350MW Mulwala data centre planned on solar farm land
By Winston Su, Editor · · Add us as a preferred source on Google

At a glance
Local landowners plan a data centre campus of up to three halls at Mulwala, the NSW town across the Murray River from Yarrawonga.
The completed campus would draw up to 350MW from the grid, and Lambruk estimates about 250MW to 280MW of that would run the computing equipment.
Lambruk says regional network operator Essential Energy has advised it can supply the first hall, and each later hall depends on connection studies and upgrades.
The site is covered by the 2018 approval for the Mulwala Solar Farm, which sells most of its output to AirTrunk under a deal tied to Google.
Data centres are not permitted under the site's current zoning, so Lambruk will seek a planning change, starting with a scoping report it aims to lodge in December 2026.
Landowners at Mulwala, on the NSW bank of the Murray River opposite the Victorian town of Yarrawonga, have published plans for a 350MW data centre campus on the northern edge of town. The proponent is Lambruk Mulwala Futures. Lambruk says the proposal is 100 per cent Australian-owned and backed by local capital. The campus would sit on the property of farmer Douglas Thomas. "I'd like to see this land help Mulwala grow and give young people more reasons to build a future here," Mr Thomas said on the project's website. Lambruk's development manager is Rutherglen-based infrastructure advisory firm Lecroma, which has also invested. Lecroma chief executive Greg Ley says a campus of that size will need a major partner.
The plan adds Mulwala to a growing list of regional NSW data centre sites: Canberra Data Centres (CDC) has proposed a 1.4GW campus at Wagga Wagga, IREN is planning its 900MW Redbank campus near Wagga Wagga, and Sharon AI has bought Visy's closed Ettamogah paper mill at Albury. The Mulwala campus would sit on land covered by the approval for the Mulwala Solar Farm, which sells most of its output to AirTrunk, and would draw power from the same substation that takes the farm's output.

Each data hall would be built once the network can supply it
Lambruk's layout for the 168ha site, which sits west of the railway line beside Mulwala Business Park, includes about 62ha for the data centre campus, 61ha kept for the solar farm and 27ha for future industrial lots. The campus would go up in three stages, with each data hall built only once the network can supply it.
At full build the campus would import no more than 350MW. Lambruk estimates 250MW to 280MW of that would run the computers, with the rest going to cooling and other plant. Land behind a 5m landscaped earth wall is held for a possible fourth hall, which would need more network capacity and its own approval.
Essential Energy can supply the first hall, Lambruk says
The campus would connect to regional network operator Essential Energy's Mulwala 132kV zone substation, about 390m south of the site, through a switchyard and a 30m easement. Lambruk says Essential Energy has advised there is capacity for the first stage, while later stages depend on connection studies and any upgrades they identify.
Ley told the Corowa Free Press that Mulwala's renewable uptake has left "excess energy at the substation", which takes power from several solar projects. Essential Energy's Distribution Annual Planning Report, dated 22 December 2025, lists a 5MW solar generator and a 4.85MW solar-and-battery plant on the Mulwala 22kV network. The 31MW Mulwala Solar Farm has since connected through a 22kV switching station and a 2km underground cable, ESD News reported.
The same report shows the substation is fed at 132kV by Essential Energy lines running between the Union Road substation at Albury and NSW transmission owner Transgrid's Finley substation. To ease the campus's draw on that network, Lambruk plans batteries and flexible computing load that would let the campus cut its grid draw by about a quarter of average load for up to two hours during grid stress. Lambruk says the NSW Data Centre Guidelines require that capability.
The solar farm's 2018 approval covers the campus land
The NSW planning department approved the Mulwala Solar Farm (SSD-9039) on 18 December 2018, and Lambruk says that approval allows 80MW, of which about 31MW is built. Where the two projects overlap, Lambruk would seek to change or surrender that part of the solar approval so only one consent covers the land. It would also use the solar farm's studies as a base for its own work on soils, groundwater, roads and views.
Danish renewables developer European Energy owns the built plant, which reached full output in November 2026. AirTrunk's offtake is part of a 2023 power purchase agreement with Google, under which renewable certificates are matched to Google's consumption. European Energy plans to add a battery at the site in 2027, which PV Tech reports at 25MW and 100MWh.
Lambruk plans to run the zoning change alongside state approval
The campus land is zoned RU1 Primary Production and R2 Low Density Residential, and neither zone permits a data centre. Lambruk lists two ways forward: rezoning the campus land to an employment or industrial zone, or adding a data centre as an additional permitted use on the site. It is seeking advice from the department and will ask the local Federation Council to support the change.
The campus itself would be assessed by the state as State Significant Development, with an environmental impact statement, and Lambruk says the zoning change can run alongside that assessment. CDC is taking a similar path at Wagga Wagga, seeking a change to the local plan alongside its own State Significant Development application.
Defence's munitions factory next door will shape the hazard studies
Across Tocumwal Road to the south-west of the campus sits the Commonwealth-owned Mulwala facility, which the Australian National Audit Office describes as "the sole remaining manufacturing site of military propellants and high explosives in Australia". Thales Australia subsidiary Australian Munitions operates it, and Lambruk's hazards study will assess separation distances with the Department of Defence and the operator.
Ley told the Corowa Free Press that night-time noise is the main constraint for the campus. Lambruk says "most homes are more than 1km from the nearest proposed data hall". Its mapping shows three dwellings within 500m of the nearest data hall and 52 between 1km and 1.5km, with none in between.
On water, Lambruk says cooling would run in a closed loop filled from the landowner's bore, with no town water proposed for cooling. Part of the site will stay free of buildings because of its Aboriginal cultural heritage values, and a new assessment with Aboriginal knowledge holders will shape the final layout.
What to watch
The scoping report. Lambruk targets December 2026 to lodge it with the department, alongside a first community briefing in Mulwala.
The study requirements. The department will then issue the Secretary's Environmental Assessment Requirements, the list of studies the application must cover. For projects that meet its data centre principles, NSW aims to issue them within two months.
The environmental impact statement. Lambruk targets lodgement in March or April 2027, with the plan open for public comment by the middle of that year, when Victorian residents can also make submissions.
A development partner. Lambruk says it will seek a major development partner at a later stage.
Essential Energy's planning report. Expected by the end of December 2026, it will update the generation connected at Mulwala.
Keep reading the market
Get The Strategic Brief in your inbox every Thursday.
The leading Australian data centre and AI infrastructure newsletter.
Your Next Read

Mulwala Solar Farm nears grid connection: the Google and AirTrunk hyperscaler PPA explained

Hunter Horizon Park data centre pairs 300MW with a battery

Microsoft wants its renewables to count under data centre rules
Latest Headlines
ByteDance plans $15bn data centre in regional Victoria
25 Nov 2026Southern Cross Electrical wins A$120m in data centre and Metro work
24 Nov 2026NVIDIA reinstates Jensen Huang: what it means for Australia
24 Nov 2026Hydro Tasmania says gas would bridge AI data centre supply
23 Nov 2026Melbourne leads Asia Pacific data centre leasing as approvals slow
23 Nov 2026
Interested in reaching this audience? Advertise with us.