Hydro Tasmania says gas would bridge AI data centre supply
By Winston Su, Editor · · Add us as a preferred source on Google

At a glance
Hydro Tasmania would rely on its Tamar Valley gas plant to help power Firmus's AI data centres from 2027 until new wind and solar farms arrive.
Hydro can supply about half the 444MW Firmus wants. The rest depends on the Basslink cable to Victoria and new wind farms.
That supply needs the dams at normal or optimal levels, and in June Hydro was still modelling a dry year.
In June, Hydro did not expect new wind farms before 2030, and the three it had identified will not all come online at once.
A second, unnamed developer has asked Hydro to price 50MW. Hydro expects to decide on Firmus by the end of 2026.
Hydro Tasmania would run its Tamar Valley gas plant to help power Tasmania's AI data centres until new wind and solar farms are built, a period it put at largely 2027 to 2029. Chief executive Rachel Watson and Executive General Manager Strategy and Commercial Erin van Maanen gave that evidence for the state-owned generator to the House of Assembly's inquiry into AI data centres in Hobart on 20 November 2026. Hydro's current modelling indicates "approximately three months of significant gas operation each year" over that period. The Mercury reported from the hearing that Hydro would rely on "significant" gas-fired power for two years to supply an AI data centre while new renewable generation is built.
Australian AI infrastructure company Firmus is building an AI factory at St Leonards in Launceston and has two more planned at Bell Bay and Wesley Vale. Firmus has asked Hydro for a long-term contract covering about 444MW across the three sites, and has committed to support about 2MW of new renewable generation for every 1MW it contracts.
Hydro told Firmus in June it could supply about half of that 444MW, with the other half depending on the Basslink cable to Victoria and new renewable generation, according to a document the ABC obtained under right-to-information laws. Hydro's supply also assumes its dams are at normal or optimal levels.
Hydro can supply about half the 444MW Firmus wants
Watson said in the June document that "the period of greatest focus sits between 2028 and 2030", when the full Firmus load is expected online but before new wind generation is commissioned. For those years, Hydro said it could supply Firmus if its dam levels were normal or optimal, topping up its hydro output with gas from Tamar Valley and imports over Basslink. It was still modelling how much it could supply when dam levels are low or Basslink is constrained.
Tamar Valley makes about 2 per cent of Tasmania's power in a normal year
Hydro's submission to Tasmania's AI data centre inquiry says the Tamar Valley Power Station is 14 per cent of Hydro's installed capacity but supplies about 2 per cent of Tasmania's electricity in a year of average rainfall, against 80 per cent from hydropower and 18 per cent from wind. The station sits at Bell Bay, near Firmus's planned 288MW site, and has five gas turbines with a combined capacity of 386MW. Like the dams, it is dispatchable, so Hydro can turn it up when it needs more supply. In September 2026 it was brought back online to replace lost capacity after fire damaged the 142MW Tungatinah hydro power station at Tarraleah.
Hydro has identified three wind farms to supply Firmus
In the same June document, Hydro said it had identified three planned Tasmanian wind farms that could supply Firmus, each "well advanced in its development approvals and connection agreements", but that the three would compete for construction resources and would not all come online at once.
Firmus wants that generation built in Tasmania. Paul Grzinic, its general energy manager, told the state's energy committee on 20 October 2026 that "all of our energy will be developed and procured on-island in Tasmania". He said Firmus would prefer to underwrite about 1,000MW of new wind farms through Hydro, because a wind farm produces about 40 per cent of its rated output on average.
Marinus Link, the new interconnector to Victoria, also has its first 750MW stage due in 2030, according to Hydro's submission. Hydro says pressures on the system are "materially reduced" once that stage is commissioned.
A second developer has asked Hydro to price 50MW
Hydro confirmed at the hearing that another, unnamed data centre developer has approached it for an energy price, for 50MW, according to a statement from Greens MP Tabatha Badger, the committee's deputy chair. Beyond Firmus, a government document tabled on 8 September 2026 lists six unnamed data centre proposals that could draw between 505MW and 705MW, and TasWater has told the inquiry six developers have sought water supply. The House of Assembly passed a Greens motion on 18 November 2026 calling for a moratorium on new AI data centres, and the government has said it will not enact one.
Hydro expects to decide on the 444MW request by the end of 2026
Hydro says a Firmus deal "could be a good thing" because it may offer more certain long-term revenue, support for new renewable generation and a bigger customer base to share fixed costs such as transmission, according to its Firmus information page. It says it would offer no preferential pricing, subsidies or concessions, and its submission says it expects to finalise its assessment by the end of calendar 2026.
Under one of the two models in Hydro's submission, Firmus would contract directly with new wind and solar developers and Hydro would fill the gaps when output falls short. Under the other, Firmus would contract with Hydro, which would sign with the new generators itself.
Firmus has 104MW under contract for St Leonards, through a three-year retail agreement signed in March 2026 with state-owned Aurora Energy, which Hydro backs with a wholesale agreement. Any new contract would also sit under the state's new expectations for data centre developers, released on 13 November 2026, under which developers are expected to contract new Tasmanian wind, solar or hydro generation and those above 20MW pay into a community fund.
What to watch
The Hydro decision. Hydro expects an outcome on the Firmus request by the end of 2026.
The hearing transcript. The committee publishes transcripts after its hearings, including Hydro's evidence of 20 November 2026 on how much gas it expects to use.
Wesley Vale. Firmus has until 15 December 2026 to lodge a complete major project proposal for its Wesley Vale AI factory.
Marinus Link. The first 750MW stage of the interconnector to Victoria is due in 2030, the earliest Hydro expects new wind farms to be running.
Keep reading the market
Get The Strategic Brief in your inbox every Thursday.
The leading Australian data centre and AI infrastructure newsletter.
Your Next Read

Firmus puts its Tasmanian power need at 444MW in inquiry submission

Firmus wins approval for 26MW AI research lab at Wesley Vale

What Firmus's pulled IPO means for Tasmania and Maas Group
Latest Headlines
Melbourne leads Asia Pacific data centre leasing as approvals slow
23 Nov 2026Southeast Asia steps up data centre oversight under US curbs
22 Nov 2026Australia pitches digital infrastructure to UK pension funds
21 Nov 2026Australia's data centre construction spend to grow fastest
20 Nov 2026Sydney's data centre pipeline sheds four early-stage plans
20 Nov 2026
Interested in reaching this audience? Advertise with us.