NT pitches itself as Australia's data centre gateway to Asia
By Winston Su, Editor · · Add us as a preferred source on Google

At a glance
Trade, Business and Asian Relations Minister Robyn Cahill wants the Territory to become "the data centre capital of the globe", and says her department is engaged with 12 investors.
In Darwin, NEXTDC runs D1 on Ryko Court and DXN runs the 75-rack Secure Data Centre on Harvey Street, which houses the NT Government's backup computing.
NEXTDC's 6MW D2 is due by 31 December 2026 next door to D1, starting with 1.5MW for a contracted subsea cable.
Beetaloo Digital at Weddell and Energy North's Project Ares in the Barkly would each build their own power stations for gigawatt-scale campuses.
Google, Inligo and Vocus each have a new route into Darwin under way or planned, from subsea cables to a fibre link from Brisbane.
The Northern Territory's data centre plans reach a run of milestones between December 2026 and July 2027. NEXTDC is due to finish D2, its second Darwin data centre, by 31 December. The Commonwealth intends to legislate national data centre standards in early 2027. Beetaloo Digital's exclusive hold on a 185-hectare site south of Darwin, where it plans up to two hyperscale campuses, runs to July. Energy North has dropped its June 2028 first-power date for Project Ares, a 1GW campus planned for a Barkly cattle station, while the Territory's environment regulator works through its assessment.
The NT Government has spent 2026 selling data centre developers on its energy resources, land and a short path to Asia. Trade, Business and Asian Relations Minister Robyn Cahill said in July 2026 that she wants to make the Territory "the data centre capital of the globe", and that her department is "actively engaged with 12 investors" on proposed projects. The government markets the Territory as Australia's "key digital gateway to Asia".
Of the projects named publicly by their developers, three are in Darwin's CBD: two operating data centres and NEXTDC's D2, under construction beside them. DCI Data Centers announced a fourth Darwin site in 2021. Two more are gigawatt campuses that would make their own electricity: Beetaloo Digital's at Weddell, about 30km south of Darwin, and Energy North's Project Ares, 683km south.
Darwin's data centres are small sites on the city grid: NEXTDC's D1 is 1MW and D2 will add about 6MW. The Territory's scale would come from two proposed gigawatt campuses that would build their own power stations, the model the NT Government backs.

NEXTDC and DXN run Darwin's operating data centres
NEXTDC added Darwin to its national network of data centres in Australia in August 2024, when it opened D1 at 8 Ryko Court. The NT Government had chosen it through an expression of interest process to build and operate a commercial data centre in the city. NEXTDC lists D1 at 1MW across 3,000 square metres of technical space.
A short walk away on Harvey Street, DXN, an ASX-listed manufacturer and operator of modular data centres, owns the Secure Data Centre. It bought the bunker facility in 2021 for A$4.88 million, when the facility had been operating for 17 years. Its FY26 annual report describes 75 racks of colocation and managed hosting capacity in Darwin. The NT Government's backup data centre runs inside the building: Darwin IT company Area9 won a 10-year contract in 2019 to provide it and engaged Secure Data Centre to house it.

A second NEXTDC data centre in Darwin is due by December
NEXTDC is building D2 next door to D1, at 2-6 Ryko Court in Darwin's CBD. Its development application for the site describes a 6MW data centre. NEXTDC's FY26 results presentation gives it about 6MW of planned power and an initial 1.5MW, with practical completion in the first half of FY27, the six months to 31 December 2026. The same presentation says that first 1.5MW is being built for a "new contracted submarine cable". Once D2 is complete, NEXTDC will run two data centres side by side in Darwin's CBD.
DCI announced an up to 10MW Darwin site in 2021
Data centre operator DCI Data Centers announced in October 2021 that it had secured 2.7 hectares in Darwin Technology Park for DRW01, a Tier III-ready design of up to 10MW subject to development approval. It also took an option to expand the site to 5 hectares. The NT Government also markets serviced land in Darwin to data centre developers at the Wishart Estate Digital Hub.
Google, Inligo and Vocus are adding routes into Darwin
D2's cable contract adds to Darwin's existing and planned links to Asia. Vocus built its Darwin-Jakarta-Singapore Cable to link the city to Singapore, and it joins its Darwin to Port Hedland cable to its Perth to Singapore cable. Google has engaged US cable maker SubCom to build Bosun from Darwin to Christmas Island, with onward connections to Asia, according to its environmental referral.

