Hunter Horizon Park data centre pairs 300MW with a battery
By Winston Su, Editor · · Add us as a preferred source on Google

At a glance
CABP Group, developer of the Kinross industrial estate, plans Hunter Horizon Park, a 300MW data centre at 343 Masonite Road, Heatherbrae, near Raymond Terrace.
The same site would carry a 100MW solar farm and a 450MW battery holding 900MWh, on about 230 hectares of mostly commercial pine plantation.
That battery is big enough to meet NSW's storage requirement for up to 900MW of contracted renewable generation, nine times the solar farm beside it.
The Hunter's other large data centre plans include AirTrunk at Kurri Kurri, Voltic DC at Warkworth and Akaysha Energy near Denman.
In-person consultation runs at Raymond Terrace on 25 and 26 November 2026, with an online webinar on 9 December.
The developer of Heatherbrae's Kinross industrial estate has proposed a 300MW data centre on a pine plantation on Masonite Road, near Raymond Terrace in the NSW Hunter, with a solar farm and a large battery on the same land. CABP Group's plan, Hunter Horizon Park, surfaced in a Newcastle Herald story on 23 November 2026, which counts it as the Hunter's fourth major data centre proposal, and in-person consultation starts on 25 November.
Under its data centre guidelines, NSW promises an assessment of no more than 75 days in state government hands to projects that meet them, and one of the guidelines asks a data centre to back new renewable power with batteries. Hunter Horizon's 900MWh battery is big enough to meet that storage requirement for up to 900MW of contracted renewable generation, nine times the solar farm planned beside it.
CABP Group plans a 450MW battery beside a 300MW data centre
The company describes the plan as a "self-sufficient precinct" on about 230 hectares of mostly pine plantation at 343 Masonite Road, in the Port Stephens council area. It combines a modular data centre of 300MW of IT load, the power for computing equipment before cooling, with a 100MW solar farm and a 450MW battery holding 900MWh.
CABP Group has held the business name Kinross Business and Industrial Park since September 2000 and is building the estate in stages along the same road, including a 26-lot subdivision that construction firm Daracon started in October 2023. Radio station 2HD reports that CABP Group is the parent of the project company, CABP High Tech Park. The project company is preparing an environmental impact statement and has proposed a community benefit fund. It is targeting cooling that uses less than one gigalitre of water a year.
CABP says the solar farm would serve the data centre's "primary operational requirements" and charge the battery, with surplus energy exported to the grid. Its concept plan marks a 132kV grid connection beside the battery and substation precinct. The company is running grid connection studies with electricity distributor Ausgrid and says the site sits in the Hunter-Central Coast Renewable Energy Zone.
The battery is big enough for NSW's storage measure on up to 900MW of generation
NSW published its Data Centre Guidelines on 17 August 2026, covering what the state expects data centres to fund, including new renewable power and storage. Meeting the guidelines is optional, and a project that skips them keeps the ordinary planning pathway without the 75-day commitment.
The renewable energy measure asks a data centre to sign power purchase and firming agreements of at least ten years with new NSW renewable projects that have not reached a final investment decision. At least 40 per cent of the contracted energy has to come from wind, storage has to equal at least 25 per cent of the contracted generation capacity for four hours, and from the fourth year of operation contracted supply has to match the data centre's annual average demand. The guidelines say on-site or nearby storage provided for demand flexibility can count toward the measure.
Hunter Horizon's 900MWh battery can deliver 225MW for four hours, and 225MW is a quarter of 900MW. So on size it could cover the storage share for up to 900MW of contracted generation, if CABP provides it for demand flexibility. The wind share would have to come from contracts beyond the site, the route AirTrunk is pursuing for its campus at Kurri Kurri.
AirTrunk lines up Hunter wind, solar and batteries for Kurri Kurri
AirTrunk's Kurri Kurri data centre, on the former Hydro Aluminium smelter site at Loxford, has a total power consumption of 550.5MW in its NSW planning application. The application is at the response to submissions stage after its environmental impact statement drew 759 submissions.
The Australian Financial Review reported on 22 September 2026 that Anthropic is in advanced talks to anchor the campus. AirTrunk has exclusivity with renewable developer European Energy Australia over 260MW of solar, up to 350MW of wind and more than 800MWh of batteries elsewhere in the Hunter, and the two are discussing a long-term power purchase agreement. The solar and batteries are due to operate in 2030 and the wind in 2032.
Akaysha and Voltic plan larger campuses further up the valley
Two of the Hunter's other large proposals sit near Denman and at Warkworth, well outside Sydney and Melbourne, where most data centres in Australia operate. Battery developer Akaysha Energy and coal miner Malabar Resources are planning the Mayfield Energy Precinct near Denman, with up to 1GW of IT capacity, a battery of up to 2GW and 8GWh, and a capital cost of up to A$10 billion. Akaysha built the Waratah Super Battery at the former Munmorah power station on the Central Coast, and says Mayfield is at an early feasibility stage, with its environmental impact statement indicatively due in the first half of 2027.

