new hall would sit beside a large campus, such as Eastern Creek, Macquarie Park and Artarmon. A network there can weigh a new connection against its neighbours as well as on its own size.

    Projects covered by the transition are likely to aim to sign connection agreements before 12 May 2027, because any still unsigned after that date move to the new standards. The consultation paper ties the proposed ramp limits to fast swings in demand, and says AI data centres can have load profiles that are "periodic, repetitive, and sustained in nature". Operators can respond in submissions closing on 17 December 2026.

    What to watch

    The 27 November information session. The AEMC is briefing industry on its data centre work program from 1pm to 3pm AEDT.

    Submissions on registration. Comments on registration, real-time data and ramp limits close on 17 December 2026.

    The 1 April 2027 draft. The commission is due to publish its draft determination on registration, real-time data and ramp limits.

    The end of the grace period on 12 May 2027. Projects covered by the transition that have not signed a connection agreement move to the new standards.

    AEMO's modelling guidelines. The market operator must publish them by 12 November 2027.

    Share this article

    Keep reading the market

    Get The Strategic Brief in your inbox every Thursday.

    The leading Australian data centre and AI infrastructure newsletter.

    One email a week. Unsubscribe in one click.

    Your Next Read

    Latest Headlines

    Interested in reaching this audience? Advertise with us.