Singapore-headquartered cable developer Inligo Networks has started building a cable landing station on Conacher Street in The Gardens, near Fannie Bay, for its Asia Connect Cable, which is planned to come ashore in late 2027. On land, Vocus plans a 4,000km fibre route from Brisbane through Townsville to Darwin, due in 2030, and Telstra lists Darwin among the nodes of its Aura network linking the capital cities.
Beetaloo Digital plans up to two hyperscale campuses south of Darwin
The Territory's two largest named projects sit well outside the CBD. Beetaloo Energy, the ASX-listed gas developer formerly called Empire Energy, launched Beetaloo Digital on 22 July 2026, and the NT Government granted it a 12-month exclusive commitment over 185 hectares at Weddell to develop its proposal and seek approvals. The company plans up to two hyperscale campuses and up to 2GW of on-site generation fuelled by Beetaloo Basin gas. The NT Government says the project could attract up to A$40 billion of private investment at full build-out, with up to 5,000 construction jobs and about 350 ongoing roles.
"Beetaloo Digital does not propose to consume power from the Northern Territory grid, we intend to add to it," the company said at launch. Beetaloo Energy's September quarter report lists two non-binding memoranda of understanding signed since: with US energy services company Halliburton on 30 July to assess the gas resource, and with the Australian Gas Infrastructure Group on 24 August to assess a pipeline of about 750km toward Darwin from its Carpentaria Gas Project. The company is talking to prospective consortium partners.
Project Ares moves into a full environmental assessment
Further south, in the Barkly region of the central Territory, developer Energy North plans Project Ares on Murranji Station. It is a 1GW AI data centre campus planned in two phases of about 500MW. It would run off the grid on about 3,000MWp of solar, 16GWh of batteries and up to 1,038MW of dispatchable generation for firming. The Northern Territory Environment Protection Authority (NT EPA) decided on 15 September 2026 that the project needs an environmental impact statement and is consulting the Australian Government before setting what the statement must cover.
Energy North vice president of project development Daniel Hunter told Reuters in early November 2026 that the June 2028 first-power date in its referral "was an indicative schedule at the time of lodgment, and we're no longer working to it". He said later phases would be financed "as the project moves through approvals toward a final investment decision". The project holds Commonwealth Major Project Status, the Australian Government's designation for projects it helps steer through Commonwealth approvals.
Site and developer | Location | Stage and size |
|---|---|---|
D1 Darwin, NEXTDC | 8 Ryko Court, Darwin City | Operating since August 2024, 1MW |
Secure Data Centre, DXN | 27 Harvey Street, Darwin City | Operating, 75 racks |
D2 Darwin, NEXTDC | 2-6 Ryko Court, Darwin City | Under construction, about 6MW, first 1.5MW due by December 2026 |
DRW01, DCI Data Centers | Darwin Technology Park | Announced October 2021, up to 10MW, subject to development approval |
Beetaloo Digital, Beetaloo Energy | Weddell, about 30km south of Darwin | Site exclusivity to July 2027, up to 2GW of on-site generation |
Project Ares, Energy North | Murranji Station, Barkly region | Environmental impact statement required, 1GW of IT capacity |
Source: NEXTDC, DXN, DCI Data Centers, Beetaloo Energy, Energy North, NT Government and NT EPA. Projects with a site named publicly by their developers, to 24 November 2026.
The NT Government backs self-powered campuses
Both gigawatt projects follow the model the NT Government set out in its submission to the Senate inquiry into artificial intelligence and data centres. It backs "dedicated standalone power generation" for large data centres, drawing on the Territory's own energy resources, and argues this would speed development by removing reliance on grid capacity. Projects outside the regulated electricity system, it says, would not affect prices or reliability for existing customers. Mining and Energy Minister Gerard Maley said in early August 2026 that many of the major proponents intend to run off-grid on standalone power.
National Cabinet agreed on 26 August 2026 to develop mandatory standards for data centre energy, water and land use, which the Commonwealth intends to legislate in early 2027. Chief Minister Lia Finocchiaro said after the meeting that national regulation would go ahead "with full recognition that the Territory's position on energy is uniquely different to the other states".
What to watch
D2's completion in Darwin. NEXTDC is due to reach practical completion on D2 by 31 December 2026, the end of its half year.
A Beetaloo Digital consortium. The Weddell exclusivity runs to July 2027. Beetaloo Energy is seeking consortium partners across data centre development, power generation and pipeline infrastructure.
Project Ares' assessment. The NT EPA is finalising the terms of reference for the environmental impact statement. Energy North will then prepare the statement for public review.
National data centre standards. The Commonwealth intends to legislate the standards in early 2027. The NT Government has argued against a mandatory requirement for data centres to fully offset their demand with new renewable generation.
Keep reading the market
Get The Strategic Brief in your inbox every Thursday.
The leading Australian data centre and AI infrastructure newsletter.
Your Next Read

Outback AI data centre drops 2028 start as NT EPA orders EIS

NEXTDC's Scroggie apologises over M3 poles, says he has a power fix

NEXTDC enters trading halt over M3 Melbourne power delay
Latest Headlines
Apprentice ratio proposed for data centre construction
25 Nov 2026350MW Mulwala data centre planned on solar farm land
25 Nov 2026ByteDance plans $15bn data centre in regional Victoria
25 Nov 2026Southern Cross Electrical wins A$120m in data centre and Metro work
24 Nov 2026Hunter Horizon Park data centre pairs 300MW with a battery
24 Nov 2026
Interested in reaching this audience? Advertise with us.