Voltic DC, managed by digital infrastructure developer APDC, plans a 500MW AI training campus with a pathway to more than 1GW. Its 20-hectare brownfield site sits beside the 151MW Redbank Power Station at Warkworth, with access to high-voltage transmission lines and an existing substation. Voltic says Redbank's owner, Verdant Earth Technologies, is pursuing a conversion of the station from coal to biomass, and that the two companies will assess potential power supply arrangements after any restart.
Project and location | Size | Power plan |
|---|---|---|
AirTrunk, Kurri Kurri Data Centre, Loxford | 550.5MW total power consumption | Exclusivity with European Energy over Hunter solar, wind and more than 800MWh of batteries |
Akaysha Energy and Malabar Resources, Mayfield Energy Precinct, near Denman | Up to 1GW of IT capacity | Battery of up to 2GW and 8GWh within the precinct |
Voltic DC, Hunter Valley AI training campus, Warkworth | 500MW, pathway to 1GW+ | Access to transmission and an existing substation beside Redbank; supply from Redbank to be assessed after any restart |
CABP High Tech Park, Hunter Horizon Park, Heatherbrae | 300MW of IT load | 100MW solar farm and 450MW, 900MWh battery on site |
Source: NSW Major Projects portal, AirTrunk, Akaysha Energy, Voltic DC, Newcastle Herald, November 2026.
AirTrunk's figure in the table is the campus's total power consumption, and the other three are IT capacity. Akaysha is assessing a battery alongside the data centre within the Mayfield precinct, while Hunter Horizon would build its battery and a solar farm on the data centre site.
What to watch
Consultation. CABP holds pop-up sessions at Raymond Terrace Marketplace from 11am to 1pm on 25 and 26 November 2026, an information evening at the Sir Francis Drake Motel from 5.30pm on 25 November, and an online webinar from 4pm on 9 December.
The environmental impact statement. CABP is preparing one under the state significant development pathway, and it will document the precinct's total power demand and the battery's role.
Ausgrid. The outcome of CABP's grid connection studies, which set how the precinct would export surplus solar power to the Hunter network.
Kurri Kurri. AirTrunk's response to the 759 submissions on its campus. A planning department letter of 20 November 2026 asks for AirTrunk's added information for its submissions report by 12 January 2027.
Keep reading the market
Get The Strategic Brief in your inbox every Thursday.
The leading Australian data centre and AI infrastructure newsletter.
Your Next Read

AirTrunk lines up 610MW of Hunter renewables for Kurri Kurri

Anthropic is in advanced talks for AirTrunk's Kurri Kurri campus

Mulwala Solar Farm nears grid connection: the Google and AirTrunk hyperscaler PPA explained
Latest Headlines
Southern Cross Electrical wins A$120m in data centre and Metro work
24 Nov 2026NVIDIA reinstates Jensen Huang: what it means for Australia
24 Nov 2026Hydro Tasmania says gas would bridge AI data centre supply
23 Nov 2026Melbourne leads Asia Pacific data centre leasing as approvals slow
23 Nov 2026Southeast Asia steps up data centre oversight under US curbs
22 Nov 2026
Interested in reaching this audience? Advertise with us.